NM ERFO FS SNTFE 2022-1(1) El Porvenir Bridge

Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF25B000001
Agency
Responses due
Not on record
Set-aside
Total Small Business

Opportunity facts

Place of performance
Las Vegas, New Mexico, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Transportation Federal Highway Administration is seeking to procure the construction of a replacement bridge for the El Porvenir Bridge in the Santa Fe National Forest, which was destroyed by the Hermits Peak/Calf Canyon fire in April 2022. The project includes the installation of a new 97-foot prefabricated steel bridge with a 16-foot width, as well as the removal of an existing low water crossing and realignment of the surrounding road. The anticipated advertisement date is October 2024 with an award date of December 2024, and construction is expected to take place between May 2025 and October 2025.

This opportunity is set aside for small businesses, and the estimated cost range for the project is between $2,000,000 and $5,000,000. The principal work items include prefabricated steel bridge, structural concrete, drilled shafts, and embankment construction. There are some special considerations, such as the need to maintain access to a nearby private youth camp and restrictions on full closures during certain months.

Notice text

PROJECT NUMBER:  NM ERFO FS SNTFE 2022-1(1)

PROJECT NAME:  EL PORVENIR BRIDGE

PROJECT DESCRIPTION:  The purpose of this project is to replace the previous bridge which was destroyed in the Hermits Peak/ Calf Canyon fire in April 2022. The bridge is located in the Santa Fe National Forest, approximately 17-miles northwest of Las Vegas, NM. The project is considered 4R and located in Mountainous terrain.

SCOPE OF THE WORK:  The proposed improvements include a new bridge west of the previously destroyed structure. The replacement bridge is planned to be a prefabricated steel structure with a span of 97 feet and a width of 16 feet. The bridge will be founded on drilled shafts with a structural metal decking and reinforced concrete topper. In addition, the scope includes removal of an existing low water crossing, which is serving as a temporary diversion for traffic along the route, and obliteration of a portion of the existing road. Embankment work will be required for the realignment of the aggregate surfaced road.

PRINCIPAL WORK ITEMS:

Prefabricated Steel Bridge: LPSM

Structural Concrete: 84 CUYD

Drilled Shafts, 24 Inch Diameter: 103 LNFT

Embankment Construction:  3,000 CUYD

ANTICIPATED SCHEDULE:  The anticipated advertisement date is October 2024 with an award date of December 2024. Physical construction activities at the site are anticipated to occur between May 2025 and October 2025.

ESTIMATED COST RANGE:  The proposed project is estimated at a cost between $2,000,000 and $5,000,000.

MISCELLANEOUS: There is a private youth camp north of the bridge, access will need to be maintained through an existing low water crossing. Full closures for construction related activities may not occur May 15 through July 15. Use of the USFS campground north of the bridge is allowed. The existing low water crossing may be used and must be maintained throughout construction.

Notice history

Notice Type Posted
NM ERFO FS SNTFE 2022-1(1) El Porvenir Bridge Award Award Notice
NM ERFO FS SNTFE 2022-1(1) El Porvenir Bridge Latest solicitation Solicitation
This notice Pre-Solicitation
NM ERFO FS SNTFE 2022-1(1) El Porvenir Bridge Original Pre-Solicitation