NM BR AAO EL vado heron & EL vado road rehab

Special Notice Posted

Not the latest version. See the latest solicitation from .

Solicitation number
6982AF25B000003
Agency
Set-aside
Total Small Business

Opportunity facts

Place of performance
Tierra Amarilla, New Mexico, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Federal Highway Administration (FHWA) has issued a Special Notice for a road and parking lot rehabilitation project in New Mexico's El Vado and Heron State Parks. The project involves a total small business set-aside contract for comprehensive infrastructure improvements across approximately 5.23 miles of roadway. Specifically, the project will target State Park Road 5001 in El Vado State Park and access roads within Heron Lake State Park. The contract opportunity has been carefully consolidated to maximize procurement efficiency, with the Senior Procurement Executive approving the consolidation on March 6, 2025. The estimated project value ranges between $5,000,000 and $10,000,000, with an anticipated advertisement in March 2025.

The primary objective of this Special Notice is to notify potential small business contractors about an upcoming roadway rehabilitation project with specific technical requirements. Eligible contractors must be classified as small businesses and capable of executing full depth reclamation (FDR) work, which includes processing 78,000 square yards of roadway, installing 13,000 tons of asphalt concrete pavement, and performing auxiliary improvements like pavement markings, sidewalk construction, and culvert cleaning. The project is divided into a main schedule (Schedule A) focusing on El Vado State Park and an optional scope (Option X) covering Heron Lake State Park's access roads and parking lots. Key project deadlines include a planned construction start in June 2025 and completion by September 2025. Contractors interested in this opportunity should carefully review the technical specifications and prepare comprehensive proposals that demonstrate capability in state park infrastructure rehabilitation.

Notice text

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

THIS NOTICE IS BEING ISSUED TO NOTIFY THE PUBLIC OF A NECESSARY AND JUSTIFIED CONSOLIDATION OF CONTRACT REQUIREMENTS FOR THIS PROJECT.

The Agency has determined that consolidation is justified and necessary in accordance with FAR 7.107-2 (a). The Senor Procurement Executive of FHWA signed off on the use of consolidation for this project on 3/6/2025. The benefits of the consolidated acquisition substantially exceed the benefits that would be derived from alternative contracting approaches.

Please see the attached approved determination.

This project will be advertised a TOTAL SMALL BUSINESS SET ASIDE.

Project Details: NM BR AAO EL VADO Heron & El Vado Road Rehabilitation

The proposed project is to rehabilitate the surfacing and improve parking lot operations. This project is being developed with a main schedule (Schedule A) and an option (Option X). Schedule A consists of the work associated with State Park Road 5001 located in El Vado State Park. Option X consists of the work associated with the access roads and parking lots located primarily within Heron Lake State Park.

This project includes full depth reclamation (FDR) of 5.23 total miles of asphalt roadway, which includes 4.61 miles along State Park Road 5001 in the El Vado State Park and 0.62 mile along the Willow Creek Boat Ramp Access Road in the Heron Lake State Park. FDR will be completed for three existing paved parking lots:

· Heron State Park Visitors Center Parking Lot, Heron Lake State Park

· Willow Creek Boat Ramp Parking Lot, Heron Lake State Park

· Ridge Rock Parking Lot and adjacent access road, Heron Lake State Park.

Additionally, an existing gravel parking located within El Vado State Park will be paved.

Curb removal, new sidewalk, signing, pavement markings, and minor drainage improvements, primarily culvert cleaning, will also be part of the project.

PRINCIPAL WORK ITEMS: Approximate quantities of principal work items include:

  • 78,000 square yards of Full Depth Reclamation with Cement, 4-inch depth
  • 13,000 ton of Asphalt Concrete Pavement
  • 75 ton of Prime Coat, Method 1
  • 55 ton of Fog Seal
  • 33 miles of Pavement Markings, Type B, Solid
  • 500 cubic yards of Roadway Excavation
  • 2,100 ton of Roadway Aggregate, Method 2
  • 60 square yards of Sidewalk, Concrete
  • 15 Cleaning Culvert in Place

It is anticipated this project will be advertised in March 2025 and be under construction June 2025 with project completion date of September 2025.

The estimated price range of the project work is between $5,000,000 and $10,000,000.

Files

Notice history

Notice Type Posted
NM BR AAO EL vado heron & EL vado road rehab Latest solicitation Solicitation
NM BR AAO EL vado heron & EL vado road rehab Pre-Solicitation
This notice Original Special Notice

Similar open opportunities

Opportunity Agency Set-aside Responses due
Access Road Repair National Elk Refuge NAICS 237310 — Total Small Business
Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1) New York, United States · NAICS 237310 Federal Highway Administration Total Small Business
Acadia National Park Maine, United States · NAICS 237310 Federal Highway Administration Total Small Business
New Mexico Forest Engineering and Road Maintenance (FERM) Santa Fe, New Mexico 87501, United States · NAICS 237310 Forest Service Total Small Business
OK FW TSM 10(1) NFH Entrance Road and Parking Improvements Tishomingo, Oklahoma 73460, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors