NIWTP Biosolids Sludge Dryer Alternative Building D/B

Closed Solicitation Posted

Solicitation number
191BWC26R0010
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Rio Rico, Arizona 85648, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The International Boundary and Water Commission (USIBWC) seeks design and construction of a Sludge Dryer Building at the Nogales International Wastewater Treatment Plant under design-build contract, with proposals due August 21, 2026, at 3 p.m. MST and questions due August 3, 2026. The government anticipates a small business set-aside, subject to market research results.

Place of performance is Rio Rico, Santa Cruz County, Arizona (coordinates 31°26'56.58"N, 110°57'49.33"W). The contract is firm fixed price with a 365-calendar-day period of performance following Notice to Proceed and an estimated magnitude between one million and five million dollars. The project comprises two phases: Phase 1 design includes site investigation, surveying, geotechnical investigations, and production of construction documents with submittals at 60%, 90%, and 100% milestones; Phase 2 construction includes site preparation, demolition of existing belt filter presses and polymer systems, relocation of an approximately 5,200-square-foot metal shed, and construction of a minimum 9,408-square-foot two-story prefabricated metal building with installation of all dewatering and drying equipment, utilities, IT/SCADA instrumentation, and commissioning to deliver a fully operational, turn-key facility.

The Design-Builder must coordinate with Equipment Contractor Shincci-USA (Contract 191BWC25C0102), obtain all federal, state, and local permits including AZPDES Construction Activity General Permit, and comply with Davis-Bacon wage requirements. Work is restricted to USIBWC right-of-way operating hours (7:30 a.m. to 4 p.m. MST, Monday through Friday). Mobilization must begin within 60 days of Construction NTP. The NAICS code is 236220, Commercial and Institutional Building Construction, with a small business size standard of 45 million dollars. Small business subcontracting plan goals include 23 percent to small businesses, 5 percent to women-owned small businesses, 5 percent to socially disadvantaged small businesses, 3 percent to service-disabled veteran-owned small businesses, and 3 percent to HUBZone small businesses. Bid guarantee, performance bond, and payment bond requirements, along with insurance coverage minimums, apply. A mandatory site visit occurred July 24, 2026.

Notice text

7 versions

Update #7 · Latest ·

Note: The Government has determined it is in its best interest to cancel the current procurement.

------------------------------------------------------------------------------------

See Revised SOW

-------------------------------------------------------------------------------------

Note: Due date for proposals is extended to August 21, 2026. Due date for questions is extended to August 3, 2026. The 3PM deadline remains the same.

-------------------------------------------------------------------------------------

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. Work as noted in the SOW:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #6 ·

Note: See Revised SOW

-------------------------------------------------------------------------------------

Note: Due date for proposals is extended to August 21, 2026. Due date for questions is extended to August 3, 2026. The 3PM deadline remains the same.

-------------------------------------------------------------------------------------

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. Work as noted in the SOW:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #5 ·

Note: See revised SOW attached.

-------------------------------------------------------------------------------------

Note: Due date for proposals is extended to August 21, 2026. Due date for questions is extended to August 3, 2026. The 3PM deadline remains the same.

-------------------------------------------------------------------------------------

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. Work as noted in the SOW:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #4 ·

Note: Due date for proposals is extended to August 21, 2026. Due date for questions is extended to August 3, 2026. The 3PM deadline remains the same.

-------------------------------------------------------------------------------------

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. Work as noted in the SOW:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #3 ·

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. Work as noted in the SOW:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #2 ·

Note: Time for site visited has been corrected to 10AM Arizona Time.

--------------------------------------------------------------------------------------

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. work shall include work under a Based Bid and Two Options:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 10 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • Magnitude is between $1 million and $5 million.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 10AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Update #1 ·

The USIBWC is issuing a Solicitation (negotiated) for the design and construction (design-build) of the Sludge Dryer Building within the USIBWC’s Nogales International Wastewater Treatment Plant Project, in Rio Rico, Santa Cruz County, Arizona.  This new building shall house the sludge dryer purchased for the plant.

  1. Description of the Work:
  2. work shall include work under a Based Bid and Two Options:
  • The project includes:
  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.
  • The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.
  • 2. Project Location
  • Nogales International Wastewater Treatment Plant
    Santa Cruz County, Arizona
    (31°26'56.58"N, 110°57'49.33"W)
  • 3. Procurement Approach
  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.
  • 4. Scope of Work Highlights
  • Phase 1: Design
    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction
    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:
    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.
  • 5. Submission Requirements (When Solicitation is Issued)
  • Interested offerors will be required to submit:
  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.
  • NDA for Site visit
  • 6. Anticipated Timeline
  • Solicitation Release:  16, 2026
  • Site Visit: July 24, 2026 at 9 AM Local. An NDA is required.
  • Questions due: July 29, 2026 at 3 PM MDT.
  • Proposal Due Date: August 14, 2026 at 3PM MDT.
  • 7. Additional Information
  • This notice is  a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

A site visit is scheduled for July 24, 2026, at 9AM local time. Names of individuals who plan to attend along with an IBWC Form 358 Non-Discloser Agreement (NDA) shall be furnished before 3:00 PM MDT (CO’s local time) on Wednesday, July 22, 2026, by email submission to seone.jones@ibwc.gov.  PPE will be required for this site visit (hard hat, safety shoes and vest). IBWC will not provide PPE. A maximum of 2 per company will be allowed. Vendors must check in with a valid ID at the administration building and let them know they are attending a site visit/walk through. All visitors must be escorted by IBWC personnel.

Photos/videos will be allowed with some restrictions. No photos of gates, fences, security features such as cameras, access points or IBWC personnel are allowed on this site visit. Only photos/video of the current sludge drying equipment will be allowed. An NDA (IBWC_Form_358_Nondisclosure_Agreement - NIWTP Biosolids Sludge Dryer Alternative Building D/B.pdf) will need to be completed prior to the site visit. Potential bidders can complete an NDA at the Pre-Proposal Conference/Site Visit.

All work is proposed to be completed within three hundred and sixty (365) calendar days after the Notice to Proceed. 

The time for completion of final paperwork is included in the three hundred and sixty (365) calendar days.  The time stated for completion shall include final cleanup of the premises.  The final design and construction Contract durations will be negotiated with Offerors during the Phase Two technical proposal evaluations.

The Solicitation will be issued pursuant to FAR Subpart 36.3 - Two-Phase Design-Build Selection Procedures.  Phase One shall include evaluation of technical qualifications and capability to perform and Phase Two shall include evaluation of technical proposal and price.

Prospective bidders shall be registered in the System for Award Management (SAM) with an active Unique Entity Indentifier (UEI) in order to be eligible to receive an award from solicitation and have the NAICS code listed above under Reps & Certs. For more information, visit the website at https://www.sam.gov.

Notification of any changes or amendments to the Solicitation will be issued only at https://www.sam.gov. It is the prospective bidder's responsibility to check the website daily for any updates, amendments or any additional information. The Government will not be held responsible for any information a prospective bidder does not receive once the information is issued on the Internet.

All responsible sources must submit a bid to be considered by the Agency.

Attachment

191BWC26R0010.pdf 

SOW NIWTP Biosolids Sludge Dryer Alternative Building DB.pdf 

IBWC Form 358 Nondisclosure Agreement - CUI.pdf 

RRFTP-0027- EQUIP. DIST.& DETAILED LAYOUTS-2026.06.07.pdf 

2006 Geotech Report - MLE Improvements.pdf 

AZ0025607_NIWTP_Final_Permit_Red.pdf 

Nogales_Asbestos_and_Lead-Paint_Survey.pdf 

NIWTP_Upgrade-Expansion_EA.pdf 

NIWTP Location Maps.pdf 

NIWTP_Upgrade-Expansion_FONSI.pdf 

Files

Show all 14

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
NIWTP Biosolids Sludge Dryer Alternative Building D/B Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
GRCA 257282 - Replace Wastewater Plant at South Ri Grand Canyon, Arizona, United States · NAICS 221320 National Office No set-aside
Operations and Maintenance (O&M) Services for the SBIWTP San Ysidro, California 92173, United States · NAICS 221320 International Boundary and Water Commission U.S.-Mexico No set-aside
Turnout Buildings NAICS 237110 Bureau of Reclamation No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity