About this opportunity

The International Boundary and Water Commission (IBWC) intends to issue a Request for Proposal for a design-build contract to construct a new building at the Nogales International Wastewater Treatment Plant in Santa Cruz County, Arizona, with a response deadline of July 16, 2026. The Government anticipates a small business set-aside, subject to market research results.

The facility will house advanced sludge dewatering and drying equipment as part of NIWTP's biosolids management upgrade. Scope includes design and construction of the new building, demolition of existing belt filter presses and polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers), and relocation of an existing three-sided metal structure. The contractor will execute all associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, turn-key facility with water, sanitary sewer, communications, electrical, and fire protection systems ready for immediate use.

The contract structure is firm fixed price with a period of performance of 365 calendar days after Notice to Proceed. Design work includes site investigation, surveying, geotechnical investigations, and preparation of construction documents and technical specifications with coordination of stakeholder and regulatory agency requirements. The project location is Santa Cruz County, Arizona.

Notice text

Pre-Solicitation Notice

The USIBWC intends to issue a Request for Proposal (RFP) for a design-build contract to construct a new building at the Nogales International Wastewater Treatment Plant (NIWTP) in Santa Cruz County, Arizona. The new facility will house advanced sludge dewatering and drying equipment, including polymer equipment, as part of the NIWTP’s biosolids management upgrade.

The project includes:

  • Design and construction of a new building to accommodate the sludge dryer system and associated equipment.
  • Demolition of the existing belt filter presses and related polymer system components (excluding concrete foundations, overhead structure, and electrical motor control centers).
  • Relocation of an existing three-sided metal structure.
  • All associated site work, utilities, permitting, and commissioning to deliver a fully operational, code-compliant, and ready-to-use facility.

The final product shall be a fully commissioned, turn-key building with all required utilities (water, sanitary sewer, communications, electrical, fire protection, etc.) and site improvements, ready for immediate use upon completion.

2. Project Location

Nogales International Wastewater Treatment Plant
Santa Cruz County, Arizona
(31°26'56.58"N, 110°57'49.33"W)

3. Procurement Approach

  • Type: Design-Build (DB)
  • Contract Structure: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (NTP)
  • Set-Aside: The Government anticipates a small business set-aside, subject to market research results.

4. Scope of Work Highlights

  • Phase 1: Design

    • Site investigation, surveying, geotechnical investigations, and design development.
    • Preparation of construction documents, technical specifications, and all required reports.
    • Coordination with stakeholders and regulatory agencies.
  • Phase 2: Construction

    • Site preparation, demolition, and relocation activities.
    • Construction of the new sludge dryer building and installation of all required systems.
    • Quality control testing, commissioning, and project closeout.
  • Compliance:

    • All work must comply with federal, state, and local codes, including NEPA, OSHA, ADA/ABAAS, and applicable environmental and safety regulations.
    • The contractor is responsible for all required permits and coordination with utility providers.

5. Submission Requirements (When Solicitation is Issued)

Interested offerors will be required to submit:

  • Qualifications and relevant experience with similar design-build projects.
  • Technical approach and project management plan.
  • Past performance information.
  • Price proposal.

6. Anticipated Timeline

  • Pre-solicitation Notice: June 2026
  • Solicitation Release: On or about July 16, 2026
  • Site Visit: To be announced in the solicitation
  • Proposal Due Date: Approximately 30 days after solicitation release

7. Additional Information

  • This notice is not a request for proposals. The solicitation, specifications, and drawings will be made available on SAM.gov.
  • All interested parties are encouraged to monitor SAM.gov for updates.
  • Questions regarding this notice may be submitted via email to the Contracting Officer listed in the forthcoming solicitation.

Notice history

Notice Type Posted
NIWTP Biosolids Sludge Dryer Alternative Building D/B Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
GRCA 257282 - Replace Wastewater Plant at South Ri Grand Canyon, Arizona, United States · NAICS 221320 National Office No set-aside
GRCA 257282 - Replace South Rim Wastewater Treatment Plant, Grand Canyon, AZ NAICS 221320 National Office No set-aside
Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant Upgrades Oklahoma City, Oklahoma 73169, United States · NAICS 237110 Franchise Acquisition Servies Total Small Business
SOLICITATION NOTICE DESIGN-BUILD TO BUDGET (DB2B) Airborne Equipment Parachute Repair Shop, Yuma Proving Ground, Yuma, Arizona Yuma Proving Ground (YPG) in Yuma, Arizona · NAICS 236220 ENDIST Los Angeles Total Small Business
Operations and Maintenance (O&M) Services for the SBIWTP San Ysidro, California 92173, United States · NAICS 221320 International Boundary and Water Commission U.S.-Mexico No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity