About this opportunity

The National Institute of Standards and Technology (NIST) is soliciting proposals for a firm fixed-price contract to replace the Thermal Column Tank (TCT) at its National Bureau of Standards Reactor (NBSR) facility in Gaithersburg, Maryland. The selected contractor must supply all labor, materials, tools and procedures to remove the existing TCT, which is leaking, and install a replacement tank provided by NIST. Proposals will be evaluated based on technical approach, experience, past performance, and price. The deadline for questions is July 14, 2023 and final proposals are due by July 28, 2023.

There is no set-aside designation for this procurement. The NAICS code is 541330 for Engineering Services and the PSC code is not specified. The replacement work is to be completed within 18 months of award at the NBSR facility in Gaithersburg, Maryland. Key deliverables for the contractor include engineered tooling designs, removal and installation procedures, shielding calculations, and reports. The TCT weighs approximately 2,500 pounds and the replacement work will take place while minimizing radiation exposure for personnel within the reactor facility.

Notice text

6 versions

Update #6 · Latest ·

7/11/23 Update: See attached Amendment 05 1333ND23QNB680268 for additional questions and answers received.

6/29/23 Update: The Date Offers Due is extended to July 28, 2023. Also, see attached Amendment 04 1333ND23QNB680268 for questions and answers, and updated Attachment A SOW as of Amendment 04.

6/9/23 Update: See attached Amendment 03 1333ND23QNB680268 for details on question and offer due dates extensions, and other questions and answers received thus far.

6/1/23 Update: See attached Amendment 02 1333ND23QNB680268 for additional questions and answers received.

5/18/23 Update: See attached Amendment 01 1333ND23QNB680268 for details on question and offer due dates extensions, site visit RSVP instructions, and other questions and answers received thus far.

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Update #5 ·

6/29/23 Update: The Date Offers Due is extended to July 28, 2023. Also, see attached Amendment 04 1333ND23QNB680268 for questions and answers, and updated Attachment A SOW as of Amendment 04.

6/9/23 Update: See attached Amendment 03 1333ND23QNB680268 for details on question and offer due dates extensions, and other questions and answers received thus far.

6/1/23 Update: See attached Amendment 02 1333ND23QNB680268 for additional questions and answers received.

5/18/23 Update: See attached Amendment 01 1333ND23QNB680268 for details on question and offer due dates extensions, site visit RSVP instructions, and other questions and answers received thus far.

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Update #4 ·

6/9/23 Update: See attached Amendment 03 1333ND23QNB680268 for details on question and offer due dates extensions, and other questions and answers received thus far.

6/1/23 Update: See attached Amendment 02 1333ND23QNB680268 for additional questions and answers received.

5/18/23 Update: See attached Amendment 01 1333ND23QNB680268 for details on question and offer due dates extensions, site visit RSVP instructions, and other questions and answers received thus far.

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Update #3 ·

6/1/23 Update: See attached Amendment 02 333ND23QNB680268 for additional questions and answers received.

5/18/23 Update: See attached Amendment 01 333ND23QNB680268 for details on question and offer due dates extensions, site visit RSVP instructions, and other questions and answers received thus far.

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Update #2 ·

5/18/23 Update: See attached Amendment 01 333ND23QNB680268 for details on question and offer due dates extensions, site visit RSVP instructions, and other questions and answers received thus far.

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Update #1 ·

The National Institutes of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW Test Reactor. This reactor is known by and licensed under the initialism NBSR, which stands for National Bureau of Standards (NBS) Reactor. NBS changed its name to NIST in 1988.

The NIST requires a contractor to supply all labor and materials to prepare for and execute the replacement of the NBSR Thermal Column Tank (TCT) with a new NIST supplied TCT at their Gaithersburg, Maryland campus. Please see attached Combined Synopsis/Solicitaiton 1333ND23QNB680268 and Attachments A-C for full details.

Files

Notice history

Notice Type Posted
Award Notice: NIST NBSR Thermal Column Tank (TCT) Replacement Award Award Notice
This notice Latest solicitation Solicitation
Sources Sought Notice - Thermal Column Tank (TCT) Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity