NEW ARSR HVAC Replacement

Closed Solicitation Posted

Solicitation number
697DCK-25-R-00318
Agency
Southwestern Region Federal Aviation Administration, Department of Transportation
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238220 Plumbing, Heating, and Air-Conditioning Contractors
PSC
Z1BC Maintenance Of Radar And Navigational Facilities
Place of performance
Pearl River, Louisiana, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Federal Aviation Administration (FAA) Eastern Acquisitions is soliciting proposals for a comprehensive HVAC replacement project at the New Air Surveillance Radar (NEW ARSR) facility in Pearl River (Slidell), Louisiana. The project involves removing and disposing of four existing HVAC units along with associated ductwork, air handlers, controls, and related components, then installing two new 20-ton packaged HVAC units, two V-PAC wall-mounted systems, HVAC controls, and all associated work. Contractors must demonstrate relevant experience by providing details of three similar contracts completed within the past five years, and the FAA will use a Lowest Priced Technically Acceptable (LPTA) source selection process to evaluate proposals based on experience and technical comprehensiveness. An optional site visit is scheduled for June 17, 2025, at 9:00 AM, with advance notice required by June 13, 2025. All questions must be submitted by June 24, 2025, at 2:00 PM EDT, and final proposals are due July 8, 2025, at 3:00 PM EDT via email to the designated contracting officers.

This procurement is designated as a total small business set-aside under NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Contractors) with average annual receipts not exceeding $19 million. No incumbent contractor information was provided in the solicitation documents. The estimated contract value ranges between $250,000 and $500,000, structured as a firm fixed-price contract with a performance period of approximately 60 calendar days. The work must be carefully coordinated to avoid disrupting the 24/7 operational radar facility, requiring installation of specific equipment including Trane Precedent 20-ton units with R-410a refrigerant and ductwork meeting SMACNA standards. All work will be performed at the Pearl River facility located at coordinates 30°20'53.5"N 89°46'46.1"W in Slidell, Louisiana, with contractors required to maintain current registration in the System for Award Management (SAM) database and demonstrate adequate bonding capacity and insurance coverage.

Notice text

2 versions

Update #2 · Latest ·

06/30/2025 – Requests For Information (RFIs)

An addition to Solicitation 697DCK-25-R-00318 has been issued.

The purpose of the addition is to provide responses to Requests for Information (RFIs) regarding the subject matter project.  A total of three (3) documents have been added, including one (1) document that contains all the RFIs and two (2) attachments.  All the RFI documents have "RFI" in the title. 

The proposal/bid due date of July 8, 2025; 3PM ET remains unchanged as does all other terms and conditions.

**********

The Federal Aviation Administration (FAA), Eastern Acquisitions-AAQ-570, College Park, GA, is issuing Screening Information Request (SIR) Number 697DCK-25-R-00318, NEW HVAC Replacement, Pearl River (Slidell), LA, as detailed in the Statement of Work (SOW) attached to the Solicitation in accordance with the Acquisition Management System (AMS) 3.2.2.2 Policy as supplemented with additional information included in this notice.

The selected Contractor will remove and dispose of the existing four (4) HVAC units and associated ductwork, air handler, controls and other related components.  The Contractor will also provide and install two (2) new 20–ton packaged HVAC units with associated ductwork, two (2) V-PAC wall-mounted systems, HVAC controls, and all associated work and components.

The FAA contemplates award of a Firm Fixed Price Contract as a result of this solicitation.
This requirement is set-aside and offered to all small business concerns. 
The NAICS code for this acquisition is 238220 – Plumbing, Heating, and Air Conditioning Contractors - $19 Million.
The estimated cost magnitude for this project is between $250,000 and $500,000.
Projected Period of Performance for this project is approximately 60 calendar days.

All interested sources should first attempt to download the attached SIR document(s).  If downloading is not possible, all requests for copies of the SIR document(s) must be made in writing to the attention of Marc Lemay, Contracting Officer (AAQ-570), via e-mail at Marc.Lemay@faa.gov and Suzanne.T-CTR.Huggins@faa.gov
NOTE: Electronic submission is preferred. The electronic submission should be in either Microsoft WORD format or portable document format (PDF), not in a zipped format. Please note that the FAA e-mail server restricts file size to 10MB per email message, therefore, responses may have to be submitted in more than one e-mail to be received.

There is an optional site visit on June 17, 2025, at 9:00am.  This is the only site visit that will be scheduled for the anticipated project; and no individual site visits will be permitted. 

Meeting point:  30°20'53.5"N 89°46'46.1"W  
Pearl River (Slidell), LA 70452 
http://maps.google.com/maps?q=30.34818%2C-89.77947

To attend the site visit, advanced notice via Marc.Lemay@faa.gov and Suzanne.T-CTR.Huggins@faa.gov is required.  Note: The site visit will be canceled without notice, if no notices of attendance are received by June 13, 2025, at 3:00pm ET.

All Questions/Requests for Information (RFI) must be emailed to Marc.Lemay@faa.gov no later than June 24, 2025; 2:00pm Eastern Daylight Time (EDT) to allow sufficient time to respond.   TELEPHONE INQUIRIES WILL NOT BE ACCEPTED.

No questions concerning the project will be answered during the site visit unless the Contracting Officer or the Contracting Officer's Representative is present at the site visit: however, no changes are made to the SIR unless a written amendment is issued. The FAA assumes no responsibility for any conclusions or interpretations made by the contractor based on the information received by any means other than in writing from the Contracting Officer. The FAA does not assume responsibility for any understanding reached or representation made concerning conditions, which can affect the work, by any of its officers or agents before the execution of this contract, unless that understanding, or representation is expressly stated in the contract.
 
Potential offerors should note that the FAA reserves the right to communicate with one or more offerors at any time during the solicitation process. Proposals must be received by email no later than July 8, 2025; 3:00 PM EDT to marc.lemay@faa.gov and suzanne.t-ctr.huggins@faa.gov

When responding to this Screening Information Request/Request for Proposal (SIR/RFP), each offeror is required to submit a technical proposal AND a cost proposal in accordance with Clause SA18 – Proposal Content outlined in Section L, page(s) 52-53 of the Screening Information Request (SIR).

In accordance with SIR Section L provision 3.2.2.3-14 entitled, "Late Submissions, Modifications, and Withdrawals of Submittals," any proposals received after the due time and date of 3:00p.m. EDT, July 8, 2025, will not be considered.  In addition, if all requested information is not furnished in the offeror's proposal, the offeror's proposal may be determined to be non-responsive and ineligible for consideration for contract award.

To be considered for award of this project, the contractor must be currently registered in the System for Award Management (SAM) database (website:  www.sam.gov).

This SIR/RFQ is not to be construed as a contract or a commitment of any kind.  The Government shall not be liable for payment of any costs attributed to the preparation and submission of requested proposal documentation.  No individual notification of any amendments will be provided.  It is the Offeror’s responsibility to visit this website frequently for updates on this procurement.  Acquisition Management System (AMS) applies to FAA in place of the Federal Acquisition Regulation (FAR) and various other provisions of Federal acquisition law.

Update #1 ·

The Federal Aviation Administration (FAA), Eastern Acquisitions-AAQ-570, College Park, GA, is issuing Screening Information Request (SIR) Number 697DCK-25-R-00318, NEW HVAC Replacement, Pearl River (Slidell), LA, as detailed in the Statement of Work (SOW) attached to the Solicitation in accordance with the Acquisition Management System (AMS) 3.2.2.2 Policy as supplemented with additional information included in this notice.

The selected Contractor will remove and dispose of the existing four (4) HVAC units and associated ductwork, air handler, controls and other related components.  The Contractor will also provide and install two (2) new 20–ton packaged HVAC units with associated ductwork, two (2) V-PAC wall-mounted systems, HVAC controls, and all associated work and components.

The FAA contemplates award of a Firm Fixed Price Contract as a result of this solicitation.
This requirement is set-aside and offered to all small business concerns. 
The NAICS code for this acquisition is 238220 – Plumbing, Heating, and Air Conditioning Contractors - $19 Million.
The estimated cost magnitude for this project is between $250,000 and $500,000.
Projected Period of Performance for this project is approximately 60 calendar days.

All interested sources should first attempt to download the attached SIR document(s).  If downloading is not possible, all requests for copies of the SIR document(s) must be made in writing to the attention of Marc Lemay, Contracting Officer (AAQ-570), via e-mail at Marc.Lemay@faa.gov and Suzanne.T-CTR.Huggins@faa.gov
NOTE: Electronic submission is preferred. The electronic submission should be in either Microsoft WORD format or portable document format (PDF), not in a zipped format. Please note that the FAA e-mail server restricts file size to 10MB per email message, therefore, responses may have to be submitted in more than one e-mail to be received.

There is an optional site visit on June 17, 2025, at 9:00am.  This is the only site visit that will be scheduled for the anticipated project; and no individual site visits will be permitted. 

Meeting point:  30°20'53.5"N 89°46'46.1"W  
Pearl River (Slidell), LA 70452 
http://maps.google.com/maps?q=30.34818%2C-89.77947

To attend the site visit, advanced notice via Marc.Lemay@faa.gov and Suzanne.T-CTR.Huggins@faa.gov is required.  Note: The site visit will be canceled without notice, if no notices of attendance are received by June 13, 2025, at 3:00pm ET.

All Questions/Requests for Information (RFI) must be emailed to Marc.Lemay@faa.gov no later than June 24, 2025; 2:00pm Eastern Daylight Time (EDT) to allow sufficient time to respond.   TELEPHONE INQUIRIES WILL NOT BE ACCEPTED.

No questions concerning the project will be answered during the site visit unless the Contracting Officer or the Contracting Officer's Representative is present at the site visit: however, no changes are made to the SIR unless a written amendment is issued. The FAA assumes no responsibility for any conclusions or interpretations made by the contractor based on the information received by any means other than in writing from the Contracting Officer. The FAA does not assume responsibility for any understanding reached or representation made concerning conditions, which can affect the work, by any of its officers or agents before the execution of this contract, unless that understanding, or representation is expressly stated in the contract.
 
Potential offerors should note that the FAA reserves the right to communicate with one or more offerors at any time during the solicitation process. Proposals must be received by email no later than July 8, 2025; 3:00 PM EDT to marc.lemay@faa.gov and suzanne.t-ctr.huggins@faa.gov

When responding to this Screening Information Request/Request for Proposal (SIR/RFP), each offeror is required to submit a technical proposal AND a cost proposal in accordance with Clause SA18 – Proposal Content outlined in Section L, page(s) 52-53 of the Screening Information Request (SIR).

In accordance with SIR Section L provision 3.2.2.3-14 entitled, "Late Submissions, Modifications, and Withdrawals of Submittals," any proposals received after the due time and date of 3:00p.m. EDT, July 8, 2025, will not be considered.  In addition, if all requested information is not furnished in the offeror's proposal, the offeror's proposal may be determined to be non-responsive and ineligible for consideration for contract award.

To be considered for award of this project, the contractor must be currently registered in the System for Award Management (SAM) database (website:  www.sam.gov).

This SIR/RFQ is not to be construed as a contract or a commitment of any kind.  The Government shall not be liable for payment of any costs attributed to the preparation and submission of requested proposal documentation.  No individual notification of any amendments will be provided.  It is the Offeror’s responsibility to visit this website frequently for updates on this procurement.  Acquisition Management System (AMS) applies to FAA in place of the Federal Acquisition Regulation (FAR) and various other provisions of Federal acquisition law.

Attachments

Files attached to this notice, newest first
File Type Posted
RFIs - 697DCK-25-R-00318 NEW ARSR HVAC Replacement.pdf PDF
Attachment 1 - RFI NEW Attic Ducts.pdf PDF
Attachment 2 - RFI NEW Site Visit Attendance.pdf PDF
Wage Determination LA20250001 050225.pdf PDF
697DCK-25-R-00318.pdf PDF
NEW HVAC SOW_Rev C.pdf PDF
Drawing M001(1) - Rev D.pdf PDF
Drawing M002(1) UPS Building HVAC - Rev C.pdf PDF

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity