MT FLAP VALLEY 20(1), Duck Creek Road
Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 69056724B000013
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Not on record
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Washington, United States
- Points of contact
-
- Contracts G. Office wfl.contracts@dot.gov (360) 619-7520
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Transportation Federal Highway Administration is seeking bids for the MT FLAP VALLEY 20(1) road improvement project located approximately 16 miles southeast of Glasgow, Montana. The project consists of roadway reconditioning, aggregate surfacing, aggregate stabilization, asphalt surfacing, subexcavation, and drainage improvements on 4.85 miles of gravel road. The work is divided into three discrete segments with varying scopes, including reconstructing and widening the deteriorated asphalt roadway, maintaining and resurfacing the existing 30-foot width, and surface reconditioning and aggregate surface placement. The estimated price range for the contract is between $5 and $10 million, with a tentative fixed completion date of Fall 2025. The solicitation is expected to be issued in Summer 2024 and will be a full and open competition.
This contract opportunity is not set-aside for any specific business category. The NAICS code is 237310 - Highway, Street, and Bridge Construction, and the PSC code is Y1LB - Construction Of Highways, Roads, Streets, Bridges, And Railways. No potential incumbents or current contractors are named. The project is anticipated to have a price range between $5 and $10 million.
Notice text
3 versions
Update #3 · Latest ·
Update 7/31/2024: QA_07-30-2024.pdf posted to attachments.
Project: MT FLAP VALLEY 20(1), Duck Creek Road
This project consists of work on 4.85 miles of gravel road in Valley County, Montana. The project begins at the intersection of Duck Creek Road with Montana Secondary Highway 24, approximately fifteen (15) miles southeast of Glasgow, Montana. The project work consists of three discrete segments for upgrades, as follows: Segment 1 (milepost 0.0 to 1.1) - reconstruct & widen deteriorated asphalt roadway from 24' to 28' with new asphalt to better accommodate RV/Boat/truck traffic and pedestrians; segment 2 (milepost 1.1 to 2.6) - maintain 30' width and resurface with 6" of gravel with dust palliative. Reduce existing steep grade for better RV/truck/boat traffic safety; and segment 3 (milepost 2.6 to 4.85) - surface reconditioning and aggregate surface placement. The work includes drainage, roadway reconditioning, asphalt surfacing, aggregate surfacing, aggregate stabilization, pavement markings and signage.
Project Location: 16 Miles SE of Glasgow, MT
Project Length: 4.85 MIles
Estimated Price Range: Between $2 and $5 Million
Tenative Solicitation Date: Summer 2024
Tenative Fixed Completion Date: Fall 2025
This will be solicited as Full and Open
See Attachment for additional information.
Update #2 ·
Project: MT FLAP VALLEY 20(1), Duck Creek Road
This project consists of work on 4.85 miles of gravel road in Valley County, Montana. The project begins at the intersection of Duck Creek Road with Montana Secondary Highway 24, approximately fifteen (15) miles southeast of Glasgow, Montana. The project work consists of three discrete segments for upgrades, as follows: Segment 1 (milepost 0.0 to 1.1) - reconstruct & widen deteriorated asphalt roadway from 24' to 28' with new asphalt to better accommodate RV/Boat/truck traffic and pedestrians; segment 2 (milepost 1.1 to 2.6) - maintain 30' width and resurface with 6" of gravel with dust palliative. Reduce existing steep grade for better RV/truck/boat traffic safety; and segment 3 (milepost 2.6 to 4.85) - surface reconditioning and aggregate surface placement. The work includes drainage, roadway reconditioning, asphalt surfacing, aggregate surfacing, aggregate stabilization, pavement markings and signage.
Project Location: 16 Miles SE of Glasgow, MT
Project Length: 4.85 MIles
Estimated Price Range: Between $2 and $5 Million
Tenative Solicitation Date: Summer 2024
Tenative Fixed Completion Date: Fall 2025
This will be solicited as Full and Open
See Attachment for additional information.
Update #1 ·
Project: MT FLAP VALLEY 20(1), Duck Creek Road
This project consists of work on 4.85 miles of gravel road in Valley County, Montana. The project begins at the intersection of Duck Creek Road with Montana Secondary Highway 24, approximately fifteen (15) miles southeast of Glasgow, Montana. The project work consists of three discrete segments for upgrades, as follows: Segment 1 (milepost 0.0 to 1.1) - reconstruct & widen deteriorated asphalt roadway from 24' to 28' with new asphalt to better accommodate RV/Boat/truck traffic and pedestrians; segment 2 (milepost 1.1 to 2.6) - maintain 30' width and resurface with 6" of gravel with dust palliative. Reduce existing steep grade for better RV/truck/boat traffic safety; and segment 3 (milepost 2.6 to 4.85) - surface reconditioning and aggregate surface placement. The work includes drainage, roadway reconditioning, asphalt surfacing, aggregate surfacing, aggregate stabilization, pavement markings and signage.
Project Location: 16 Miles SE of Glasgow, MT
Project Length: 4.85 MIles
Estimated Price Range: Between $5 and $10 Million
Tenative Solicitation Date: Summer 2024
Tenative Fixed Completion Date: Fall 2025
This will be solicited as Full and Open
See Attachment for additional information.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| MT FLAP VALLEY 20(1), Duck Creek Road | Award Notice | |
| MT FLAP VALLEY 20(1), Duck Creek Road | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| ID FLAP KOOTEN 8450(1), Yellowstone Trail Road, Segment 1 | Federal Highway Administration | No set-aside | |
| Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1) | Federal Highway Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity