About this opportunity

The Department of Veterans Affairs Veterans Health Administration (VA) is seeking a contractor to perform comprehensive boiler maintenance and safety testing services at the Bedford VA Medical Center. The solicitation requires semi-annual calibrations, combustion testing, and safety device testing for boilers located in Buildings #22 and #70, specifically covering three Cleaver Brooks CB700LE boilers and two HB Smith low-pressure boilers. Contractors must comply with the VHA Boiler and Associated Plant Safety Device Testing Manual, provide detailed calibration reports, and use specialized testing equipment and laptop computers to document and backup control settings. The work involves inspecting and calibrating multiple control systems, including instruments from manufacturers like Preferred Instruments, CB Hawk, Foxboro, Yokogawa, Siemens, and Johnson Controls. The pre-solicitation notice indicates a response deadline of May 16, 2025, with contractors expected to perform comprehensive testing, provide technical reports, and identify potential repair or replacement needs.

The opportunity is set aside for Veteran-Owned Small Businesses and focuses on the NAICS category 238220 for Plumbing, Heating, and Air-Conditioning Contractors. The contract will require extensive technical expertise, with contractors needed to perform safety device testing on over 30 specific system components, including high-pressure cut-outs, safety valves, fuel system interlocks, and various alarm and control mechanisms. Contractors must have an ASME Board Certified Inspector available and be prepared to open boiler water and firesides for internal inspections. While specific award values are not disclosed, the comprehensive nature of the work suggests a significant technical and operational commitment. The contract requires two semi-annual service periods approximately six months apart, with precise scheduling to be coordinated with the Maintenance and Operations Supervisor. No details about incumbent contractors were provided in the pre-solicitation notice.

Notice text

Page 2 of 2

VA Bedford HCS

STATEMENT OF WORK

Boiler Plant Burners, Controls, Instruments, and Data Management

Inspection, Safety Device Testing and Calibration

General Scope of Work

1. Semi-Annual Calibrations of Boiler Plant Controls and Instrumentation

2. Semi-Annual Combustion Testing of Boilers

3. Semi-annual Safety Device Testing

4. Semi-Annual Calibrations of Boiler Plant Controls and Instrumentation.

A. OVERVIEW

1. Contractor shall provide all labor, tools, testing equipment and supplies required for semi-annual calibrations of Boiler plant controls and instrumentation for three boilers located in Building #22, two boilers in Building #70, and other plant equipment.

2. Contractor shall ensure all work is in accordance with the procedures outlined in VHA Boiler and Associated Plant Safety Device Testing Manual Eighth Edition, or the most current edition.

3. Contractor must have a laptop computer and required software to plug into and back-up all settings in the PCCIII controls and provide a back-up flash drive to Plant Supervisor.

4. Contractor will not be accessing any sensitive VA Information Systems, these are boiler controls only. Control devices will include but are not limited to the following: Preferred Instruments, CB Hawk, Foxboro, Yokogawa, Siemens, and Johnson Controls.

5. Contractor shall also supply to customer, calibration reports for each piece of equipment, indicating date, settings, pass/fail, technical data, and name of technician performing calibrations.

6. Contractor will provide a list of line items that require parts/replacement and the costs required to repair/replace those items. Additional work beyond the scope of this contract, requires approval from the Contracting Officer. See attached list of controls and instrumentation to be calibrated.

B. CALIBRATION

The following is a list of devices that will require calibration:

1. Plant Master PCIII

Outside air temp

Plant steam flow

Distribution steam flow

Plant demand

Steam header press Hi/Lo and alarms

Oil pressure transmitter and alarms

Propane pilot gas transmitter and alarms

Main gas pressure transmitter and alarms

Control air pressure transmitter and alarms

Low main gas pressure alarm

High main gas pressure alarm

Explosive gas and carbon monoxide detection system

2. DA PCIII

High oil header press alarm

Low oil header press alarm

DA steam PSI

DA temp

DA level

High DA level alarm

Low DA level alarm

Cond PCIII: Condensate tank level

Condensate tank high level alarm

Condensate tank low level alarm

Condensate tank temp

Condensate tank make-up valve

3. Hawk Controllers Boilers, 1, 2, and 3

Plant demand

Boiler demand

Firing rate

Steam flow

Economizer flue temp-in

4. #1 and #2 Draft PCIII

Oxygen transmitter

Damper %

Outlet temp

Jackshaft position

Efficiency

5. #1 and #2 Fuel Flow PCIII

Boiler gas flow

Boiler oil flow

Flue gas temp monitor calibration

Flue gas temp High and Low temp alarms

6. #1, #2, and #3 Feedwater Pump Variable Frequency Drive Units

Note; there is a new DA Tank installed as of October 2024. Testing will reflect the new parameters required on the new system.

C. SEMI-ANNUAL COMBUSTION TESTING OF BOILERS

1. Contractor will provide all labor and materials required to perform burner calibration on three (3) Cleaver Brooks CB700LE boilers. Each burner assembly will be inspected and adjusted to manufacturer s settings. Each boiler will be calibrated on gas and oil firing twice a year, approximately 6 months apart, as scheduled by the Maintenance and Operations Supervisor.

2. Contractor will provide burner calibration printouts for each pin on the gas and oil cams 20 on CB Hawk for all three boilers. Settings will be as close and safe as possible for max input for gas and oil firing at high fire as per the inputs listed on the boiler plate.

3. Contractor will calibrate the burners and not exceed the requirements of this facilities permit for emissions. Contractor will perform a smoke test on boilers.

4. Contractor is responsible for providing all tools and specialized equipment required to perform the work.

D. SAFETY DEVICE TESTING

1. Contractor shall provide all labor, tools, and all testing equipment required to perform Semi-Annual Safety Device testing on three (3) Cleaver Brooks LE fire-tube boilers, and other plant equipment as identified in the VHA Boiler and Associated Plant Safety Device Testing Manual, Eighth Edition, or current edition. Testing shall be in accordance with the procedures outlined in VHA Boiler and Associated Plant Safety Device Testing Manual Eighth Edition or the most current edition. Testing manual will be available upon request.

2. Contractor shall provide a detailed report including a picture of each device as installed on the system and all other information required by the VHA Boiler and Associated Plant Safety Device Testing Manual, Eighth Edition or current edition shall be scheduled with the Boiler Plant Supervisor.

3. Contractor will furnish all tools, parts, and specialized equipment to accomplish this.

4. Devices tested shall include, but not be limited to the list below as changes may be made to the VHA Boiler and Associated Plant Safety Device Testing Manual Eighth Edition.

High-steam pressure cut-out (recycle), High-steam pressure cut-out (non-recycle).

Steam safety valves (raise boiler pressure until valves lift and reset).

Check gas vent for leaks.

High-gas fuel pressure cut-off.

Low-gas fuel pressure cut-off.

Gas fuel safety shut off valves proof of closure.

Leak test fuel oil safety shut off valves.

Check operation of Liquid Propane Gas pilot.

Low-pilot gas pressure cut-out.

Forced draft fan motor interlock.

Forced draft fan damper wide open for purge.

Boiler outlet damper wide open for purge.

Purge air flow interlock.

Timing for pre-purge.

Timing for post-purge.

Igniter timing.

Leak test gas fuel safety shut off valves.

High-fuel oil temperature cut-off (heated fuel, N/A).

Low-fuel oil temperature cut-off (heated fuel, N/A).

Low-atomizing air pressure for fuel oil (HH) Low fire position interlock.

Combustion air interlocks.

Main flame out; i.e., time to close valves.

Ignition flame out; i.e., time to close valves.

Minimum igniter flame test.

Scanner not sensing ignition spark.

Low-oxygen alarm and/or cut-out.

Pre-purge setting of flue gas recirculation damper.

Interlock of building outside air damper with burner control.

High-fuel oil pressure cut-off.

Low fuel oil pressure cut-off.

DA tank high- and low-level alarms.

DA tank overflow device.

DA tank high pressure alarm.

DA tank safety valve.

Condensate Receiver tank high- and low-level alarms.

Economizer safety valve.

E. BUILDING #70 BOILER MAINTENANCE, INSPECTION AND TUNE UP

1. Contactor shall open the boilers water and firesides, for 2 HB Smith, 14 section, cast-iron, low-pressure boilers.

2. Contractor shall prepare the boiler and its auxiliary devices for an internal inspection by a Contractor supplied ASME Board Certified Inspector.

3. Contractor will perform all required safety device testing per the VHA Boiler and Associated Plant Safety Device Testing Manual Eighth Edition.

4. Upon completion of the inspection, if any repairs are required at that time, a written quote will be provided to the facility. No repairs will be made unless approved separately by the Contracting Officer.

5. Once the boiler is inspected and/or repaired, the Contractor will put the boiler back together, fill with water, fire up the unit, and perform an operational and combustion test on oil and gas, making any adjustments needed for proper operation.

6. Contractor will be responsible for any gaskets and seals that may be required to put boiler back together after inspection such as inspection port gaskets, low water cutout gaskets.

7. Contractor is responsible to provide any specialized tools or equipment to perform the work.

8. Contractor will provide a service report and all combustion printouts to the Contracting Officers Representative (COR) upon completion of work.

9. Contractor will sign in/out at the Main Boiler Plant, Building #22, and will be escorted to the work site.

10. No changes to this Statement of Work can be made without prior written approval of the Contacting Officer

Attachments:

VHA Boiler and Associated Plant Safety Device Testing Manual Eighth Edition

VHA Directive 1810, Boiler and Boiler Plant Operations, January 4, 2023

Files

File Type Posted
36C24125Q0469.docx DOCX document

Similar open opportunities

Opportunity Agency Set-aside Responses due
J045--FY27 Boilers Maintenance & Testing Department of Veterans Affairs VA Caribbean Healthcare Syatem San Juan, Puerto Rico 00921, United States · NAICS 238220 Veterans Integrated Service Network 8 Service-Disabled Veteran-Owned Small Business
J048--NEW - Energy Center Steam Header& Boilers valves, gaskets, and vent replacement Department Of Veterans Affairs VA North Texas Health Care System Dallas TX 75216 · NAICS 238220 Veterans Integrated Service Network 17 Service-Disabled Veteran-Owned Small Business
16292 Steam Boiler Replacement Hill AFB, Utah 84056, United States · NAICS 238220 Air Force Sustainment Center Total Small Business
White City, Oregon, Boiler Inspection Services Solicitation Base Year + Four Option Years (offers are now due on 11/13/2026) White City, Oregon 97503, United States · NAICS 561210 Veterans Integrated Service Network 20 Service-Disabled Veteran-Owned Small Business
Z1DA--Project 695-24-107 Replace Boilers 4 and 5 Clement J. Zablocki, VA Medical Center 5000 West National Avenue Milwaukee, WI 53295 United States · NAICS 238220 Veterans Integrated Service Network 12 Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors