Install Plate and Frame Heat Exchanger, at the Lloyd D. George Federal Courthouse, 333 Las Vegas Blvd. South, Las Vegas, NV
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 47PK1721R0007
- Agency
-
Region 9
Public Buildings Service, General Services Administration
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Place of performance
- Las Vegas Nv Usa
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks design-build services to install a new plate and frame heat exchanger at the Lloyd D. George Federal Courthouse located at 333 Las Vegas Boulevard South in Las Vegas, Nevada. The General Services Administration Public Buildings Service Region 9 is procuring these services. The contractor will be responsible for placing a new housekeeping pad, installing the new heat exchanger and associated hydronic piping, conducting start-up and balancing activities, and ensuring proper interface with existing controls systems. The work must be coordinated to minimize impacts to daily operations. Proposals were due by April 13, 2021. Evaluation criteria include technical approach, past performance, and price.
This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses. The NAICS code is 238220 and PSC code R499. The estimated award value is between $250,000 and $500,000. The contractor must complete all work within 348 calendar days of receiving the notice to proceed. The place of performance is the Lloyd D. George Federal Courthouse located at 333 Las Vegas Boulevard South in Las Vegas, Nevada.
Notice text
2 versions
Update #2 · Latest ·
Amendment 2 has been issued, dated 03292021. Please see below in attachments for the following documents:
Amendment 2_47PK1721R0007
Amendment 2_Attachment B - Standard Form 1442 - Solicitation, Offer and Award
----------------------------------------------------------------------------------------------------------------------------------------------------------
Amendment 1 has been issued, dated 03182021. Please see below in attachments for the following documents:
Amendment 1_47PK1721R0007
Attachment K - Past Performance Questionnaire
Attachment L - Notice of Invoicing Procedures and Instructions
Site Visit Sign-In Sheets for March 4 and March 9 2021
-------------------------------------------------------------------------------------------------------------
Design build services to include but not limited to:
1. Placing a new housekeeping pad.
2. Installing a new heat plate exchanger sized for this existing system.
3. Installing new hydronic piping to this exchanger and connecting the new piping to the existing piping.
4. Flush and treat new and existing piping as required.
5. Conduct all start up and balancing required to bring the system online.
6. Make any final adjustments when the system is under full load.
7. Ensure new system properly interfaces with existing control systems.
8. The work shall be coordinated with the GSA to ensure the work minimally impacts daily
operations. This will include limiting overly noisy operations to after normal working hours
(after 1700 and before 0700hours.)
9. The General Contractor shall provide non-hazardous construction & demolition waste
figures as part of the “Close Out” documentation.
10. The General Contractor shall provide a minimum of a two (2) year warranty for all labor and
materials associated with the project, unless a longer term is stated elsewhere.
Update #1 ·
Design build services to include but not limited to:
1. Placing a new housekeeping pad.
2. Installing a new heat plate exchanger sized for this existing system.
3. Installing new hydronic piping to this exchanger and connecting the new piping to the existing piping.
4. Flush and treat new and existing piping as required.
5. Conduct all start up and balancing required to bring the system online.
6. Make any final adjustments when the system is under full load.
7. Ensure new system properly interfaces with existing control systems.
8. The work shall be coordinated with the GSA to ensure the work minimally impacts daily
operations. This will include limiting overly noisy operations to after normal working hours
(after 1700 and before 0700hours.)
9. The General Contractor shall provide non-hazardous construction & demolition waste
figures as part of the “Close Out” documentation.
10. The General Contractor shall provide a minimum of a two (2) year warranty for all labor and
materials associated with the project, unless a longer term is stated elsewhere.
Files
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| Install Plate and Frame Heat Exchanger, at the Lloyd D. George Federal Courthouse, 333 Las Vegas Blvd. South, Las Vegas, NV | Award Notice | |
| This notice | Solicitation | |
| Install Plate and Frame Heat Exchanger, at the Lloyd D. George Federal Courthouse, 333 Las Vegas Blvd. South, Las Vegas, NV | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| HVAC Unit Replacement | National Oceanic and Atmospheric Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity