Indefinite delivery indefinite quantity (IDIQ) requirement for paving

Closed Pre-Solicitation Posted

Solicitation number
W912PA-18-R-0002
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Contract number
W912PA19D0001 Federal IDV award
Awardee
Etablissements Wanty Maurice
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
(1) Chievres Air Base - 7950 Chievres, Belgium. (2) Shape 7010 Shape. (3) Nato Support Activity (NSA) - Chaussee de Louvain, 13, 1932 Sint-Stevens-Woluwe. (4) Brussels American Schools (BAS) - Avenue J.F Kennedy, 12, 1933 Sterrebeek. (5) Zutendaal - 3690 Zutendaal. Chievres, Belgium

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Offers are due in 16 October 2018 - 11.00 hrs AM LOCAL TIME
The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.


.

Update #5 ·

Offers are due in 10 October 2018 - 10.00 hrs AM LOCAL TIME
The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

Evaluation:


The government will award a contract resulting from this solicitation to the responsible offeror whose offer confirming to the solicitation, will be most advantageous to the government, price and other factors considered, utilizing the Lowest Price Technically Acceptable (LPTA) source selection process. The following factors will be used to evaluate offers:
(1) Price


(2) Technical


(a) Contractors shall comply with the following classes - categories and sub-categories agreed upon by the competent Belgian regional minister - Belgium Ministry of Public Works - Valid Certificate for Class 5 (up to 1,810,000.00 Euros), C (general enterprise of road works) or EU equivalent.


(b) ISO 9001 and ISO 14001 Certification.


(c) Contractor shall possess a Certificate VCA - For Safety, Health and Environment - See web site (http://www.vcadirect.com/vca-course/all-about-vca


(3) Past Performance - Provide evidence of five (5) years of government and/or public works involving paving and road construction.


The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Eustace McKenzie at eustace.mckenzie.civ@mail.mil or Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.


.

Update #4 ·

Offers are due in 19 September 2018 - 10.00 hrs AM LOCAL TIME
The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

Evaluation:


The government will award a contract resulting from this solicitation to the responsible offeror whose offer confirming to the solicitation, will be most advantageous to the government, price and other factors considered, utilizing the Lowest Price Technically Acceptable (LPTA) source selection process. The following factors will be used to evaluate offers:
(1) Price


(2) Technical


(a) Contractors shall comply with the following classes - categories and sub-categories agreed upon by the competent Belgian regional minister - Belgium Ministry of Public Works - Valid Certificate for Class 5 (up to 1,810,000.00 Euros), C (general enterprise of road works) or EU equivalent.


(b) ISO 9001 and ISO 14001 Certification.


(c) Contractor shall possess a Certificate VCA - For Safety, Health and Environment - See web site (http://www.vcadirect.com/vca-course/all-about-vca


(3) Past Performance - Provide evidence of five (5) years of government and/or public works involving paving and road construction.


The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Eustace McKenzie at eustace.mckenzie.civ@mail.mil or Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.


.

Update #3 ·

Offers are due in 19 September 2018 - 10.00 hrs AM LOCAL TIME

The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

Evaluation:


The government will award a contract resulting from this solicitation to the responsible offeror whose offer confirming to the solicitation, will be most advantageous to the government, price and other factors considered, utilizing the Lowest Price Technically Acceptable (LPTA) source selection process. The following factors will be used to evaluate offers:
(1) Price


(2) Technical


(a) Contractors shall comply with the following classes - categories and sub-categories agreed upon by the competent Belgian regional minister - Belgium Ministry of Public Works - Valid Certificate for Class 5 (up to 1,810,000.00 Euros), C (general enterprise of road works) or EU equivalent.


(b) ISO 9001 and ISO 14001 Certification.


(c) Contractor shall possess a Certificate VCA - For Safety, Health and Environment - See web site (http://www.vcadirect.com/vca-course/all-about-vca


(3) Past Performance - Provide evidence of five (5) years of government and/or public works involving paving and road construction.


The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Eustace McKenzie at eustace.mckenzie.civ@mail.mil or Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.



Update #2 ·

The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

Evaluation:


The government will award a contract resulting from this solicitation to the responsible offeror whose offer confirming to the solicitation, will be most advantageous to the government, price and other factors considered, utilizing the Lowest Price Technically Acceptable (LPTA) source selection process. The following factors will be used to evaluate offers:
(1) Price


(2) Technical


(a) Contractors shall comply with the following classes - categories and sub-categories agreed upon by the competent Belgian regional minister - Belgium Ministry of Public Works - Valid Certificate for Class 5 (up to 1,810,000.00 Euros), C (general enterprise of road works) or EU equivalent.


(b) ISO 9001 and ISO 14001 Certification.


(c) Contractor shall possess a Certificate VCA - For Safety, Health and Environment - See web site (http://www.vcadirect.com/vca-course/all-about-vca


(3) Past Performance - Provide evidence of five (5) years of government and/or public works involving paving and road construction.


The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Eustace McKenzie at eustace.mckenzie.civ@mail.mil or Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.


.

Update #1 ·

The US Government currently anticipates an Indefinite Delivery Indefinite Quantity (IDIQ) construction requirement for the renovation and maintenance of roads located inside USAG Benelux installations at Chièvres Air Base, S.H.A.P.E., NATO Support Activity (NSA) Brussels American Schools (BAS) and Zutendaal. Worked performed under this requirement must conform to Belgium and European Standards regulations as identified under the Bureau de Normalisation.
Principal Features:
Principal items to be performed to accomplish the work consist of but are not limited to:
1) Preliminary work
2) Demolitions
3) Earthwork
4) Sub-foundations
5) Foundations
6) Concrete coverings
7) Hydrocarbon coverings
8) Miscellaneous coverings
9) Linear elements
10) Sewage
11) Small constructions
12) Marking
13) Maintenance and repair work
14) Rehabilitation of the surroundings
15) Miscellaneous
Performance of Work:
The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform repair, alteration and maintenance of roads, sewage, structures in US Government property in the quantities and description identified and ordered by individual task orders.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

Evaluation:


The government will award a contract resulting from this solicitation to the responsible offeror whose offer confirming to the solicitation, will be most advantageous to the government, price and other factors considered, utilizing the Lowest Price Technically Acceptable (LPTA) source selection process. The following factors will be used to evaluate offers:
(1) Price


(2) Technical


(a) Contractors shall comply with the following classes - categories and sub-categories agreed upon by the competent Belgian regional minister - Belgium Ministry of Public Works - Valid Certificate for Class 5 (up to 1,810,000.00 Euros), C (general enterprise of road works) or EU equivalent.


(b) ISO 9001 and ISO 14001 Certification.


(c) Contractor shall possess a Certificate VCA - For Safety, Health and Environment - See web site (http://www.vcadirect.com/vca-course/all-about-vca


(3) Past Performance - Provide evidence of five (5) years of government and/or public works involving paving and road construction.


The solicitation for this requirement is expected to be released on or about 15 March 2018, with an award date on or about 30 April 2018.


Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of a solicitation.


Payment for this requirement will be made through the Wide Area Work Flow (WAWF) system. Contractors shall be registered in WAWF.


Because this requirement is located OCONUS, FAR Part 19 does not apply, therefore this requirement will not be set aside for small business.


All enquiries in response to this notice shall be submitted via email to Eustace McKenzie at eustace.mckenzie.civ@mail.mil or Sandra R. Van Beneden sandra.r.vanbeneden.ln@mail.mil or usarmy.rheinland-pfalz.409-contr-spt-bde.mbx.409csb-bru-request@mail.mil


No phone calls, please.



Files

File Type Posted
W912PA-18-R-0002-0004.pdf PDF
Attachment_1_-_Statement_of_Work_-_2_Oct_18.pdf PDF
W912PA-18-R-0002-0003.pdf PDF
W912PA-18-R-0002-0002.pdf PDF
W912PA-18-R-0002-0001.pdf PDF
W912PA-18-R-0002.pdf PDF
Attachment_1_-_Statement_of_Work_-_20_Jun_18.doc DOC document
Attachment_2_-_Schedule_-_Revised_19_June_18.XLS XLS spreadsheet