General Contractor for the Infrastructure Project at the Philip J Burton Federal Building and U. S. Courthouse in San Francisco, CA

Award Notice Posted

Solicitation number
GS-09P-16-KT-C-7006
Agency
Awarded
to Abide International, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
GS-09P-16-KT-C-7028 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Place of performance
450 Golden Gate Avenue San Francisco, California 94133, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Amendment 0005 is being issued to solicitation GS-09P-16-KT-C-7006 to incorporate the following changes to the solicitation:

1) Revised Contract Price Form (clarify relation to specs/project manual)

END OF AMENDMENT 0005 

Update #5 ·

Amendment 0004 is being issued to solicitation GS-09P-16-KT-C-7006 to incorporate the following changes to the solicitation:

1)    Questions and Answers dated 6/9/2016

2)    Addendum #4 Drawings and Specs (Addendum #3 was skipped to match Amendment #4 numbering) - for copy of Addendum #4 Drawings and Specs please email request to Wesley Lau at Wesley.Lau@gsa.gov 

3)    Summary of Addendum #4 Drawings and Specs

4)     Photos from Investigative Demolition 

END OF AMENDMENT 0004 

Update #4 ·

**********************************************************************
 
Amendment 0003 is being issued to solicitation GS-09P-16-KT-C-7006 to incorporate the following changes to the solicitation:

 


1)    The due date for receipt of proposals has been extended to:


4:00pm PST on Wednesday, June 15, 2016


Corresponding changes to the due dates of Past Performance references have also been extended. An additional site visit scheduled for Wednesday, May 25, 2016 at 9am has also been added. Please refer to the amended solicitation for further details. Changes have been highlighted in yellow.


2)    “Similar projects” definition has been revised to:


"SIMILAR PROJECT" is defined as a project that is similar in size, type and complexity. To be considered similar in “size”, project(s) must exceed $4,000,000.00 in construction costs and be completed in the last 10 years. To be considered similar in “type”, project(s) must include infrastructure work and construction in an occupied building. To be considered similar in “complexity”, project(s) must include, but are not limited to, public-use buildings or commercial office buildings.


3)    Language in Total Price Evaluation Form has been amended. Amended language is highlight in yellow.  

END OF AMENDMENT 0003 

Update #3 ·

Amendment 0002 is being issued to Solicitation GS-09P-16-KT-C-7006 in order to incorporate the following changes:

        a. (Ref. Addendum2_450 GG_Drawings_2016-05-06)

·         Further defines Reglet and Counterflashing requirements for Penthouse Columns, Parapet Wall Base and Wall Base and continuous cleats for Low Parapet details;


·         Adds underlayment to Parapet Coping between Stainless Steel and Aluminum;


·         Clarifies scope for relocated AP-06 antennae and adds a detail for mounting.


       b..  (Ref. 099623 graffiti-resistant coating add02)


·         Adds specification section defining requirements for the anti-graffiti coating scope presented in Addendum #1


       c.  (Ref. 076200 sheet metal flashing and trim new add2)


·         Revises Bid Set spec. by adding requirements for Reglets, references related to Aluminum Siding spec. section, eliminates references to roof felt work and standards, and deleted reference to Steel Siding, adds Manufacturer Technical Data requirements for submittals, clarifies full dimensional requirements of sheet metal seam samples, eliminates the removal of cloths, tarps and containers at the end of every days work and grammatical corrections.


       d.  (Ref. 075419 pvc membrane roofing new add02)


·         Changes the PVC color desired from White to Grey.


       e.  (Ref. 000110 toc add02)


·         Revises the Specification Table of Contents highlighting specifications revised and added.


 


END OF AMENDMENT 0002


 

Update #2 ·

**************************************************************

Amendment 0001 is being issued to Solicitation GS-09P-16-KT-C-7006 in order to incorporate the following changes:

1) The period of performance is changed from 365 calendar days to 426 calendar days.

2) To include or revise the following scope of work items:
 
a. (Ref. Addendum1_450 GG_Drawings_2016-05-05) [Drawings provided upon request. Please email Wesley.Lau@gsa.gov to request copy of drawings.]
• Adds preparatory cleaning and the application of an anti-graffiti coating to both the new OA intake riser exterior stone cladding and the lower 10 feet of stone cladding around the building's entire perimeter;
• Removes reinstallation scope for approx. (1) antenna and (2) dishes now slated for demolition and for (1) dish to remain in place, not to be salvaged or reinstalled;
• Adds scope for the mounting of (1) new microwave dish on the north wall into an existing bracket;
• Adds scope for redirecting one existing weather head from wall to roof, providing (1) new roof mounted weather head and (2) roof mounts for antennae relocations by others;
• Adds pipe mounting bracket scope and structural details for approx. (7) whip antennae on the Penthouse walls;
• Moved window film scope for the Main South Entry from the base scope to a newly added Option 6A;
• Adds window film for (16) glass panels in the Main South Entry metal doors as a part of Option 6A;
• Adds base scope window film previously NIS for (7) 14th floor and (46) 16th floor windows, but removes window film for (44) 3rd floor windows;
• Adds granite stone facia attic stock and a mock-up for the facia;
• Adds a mock-up for anti-graffiti coating;

b. (Ref. 017810 project record documents new add01)
• Revision to previous specification section 017810

c. (Ref. 044200 mc exterior stone cladding add01)
• Revision to previous specification regarding attic stock provisions

d. (Ref. Addendum 1 - Structural Calculations)
• New structural calculations that provide dimensional and structural requirements for antennae pole masts and bracketing

e. (Ref. 000110 toc add01)
• New Specification Table of Contents highlighting specifications revised

END OF AMENDMENT 0001

Update #1 ·

The General Services Administration (GSA) announces a requirement for a general contractor to perform construction services for the infrastructure project at the Philip J Burton Federal Building located on 450 Golden Gate Avenue in San Francisco, California. This solicitation is being posted pending approval of funds.

552.219-71 Notice to Offerors of Subcontracting Plan Requirements (MAR 2012)
The General Services Administration (GSA) is committed to assuring that maximum practicable opportunity is provided to small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns to participate in the performance of this contract consistent with its efficient performance. GSA expects any subcontracting plan submitted pursuant to FAR 52.219-9, Small Business Subcontracting Plan, to reflect this commitment. Consequently, an offeror, other than a small business concern, before being awarded a contract exceeding $700,000 ($1,500,000 for construction), must demonstrate that its subcontracting plan represents a creative and innovative program for involving small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns as subcontractors in the performance of this contract.


*The General Contractor who is awarded this contract will be expected to conduct a small business outreach event to publicize possible subcontracts to the small business community. The event will utilize the conference space at 450 Golden Gate Avenue at no cost to the Contractor. The GSA will also participate and help plan/publicize the event.

The North American Industry Classification System (NAICS) code is 236220 - Commercial and Institutional Building Construction. Prospective bidders must be registered in the System for Awards Management (SAM). Information regarding registration can be found at http://www.sam.gov.

Project Summary:
The GSA announces an opportunity for a General Contractor to submit a proposal for a firm-fixed price construction contract for the Infrastructure Project at the Philip J. Burton Federal Building located at 450 Golden Gate Avenue in San Francisco, California. 


The Phillip Burton Federal Building and United States Courthouse is located in the Civic Center area of San Francisco. The building is the largest office building in the vicinity and the largest federal building in the San Francisco metropolitan area. Constructed in 1964, the building consists of 20 stories above ground with two underground basement and sub-basement levels which include parking. Situated on 2.6 acres of land area, the building has approximately 1,244,600 rentable square feet with 236 underground parking spaces.


The building is rectangular in shape and sheathed in an aluminum and glass exterior with a limestone and granite stone facade over concrete walls and columns. The building was renovated from 1989 through 1995 for asbestos removal and tenant space changes. The front plaza was redesigned and reconstructed in 2000. A new main entry project to enhance the security and first impressions of the building was completed in December 2005.


The proposed project shall include the following Scope of Work:
1. Install outside air (OA) intake risers from the north side building grade level up to below the 3rd floor windows as shown on the Contract Documents (CDs) attached to the RFP for this project;
2. The partial replacement of existing cold water (CW) mains with limited ACM pipe insulation abatement through basement and sub-basement areas from (2) CW service locations;
3. The ACM abatement of insulation for domestic CW riser fittings, limited ACM Steel beam fireproofing abatement over width of shaft wall demolition and the selective replacement of CW pipe risers from sub-basement to the roof of the building as shown on the CDs.
4. Replace adhesive based building solar control window film from the 1st floor to the 20th floor, less floor 8 and selective areas shown as not in contract (NIC) within the CDs.
5. Replace the building roof, replace (4) exhaust fans and demo (2) exhaust fans and rooftop ducting and pans over their respective duct drop curb, demo (2) end-suction pumps and piping and cap above roof. Perform salt corrosion repairs of roof mounted exhaust fan housings, limited replacement or salt corrosion repair of steel cooling tower platform supports and frames and large condenser water pipe support weldments as shown on the CDs;
6. Replace N & S Penthouse walls and ACM footing abatement.
7. Replace Window Film on floors 2 through 20


The Federal Building must remain fully operational throughout construction. Domestic water for washing and toilet flushing, potable water for the Cafeteria, HVAC exhaust and communications systems must remain operational during all occupied periods. Work deemed to be disruptive to tenants and the normal operation of the building (including loud noise, hazardous odors, dust, etc) must be scheduled for after normal building operation hours to minimize disruptions to building occupants and to maintain public safety. All work shall be in accordance with GSA quality standards and requirements, including Federally established energy and sustainability goals, accessibility requirements and security specifications. 100% Construction Drawings will be provided to the bidders. 

Prospective Offeror's experience must include, but is not limited to, demonstrated experience executing projects in an occupied building of similar size and complexity. The scope of work includes construction inspections, end-to-end pre-commissioning testing, commissioning, cost estimating, site investigation, site measurements, reproduction services, coordination, limited ACM and LBP abatement, demolition with recycling waste diversion and disposal, site supervision, quality management, security clearances for workers (HSPD-12) badging and other related services. Related services shall include, but are not limited to, delivery and staging sequencing through coordination with GSA Building Management, permitting, industrial safety and monitoring, and all necessary inspection services during construction, commissioning and potentially other related additional requirements.


The estimated cost for construction is between $15,000,000.00 and $25,000,000.00. The award of a firm-fixed price contract is anticipated to be made in July 2016. The award is subject to the availability of funds.


Procurement Details:
This procurement is a full and open procurement. GSA intends to award a firm-fixed price contract to a general contractor utilizing the best-value trade-off process in a competitive procurement. This One-Stage procurement process for the Construction Contract will be based upon evaluation criteria developed pursuant to the Federal Acquisition Regulation (FAR) Subpart 36.2 SPECIAL ASPECTS FOR CONSTRUCTION CONTRACTING and FAR subpart 15.3 SOURCE SELECTION.


The Government invites all interested responsible parties to submit a proposal. The solicitation shall be prepared in accordance with FAR Part 15 and include evaluation factors, developed in accordance with FAR 15.304. The solicitation will require submission of technical and price proposals, which shall be evaluated separately in accordance with FAR Part 15. The Government will reserve the right to make an award upon the basis of the initial technical and price proposals without discussions. Per FAR 28.102, Performance and Payment Bonds will be required by the successful Offeror in the penal amount of 100 percent of the original contract price.


The Government will award a contract resulting from this Solicitation to the responsible Offeror whose offer conforming to the Solicitation will be the best value to the Government, Total Evaluated Price and other factors considered. In addition to Total Evaluated Price, the following non-price factors shall be used to evaluate offers. They are listed in descending order of importance.
(1) Experience on Similar Project
(2) Experience of Key Personnel
(3) Past Performance on Similar Projects
(4) Small Business Subcontracting Plan


Non-Price Factors, when combined, are more important than Total Evaluated Price.


Although not mandatory, firms are encouraged to affix their names to the Interested Vendors Listing for this requirement and register to receive notifications.


There will be a pre-proposal conference scheduled for:
9:00am - 12pm
Thursday, April 7, 2016
Philip J. Burton Federal Building and Courthouse
Arizona Room
450 Golden Gate Avenue, 2nd Floor
San Francisco, California, 94102


Interested parties must notify the Contracting Officer for further information about attendance and to confirm location, time, and date. Only those parties who have notified the Contracting Officer and provided necessary information in advance of the meeting will be allowed to attend. To request a reasonable accommodation due to a disability, contact the Contracting Officer. The Pre-proposal conference and site walk are not mandatory. Please bring a valid Government Issued Identification card (i.e. valid Drivers License) as it is required to enter the Federal Building.


Site Walk:


The site walk will follow the pre-proposal conference on April 7th. There will be a second site walk date on Friday, April 8, 2016 at 10am. Interested parties must notify the Contracting Officer 2 days in advance before attending the site walk so escorts can be made available.


Proposal due date:


In order to be considered for award, offers conforming to the requirements of the solicitation must be received at the following office no later than 4:00 pm Pacific Standard Time on the following date and at the following address:


Date: Thursday May 12, 2016
Address: 50 United Nations Plaza, 3rd floor Room 3685, San Francisco, California 94102


Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.


Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.

The past performance survey has been attached to this notice for the bidders convenience. 

Files

Show all 20

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors