This solicitation from the Bureau of Land Management seeks construction services to repair the South Fork Dry Blood Dam located in Petroleum County, Montana. The contractor will be responsible for dewatering, excavating portions of the existing dam, reconstructing the embankment with fill and erosion protection, constructing a new principal spillway, outlet conduit and auxiliary structures, installing road gravel and fencing, and reclaiming disturbed areas. Proposals will be evaluated based on technical qualifications, past performance, and price. The deadline for questions is July 22nd and completed proposals are due by August 5th.

The contract is set aside for total small businesses and has a NAICS code of 237990 with a PSC code of R404. The estimated value is between $1-5 million to be completed within 230 days of the notice to proceed. Work will be performed at the South Fork Dry Blood Dam approximately 14 miles north of Winnet, Montana.

Notice text

The Bureau of Land Management (BLM) has a construction requirement for all labor, materials, equipment, and supervision to repair South Fork Dry Blood Dam located in Petroleum County, approximately 14 miles north of Winnet, MT. The requirement entails the following significant tasks:

1. Dewater reservoir and construction area.
2. Excavate a portion of the existing dam embankment and foundation to remove the existing primary spillway.
3. Reconstruct the dam embankment, including:
a. Placement of compacted fill from onsite borrow sources,
b. Placement of compacted lime amended fill,
c. Placement of imported erosion protection within excavated areas of the upstream face,
d. Placement of erosion protection matting within excavated areas of the downstream face,
e. Placement and compaction of imported sand and gravel for internal filter and drain features.
4. Construct a precast concrete spillway riser for a new principal spillway.
5. Construct concrete encased, precast reinforced concrete pipe outlet conduit.
6. Construct precast concrete low-level inlet structure.
7. Construct a grouted riprap stilling basin.
8. Place road gravel surfacing along the crest of the dam.
9. Construct a temporary construction access road from Valentine Rd. to the dam embankment crest, as necessary.
10. Construct improvements to the auxiliary spillway upstream and downstream of the dam centerline.
11. Remove existing barb wire fencing and cattle guards in the vicinity of the dam.
12. Install a cattle new cattle guard on Valentine Rd. and construct a new barb wire fence.
13. Reclaim all disturbed areas, including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding.

Files

Notice history

Notice Type Posted
Gaoa SFK dry blood DAM reconstruction Award Award Notice
This notice Latest solicitation Solicitation
South Fork Dry Blood Dam Reconstruction Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Cableway crane refurbishment NAICS 237990 Bureau of Reclamation No set-aside
Sources Sought:Neopit Dam Remediation Construction NAICS 237990 Central Office No set-aside
4 GAOA Flaming Gorge Water System Buckboard in Ashley NF, Wyoming Mc Kinnon, Wyoming 82935, United States · NAICS 237110 Forest Service Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors