GAOA Lava River Cave Trail Construction

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
1240BH21Q0008
Agency
Region 6 - Pacific Northwest Region Forest Service, Department of Agriculture
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z2PA Repair Or Alteration Of Recreation Facilities (Non-Building)
Place of performance
Bend OR 97701, United States

Notice details come from SAM.gov. Updated .

Notice text

7 versions

Update #7 · Latest ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

03/18/2021:  Amendment #2 issued.

03/20/2021:  Amendment #3 issued.

03/29/2021:  Amendment #4 issued.

04/01/2021:  Amendment #5 issued.

04/07/2021:  Amendment #6 issued.

Update #6 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

03/18/2021:  Amendment #2 issued.

03/20/2021:  Amendment #3 issued.

03/29/2021:  Amendment #4 issued.

04/01/2021:  Amendment #5 issued.

Update #5 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

03/18/2021:  Amendment #2 issued.

03/20/2021:  Amendment #3 issued.

03/29/2021:  Amendment #4 issued.

Update #4 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

03/18/2021:  Amendment #2 issued.

03/20/2021:  Amendment #3 issued.

Update #3 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

03/18/2021:  Amendment #2 issued.

Update #2 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

03/15/2021:  Amendment #1 issued.

Update #1 ·

The Lava River Cave Trail project involves replacement of the existing perimeter fence surrounding the cave sink and replacement of the existing asphalt trail, benches and handrails within the cave sink with a new concrete trail, benches and handrails.  Solicitation documents attached.

Attachments

Show all 13

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
GAOA Lava River Cave Trail Construction Award Award Notice
GAOA Lava River Cave Trail Construction This notice · Latest solicitation Solicitation
GAOA Lava River Cave Trail Construction Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity