Fort randall private office renovation

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9128F23Q0001
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Pickstown, South Dakota 57367, United States

Notice details come from SAM.gov. Updated .

Notice text

9 versions

Update #9 · Latest ·

**9 FEB 23 - AM0008  - Specifications Modified, Quote Due and Contract Completion Extended**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #8 ·

**3 FEB 23 - AM0007  - Specifications Modified**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #7 ·

**2 FEB 23 - AM0006  - Extend the Quote Due Date and Contact Competion Date**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #6 ·

**27 JAN 23 - AM0005  - Extend the Quote Due Date with changes to the specifications and drawings**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #5 ·

**18 JAN 23 - AM0004  - Extend the Quote Due Date and Extend the Contract Completion Date**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #4 ·

**12 JAN 23 - AM0003  - Davis Bacon General Decision Number SD20220010 Updated**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #3 ·

**6 JAN 23 - AM0002  - Specfications and Drawings Modified Notice**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #2 ·

**3 JAN 23 - AM0001 rescheduling site visit and extending quote due date is posted**

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Update #1 ·

In preparation for the increased Construction Division support during the Fort Randall – Major

Unit Rehab, two of the private offices will be subdivided in the Fort Randall Powerhouse

Administration Area. This will provide an additional private office and cubicle workspace for

Construction Division personnel.

The second-floor office space at Fort Randall Dam is in need of a renovation in order to

accommodate the temporary placement of additional construction division personnel. The

renovation includes the installation of demountable walls in two private offices, as well as the

installation of a demountable wall in the open space between the elevators and the bathrooms. In

order to create workable office space this renovation will also include masonry rework of an

existing wall to add a door opening. One of the office spaces will also require the removal of an

existing door from its frame. Lighting fixtures will be replaced, and lighting controls will be

updated to accommodate the demountable walls. Additional receptacles and communication

drops will be installed to accommodate the increase of workstations. Smoke detectors and

audible notification devices integrated into the fire alarm systems will be installed. New

emergency exit signage will be installed. Existing ductwork will be modified to provide

additional supplies and returns.

In accordance with FAR 36.204, the estimated price of this project is between $100,000 and $250,000.

Files

Show all 23

Notice history

Notice Type Posted
Fort randall private office renovation Award Award Notice
This notice Latest solicitation Solicitation
Fort randall private office renovation Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors