Flagler County Coastal Storm Risk Management (CSRM) Project – City of Flagler Beach, Florida
Closed Special Notice Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912EP24Z0005
- Agency
-
ENDIST Jacksonville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
- Place of performance
- Flagler Beach, Florida, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Special Notice was published by the U.S. Army Corps of Engineers Engineering District Jacksonville to provide an industry overview for the initial construction of the Flagler County, Florida Coastal Storm Risk Management Project within the City of Flagler Beach. The project involves beach nourishment and dredging services with an anticipated value between $25-100 million.
The Notice announces an Industry Day on December 13, 2023 to brief contractors on the project scope which includes placement of 1.3 million cubic yards of sand and construction of dunes and vegetation across 3 miles of shoreline. Interested contractors must submit company information and size classification to the Corps by December 12th to participate in breakout sessions at the Industry Day where they can provide feedback and have questions addressed. The solicitation for the project will be issued under NAICS Code 237990 with a $45 million small business threshold. Bids are due by April 1, 2024 and the awarded contract is expected to be completed by March 2025.
Notice text
3 versions
Update #3 · Latest ·
The purpose of this Industry Day is to provide an overview to the dredging industry regarding initial construction of the Flagler County, FL CSRM Project within the City of Flagler Beach, Florida. This will be in-person only w/no streaming webinar.
DATE: Wednesday, December 13, 2023.
TIME: 09:00 pm – 03:00 PM EST
LOCATION: City of Flagler Beach - City Hall Main Conference Room - 105 S 2nd Street Flagler Beach, FL 32136 (Parking Available in Public Parking Lots around City Hall)
NAICS Code 237990: Other Heavy and Civil Engineering Construction
Small Business Standard: $45 million
Magnitude of Construction: between $25,000,000.00 and $100,000,000.00.
This is a SAVE-THE-DATE special notice. Draft plans and specifications will be uploaded along with a list of questions to be used during contractor breakout sessions to the SAM.gov website under the subject Notice ID. All interested Offerors are required to access SAM.gov for future updates. (Draft Plans and Specifications have been uploaded)
DESCRIPTION:
The agenda includes:
9:00 am – 9:30 am (Arrival/Meet and Greet)
9:30 am – 10:30 am (Formal Presentation by USACE Team)
- Project Management Overview – Jason Harrah (Project Manager)
- Engineering Overview – Rosie Pinto (Engineering Technical Lead)
- Environmental Overview – Lindsay Brantley/Julia Lombardo (Environmental Leads)
- Construction Overview (i.e. sequence of work, etc.) Paul Cotter and/or Gavin Jackson (Area Engineer and Resident Engineer)
- Contracting Overview Manuela Voicu, Guesley Leger
- Nearby Projects Overview – Jason Harrah (Project Manager)
- Sponsor Remarks (Flagler County and/or City of Flagler Beach Representatives)
10:30 am – 11:00 am Open Q&A Regarding Formal Presentation
11:00 am – 12:30 pm Lunch Break and Contractors can visit the project site, look at staging areas, beach access, etc.
12:30 pm – 3:00 pm Prime Contractor Breakout Sessions - Depending on how many contractors we have this could be shortened, but we will have 30 min breakout sessions with each prime contractor individually to solicit feedback of the project with 5 specific questions pre-determined by the project delivery team. If we only have a few contractors this could end sooner. This will be decided the day of the meeting based on how many contractors show up.
If interested in attending this event, firms can register utilizing sign-up sheet of paper on the desk as you walk in the conference room with 30 min time slots where contractors should write their names down on a first come first serve basis and request a 30-minute breakout session to answer the Government’s questions. Please indicate your preferred time slot between 1230 – 3 pm. Times cannot be guaranteed and specified times will be provided before the 11:00 am break.
Breakout Session Questions:
- What concerns do you have with the proposed accesses and road closure schedule coordinated with FDOT and Local Sponsor?
- Will upland sand source be necessary for access and working pad construction for access off of A1A?
- Any concerns with obtaining and operating under a FDOT permit for the portions designated on A1A and FL 100?
- Is the schedule for portion of the work north/south of the pier achievable given the road closure and access schedule provided?
- Concerns with adjacent projects (i.e. seawall, pier construction, paving)?
ADDITIONAL INFORMATION REQUIRED:
Provide an email to Mr. Jason Harrah at jason.s.harrah@usace.army.mil, Ms. Manuela Voicu at Manuela.d.voicu@usace.army.mil, and Mr. Guesley Leger at guesley.leger@usace.army.mil to include the information listed below:
1. Company Name
2. Point of Contact
3. Company Address
4. Phone Number
5. Email Address
6. Duns Number
7. Cage Code
8. Offeror shall identify their size classification and Small Business Size:
-Large Business
-Small Business
-Small Disadvantage Business
-8(a) Small Business
-HUBZone
-SDVOSB
-WOSB
Your email subject line should be addressed as "Industry Day Request (Company Name) - Industry Day Notice: Flagler County Coastal Storm Risk Management Project in order to ensure all requests are handled in a timely manner. The required information is due to Mr. Jason Harrah, Ms. Manuela Voicu, and Mr. Guesley Leger no later than 12 December 2023 at 2:00pm EST.
NOTES:
DO NOT SUBMIT A RESPONSE TO THIS NOTICE IF YOU DO NOT INTEND TO SUBMIT A PROPOSAL ON THIS PROJECT.
DO NOT RESPOND TO QUESTIONS UNTIL YOUR SCHEDULED BREAKOUT SESSION.
DO NOT SUBMIT PROPRIETARY AND/OR BUSINESS CONFIDENTIAL DATA.
NO REIMBURSEMENT WILL BE MADE FOR ANY COST ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO SAID NOTICE, ATTENDANCE AT THE INDUSTRY DAY EVENT OR ANY FOLLOW-UP INFORMATION SUBSEQUENTLY REQUESTED.
Update #2 ·
The purpose of this Industry Day is to provide an overview to the dredging industry regarding initial construction of the Flagler County, FL CSRM Project within the City of Flagler Beach, Florida. This will be in-person only w/no streaming webinar.
DATE: Wednesday, December 13, 2023.
TIME: 09:00 pm – 03:00 PM EST
LOCATION: City of Flagler Beach - City Hall Main Conference Room - 105 S 2nd Street Flagler Beach, FL 32136 (Parking Available in Public Parking Lots around City Hall)
NAICS Code 237990: Other Heavy and Civil Engineering Construction
Small Business Standard: $45 million
Magnitude of Construction: between $25,000,000.00 and $100,000,000.00.
This is a SAVE-THE-DATE special notice. Draft plans and specifications will be uploaded along with a list of questions to be used during contractor breakout sessions to the SAM.gov website under the subject Notice ID. All interested Offerors are required to access SAM.gov for future updates.
DESCRIPTION:
The agenda includes:
9:00 am – 9:30 am (Arrival/Meet and Greet)
9:30 am – 10:30 am (Formal Presentation by USACE Team)
- Project Management Overview – Jason Harrah (Project Manager)
- Engineering Overview – Rosie Pinto (Engineering Technical Lead)
- Environmental Overview – Lindsay Brantley/Julia Lombardo (Environmental Leads)
- Construction Overview (i.e. sequence of work, etc.) Paul Cotter and/or Gavin Jackson (Area Engineer and Resident Engineer)
- Contracting Overview Manuela Voicu, Guesley Leger
- Nearby Projects Overview – Jason Harrah (Project Manager)
- Sponsor Remarks (Flagler County and/or City of Flagler Beach Representatives)
10:30 am – 11:00 am Open Q&A Regarding Formal Presentation
11:00 am – 12:30 pm Lunch Break and Contractors can visit the project site, look at staging areas, beach access, etc.
12:30 pm – 3:00 pm Prime Contractor Breakout Sessions - Depending on how many contractors we have this could be shortened, but we will have 30 min breakout sessions with each prime contractor individually to solicit feedback of the project with 5 specific questions pre-determined by the project delivery team. If we only have a few contractors this could end sooner. This will be decided the day of the meeting based on how many contractors show up.
If interested in attending this event, firms can register utilizing sign-up sheet of paper on the desk as you walk in the conference room with 30 min time slots where contractors should write their names down on a first come first serve basis and request a 30-minute breakout session to answer the Government’s questions. Please indicate your preferred time slot between 1230 – 3 pm. Times cannot be guaranteed and specified times will be provided before the 11:00 am break.
Breakout Session Questions:
- What concerns do you have with the proposed accesses and road closure schedule coordinated with FDOT and Local Sponsor?
- Will upland sand source be necessary for access and working pad construction for access off of A1A?
- Any concerns with obtaining and operating under a FDOT permit for the portions designated on A1A and FL 100?
- Is the schedule for portion of the work north/south of the pier achievable given the road closure and access schedule provided?
- Concerns with adjacent projects (i.e. seawall, pier construction, paving)?
ADDITIONAL INFORMATION REQUIRED:
Provide an email to Mr. Jason Harrah at jason.s.harrah@usace.army.mil, Ms. Manuela Voicu at Manuela.d.voicu@usace.army.mil, and Mr. Guesley Leger at guesley.leger@usace.army.mil to include the information listed below:
1. Company Name
2. Point of Contact
3. Company Address
4. Phone Number
5. Email Address
6. Duns Number
7. Cage Code
8. Offeror shall identify their size classification and Small Business Size:
-Large Business
-Small Business
-Small Disadvantage Business
-8(a) Small Business
-HUBZone
-SDVOSB
-WOSB
Your email subject line should be addressed as "Industry Day Request (Company Name) - Industry Day Notice: Flagler County Coastal Storm Risk Management Project in order to ensure all requests are handled in a timely manner. The required information is due to Mr. Jason Harrah, Ms. Manuela Voicu, and Mr. Guesley Leger no later than 12 December 2023 at 2:00pm EST.
NOTES:
DO NOT SUBMIT A RESPONSE TO THIS NOTICE IF YOU DO NOT INTEND TO SUBMIT A PROPOSAL ON THIS PROJECT.
DO NOT RESPOND TO QUESTIONS UNTIL YOUR SCHEDULED BREAKOUT SESSION.
DO NOT SUBMIT PROPRIETARY AND/OR BUSINESS CONFIDENTIAL DATA.
NO REIMBURSEMENT WILL BE MADE FOR ANY COST ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO SAID NOTICE, ATTENDANCE AT THE INDUSTRY DAY EVENT OR ANY FOLLOW-UP INFORMATION SUBSEQUENTLY REQUESTED.
Update #1 ·
The purpose of this Industry Day is to provide an overview to the dredging industry regarding initial construction of the Flagler County, FL CSRM Project within the City of Flagler Beach, Florida. This will be in-person only w/no streaming webinar.
DATE: Wednesday, December 13, 2023.
TIME: 09:00 pm – 03:00 PM EST
LOCATION: City of Flagler Beach - City Hall Main Conference Room - 105 S 2nd Street Flagler Beach, FL 32136 (Parking Available in Public Parking Lots around City Hall)
NAICS Code 237990: Other Heavy and Civil Engineering Construction
Small Business Standard: $45 million
Magnitude of Construction: between $25,000,000.00 and $100,000,000.00.
This is a SAVE-THE-DATE special notice. Draft plans and specifications will be uploaded along with a list of questions to be used during contractor breakout sessions to the SAM.gov website under the subject Notice ID. All interested Offerors are required to access SAM.gov for future updates.
DESCRIPTION:
The agenda includes:
9:00 am – 9:30 am (Arrival/Meet and Greet)
9:30 am – 10:30 am (Formal Presentation by USACE Team)
- Project Management Overview – Jason Harrah (Project Manager)
- Engineering Overview – Rosie Pinto (Engineering Technical Lead)
- Environmental Overview – Lindsay Brantley/Julia Lombardo (Environmental Leads)
- Construction Overview (i.e. sequence of work, etc.) Paul Cotter and/or Gavin Jackson (Area Engineer and Resident Engineer)
- Contracting Overview Manuela Voicu, Guesley Leger
- Nearby Projects Overview – Jason Harrah (Project Manager)
- Sponsor Remarks (Flagler County and/or City of Flagler Beach Representatives)
10:30 am – 11:00 am Open Q&A Regarding Formal Presentation
11:00 am – 12:30 pm Lunch Break and Contractors can visit the project site, look at staging areas, beach access, etc.
12:30 pm – 3:00 pm Prime Contractor Breakout Sessions - Depending on how many contractors we have this could be shortened, but we will have 30 min breakout sessions with each prime contractor individually to solicit feedback of the project with 5 specific questions pre-determined by the project delivery team. If we only have a few contractors this could end sooner. This will be decided the day of the meeting based on how many contractors show up.
If interested in attending this event, firms can register utilizing sign-up sheet of paper on the desk as you walk in the conference room with 30 min time slots where contractors should write their names down on a first come first serve basis and request a 30-minute breakout session to answer the Government’s questions. Please indicate your preferred time slot between 1230 – 3 pm. Times cannot be guaranteed and specified times will be provided before the 11:00 am break.
ADDITIONAL INFORMATION REQUIRED:
Provide an email to Mr. Jason Harrah at jason.s.harrah@usace.army.mil, Ms. Manuela Voicu at Manuela.d.voicu@usace.army.mil, and Mr. Guesley Leger at guesley.leger@usace.army.mil to include the information listed below:
1. Company Name
2. Point of Contact
3. Company Address
4. Phone Number
5. Email Address
6. Duns Number
7. Cage Code
8. Offeror shall identify their size classification and Small Business Size:
-Large Business
-Small Business
-Small Disadvantage Business
-8(a) Small Business
-HUBZone
-SDVOSB
-WOSB
Your email subject line should be addressed as "Industry Day Request (Company Name) - Industry Day Notice: Flagler County Coastal Storm Risk Management Project in order to ensure all requests are handled in a timely manner. The required information is due to Mr. Jason Harrah, Ms. Manuela Voicu, and Mr. Guesley Leger no later than 12 December 2023 at 2:00pm EST.
NOTES:
DO NOT SUBMIT A RESPONSE TO THIS NOTICE IF YOU DO NOT INTEND TO SUBMIT A PROPOSAL ON THIS PROJECT.
DO NOT RESPOND TO QUESTIONS UNTIL YOUR SCHEDULED BREAKOUT SESSION.
DO NOT SUBMIT PROPRIETARY AND/OR BUSINESS CONFIDENTIAL DATA.
NO REIMBURSEMENT WILL BE MADE FOR ANY COST ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO SAID NOTICE, ATTENDANCE AT THE INDUSTRY DAY EVENT OR ANY FOLLOW-UP INFORMATION SUBSEQUENTLY REQUESTED.
Files
Notice history
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Pass-a-grille-pass, maintenance dredging, pinellas county, florida | ENDIST Jacksonville | Total Small Business | |
| St. Lucie South Jetty Repair Industry Day | ENDIST Jacksonville | No set-aside | |
| Beach Renourishment, Kennedy Space Center, Brevard County, Florida | ENDIST Jacksonville | No set-aside | |
| Tampa Harbor Improvements Industry Day | ENDIST Jacksonville | No set-aside | |
| Delaware Avenue Revetment, Cape May, NJ | ENDIST Philadelphia | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity