A.02 Flagler County, FL CSRM Project Industry Day Presentation - 5DEC 2023 UPDATED.pdf
PDF 6 MB Posted
- Attached to
- Flagler County Coastal Storm Risk Management (CSRM) Project – City of Flagler Beach, Florida
- Solicitation number
- W912EP24Z0005
About this file
This presentation outlines requirements for a coastal storm risk management project in Flagler County, Florida. The U.S. Army Corps of Engineers seeks bids for beach nourishment along 3 miles of shoreline including placement of 1.3 million cubic yards of sand and construction of dunes and vegetation. Bids are due by April 1, 2024 under solicitation W912EP24Z0005 with award by May 2nd and work completion by March 2025. The federal share is 65% with non-federal sponsor Flagler County contributing 35% for initial construction and 50% for periodic renourishment every 11 years. Staging areas will be required at Veterans Park, 6th Street, and a homeowners' area with road closures and detours planned. The project involves coordination with adjacent pier and seawall work. Subcontracting opportunities may exist for environmental monitoring, surveying, and dune planting.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Flagler County, FL Coastal Storm Risk Management (CSRM) Project
INDUSTRY DAY PRESENTATION
DECEMBER 13, 2023
Presented by: Jacksonville District, U.S. Army Corps of Engineers Non-Federal Sponsor: Flagler County Board of County Commissioners
AGENDA
9:00 AM – 9:30 AM Arrival/Sign In/Meet and Greet
9:30 AM – 10:30 AM Formal Presentation by USACE
10:30 AM – 11:00 AM Q&A from Presentation
11:00 AM – 1:00 PM Contractor Site Visit/Lunch
1:00 PM – 3:00 PM Prime Contractor Breakout Sessions
FEDERAL BEACH PROJECT OVERVIEW
Presented by: Jason Harrah, Project Manager
Trusted Partners Delivering Value Today for a Better Tomorrow
BUILDING STRONG
Project Benefits:
$2.4M Average Annual
Benefits Benefit to Cost Ratio
1.9:1 ~3.2 acres of environmental habitat created
95% reduction in damages through
FEDERAL BEACH PROJECT OVERVIEW
Non-Federal Sponsor: Flagler County Board of County Commissioners Project Limits: ~3 miles (7th St. South to 28th St. South) Project Features: Beach Berm, Dune, Vegetation, Signage Construction Intervals: Initial Construction (2024), Emergency Renourishments (after major storm events (as approved), regular renourishments ~every 11 years (2035, 2046, 2057, 2068).
Project Cost Share: 65% Fed, 35% Non-Fed for Initial, 50%/50% Renourishments, 100% Fed for Emergency Events.
Design Details:
Dune Height: +19.0’ Dune Width: Varies Berm Width: 140’ Dune Vegetation: Sea Oats, Bitter Panic-grass, Railroad Vine, Dune Sunflower Volume of Sand Placed: 1.3M cubic yards
7th St.
North
7th St.
South
28th St.
South
Gamble Rodgers
State Park
Non- Federal Section 120,000 cubic yards of sand
Federal Section
1,310,000 cubic yards of sand
Offshore Borrow Area
3A
PROJECT OVERVIEW
Non- Federal Section 150,000 cubic yards of sand
CONTRACTOR STAGING AREAS & BEACH ACCESS
Staging/Access #1 Veterans Park
Staging/Access #2 6th St. South
Staging/Access #3 Pebble Beach HOA
Staging Only #4 Water Tower Area
#1 #2 #3 #4
Beach Nourishment (7th St. North – Gamble Rodgers SP) Hotel Construction (near Veterans Park) FDOT Asphalt Resurfacing (8th St. South – 18th St. North) Pier Rehabilitation FDOT Secant Wall Construction(~ South near Gamble
Rodgers State Park towards Volusia County)
Courtesy of Research Gate
FLAGLER BEACH IS GOING TO BE BUSY!!!
PUBLIC OUTREACH DURING CONSTRUCTION
Social Media USACE Website
Contractor Updates
KEY DATES
Activity Schedule Plans & Specs Certified by USACE January 26, 2024
Contract Advertised (IFB) February 29 – April 1, 2024 Bid Opening April 1, 2024
Contract Award May 2, 2024 Contractor Mobilization July 5, 2024
Construction Completion March 2025
DESIGN OVERVIEW
Presented by: Rosie Pinto, P.E. - Engineering Technical Lead
Beach Fill Layout
Atlantic Ocean
Borrow Area 3A
-5
EL
EV
A
TIO
N (F
T- N
A V
D
150 250 350 450200 300 400
2023 Existing Beach
Equilibrated Profile
State Road A1A
Federal 2023 Construction Template
(Not to Scale)
140’
1V:2.5H
1V:35H
1V:10H
Exposed Revetment
DISTANCE FROM R-MONUMENT (FT)
FOR DISCUSSION PURPOSES ONLY
DESIGN PROFILE – FEDERAL REACH
NOT TO SCALE
Elev. +19’
Elev. +11’
Elev. +7’
Estimated Volume: 1,315,000 cubic yards
-5
EL
EV
A
TIO
N (F
T- N
A V
D
150 250 350 450200 300 400
2023 Existing Beach
Equilibrated Profile
State Road A1A
Non-Federal 2023 Construction Template
(Not to Scale)
100’
1V:3H 1V:50H
1V:15H
DISTANCE FROM R-MONUMENT (FT)
FOR DISCUSSION PURPOSES ONLY
CONSTRUCTION PROFILE – FEDERAL REACH
NOT TO SCALE
Elev. +11’
Elev. +8’
Elev. +10’
Estimated Volume: 270,000 cubic yards
WALKOVERS AND ARMORING
FILL AROUND WALKOVERS
Before
Construction After
Construction
DUNE PLANTING – FEDERAL REACH
Typical Dune Planting Cross Section
Typical Dune Planting Staggered Layout
Estimated Number of Plants: 330,000 Non-Federal Reach includes vegetating dune crest only
KEY DESIGN TAKAWAYS
Two construction templates = two separate permits One offshore borrow area Truck haul may be required in areas of the non-federal project to build up for staging and access.
Dune vegetation Sand fencing MEC screening on the beach and onsite support Hand tools may be required for work around walkovers
ENVIRONMENTAL OVERVIEW
Presented by: Julia Lombardo & Lindsay Brantley
• Threatened and Endangered (T&E) Species
Must comply with USFWS & NMFS: South Atlantic Region Biological Opinion (SARBO), Statewide Programmatic Biological Opinion (SPBO), Programmatic Piping Plover Biological Opinion (P3BO)
– Endangered/Protected Species Observer (ESO/PSO) – required to have 24-hr monitoring via observers watching for T&E in the water and entrained in the dredge (i.e., dragheads, screening, boxes, etc.)
– Relocation Trawling – not required; may be implemented on an as needed basis
– Nesting Marine Sea Turtles – surveys/relocations required April 15 through October 31
– Nesting surveys/relocations must start 65 days prior to construction if any beach work will occur during the April 15 – October 31 timeframe
Source: https://www.visitflagler.com/blog/post/witness-a-florida-phenomenon-turtle-nesting-season/
ENVIRONMENTAL COMPLIANCE
• Other Protected Species
Must comply with the Marine Mammal Protection Act of 1972, Migratory Bird Treaty and Migratory Bird Conservation Act, and other Florida State Laws
– Marine Mammals – Prohibits “take” of whales (blue, fin, sei, sperm), dolphins and porpoises, Florida manatees, etc.
– Shorebirds - shorebird protection/monitoring required during nesting/breeding seasons (February 15 - September 1)
– Active Gopher tortoise burrows present in project area – surveys and relocations are required to be completed prior to the start of construction and monitoring/relocations during construction
• Cultural Resources
– Must maintain 3 avoidance buffers within the nearshore placement area (100 ft for 2 targets, 150 ft for 1 target) in accordance with project specifications
Source: https://www.visitflagler.com/beaches/
ENVIRONMENTAL COMPLIANCE
Federal Project Description (FDEP Permit No.: 0378136-002-JM):
• The project consists of restoration and nourishment of approximately 2.6 miles of federally authorized shoreline.
• Sand will be sourced from Federal Borrow Area 3A.
• The project includes both dune and beach berm features.
Non-Federal Project Description (FDEP Permit No.: 0379716-001-JC & DA Permit No.: SAJ-2019-02065):
• The project will restore and maintain two reaches (North and South Reach) along approximately 4.1 miles of shoreline.
• Sand will be sourced from Federal Borrow Area 3A.
• The project includes both dune and beach berm features.
o A minor permit modification from FDEP is pending.
o A permit modification from the USACE Jacksonville Regulatory Office is pending.
BOEM will be issuing one combined Agreement for Borrow Area 3A.
Monitoring & Reports Required by Permits:
• ESO/PSO, trawling – if implemented, marine turtle and shorebird protections during nesting/breeding seasons, turbidity, tilling/compaction/escarpment remediation, lighting requirements, sediment QA/QC, bathymetric/topographic surveys.
ENVIRONMENTAL PERMITS & COMPLIANCE
CONSTRUCTION OVERVIEW
Presented by: Paul Cotter, P.E. Area Engineer
MAINTENANCE OF TRAFFIC OVERVIEW
The contractor is required to prepare a detailed maintenance of traffic plan for approval by the contracting officer. This maintenance of traffic plan is needed to avoid risks to the public during beach access ramp construction and ingress/egress from the staging/access areas as provided.
As part of the maintenance of traffic plan the contractor should consider the following options that have been discussed with the non-federal sponsor and Florida Department of Transportation (FDOT):
1. Beach Nourishment North of Pier: Utilization of Veterans Park Staging/Beach Access Area Construction
• Southbound Traffic on State Road A1A will detour 2nd St. North to North Flagler Ave.
• Local Resident Traffic Southbound on State Road A1A will still have vehicular access to business between 2nd St. North and Moody Blvd.
• Northbound Traffic on State Road A1A will detour 2nd St. South to South Flagler Ave.
• Northbound Semi Traffic on State Road A1A will detour 5th St. South to South Flagler Ave.
2. Beach Nourishment Immediately South of Pier: Transition from Veterans Park Staging Area to 6th St. Staging/Beach Access Area Construction
• Southbound Traffic on State Road A1A will detour to Moody Blvd. (aka Highway 100) to South Flagler Ave. to 7th St. South to SRA1A
• Northbound Traffic on State Road A1A will detour to 7th St. South to South Flagler Ave. to Moody Blvd. to SRA1A
• Local Resident Traffic Northbound on State Road A1A will still have vehicular access to business between 7th St. South and 6th St. South
• Road Closures will be placed at 6th St. South/SRA1A, 5th St. South/SRA1A, 4th St. South/SRA1A, 3rd St. South/SRA1A, 3rd St. South/SRA1A and 2nd St. South/SRA1A to avoid crossover into the work area located along SR A1A
• The contractor shall expedite beach ramp construction in this area and once equipment is fully mobilized to the beach, all road closures/signage will be removed with full vehicular access restored
3. Beach Nourishment South of Pier: Transition to Pebble Beach HOA Staging/Beach Access Area Construction
• No road closures are anticipated for this area
• Reduced Speed Zones (45mph to 35 mph) will be established for Northbound and Southbound Traffic along State Road A1A
LOCAL TRAFFIC ONLY
STAGING AREA #1 AT VETERANS PARK
Available 5 July 2024 – 15 Dec. 2024
Restore to Pre-Project Conditions
ROAD BARRICADE
Start: 5 July 2024 Local Traffic Only
FENCED PEDESTRIAN
ACCESS
ROAD BARRICADE
Start: 5 July 2024
No Thru Traffic
BEACH ACCESS RAMP #1
Upland Sand May be Required
Access Near Road to be Restored to Pre-Project Conditions
SECURITY FENCE
ROAD BARRICADE
Start: 5 July 2024
End: 30 September 2024 No Thru Traffic
BEACH ACCESS #1
Special Conditions
1. Police Escort
2. Mats for tract equipment
ROAD DETOUR to FLAGLER AVE.
Starting 5 July 2024
TRUCKS USE 5TH ST. SOUTH TO
FLAGLER AVE.
PEDESTRIAN
ACCESS
ROAD BARRICADE
Start: 5 July 2024 Local Traffic Only
ROAD BARRICADE
Start: 5 July 2024
No Thru Traffic
ROAD DETOUR to North Flagler Ave.
Starting 5 July 2024
FENCED PEDESTRIAN
ACCESS
BEACH ACCESS
RAMP #1
N 2ND ST
US 100
ROAD BARRICADE
Approximate Closure: 30 Sept. – 15 Oct. 2024
Local Traffic Only
STAGING AREA #2
AT 6TH ST.
Available 5 July 2024 – End of Construction
BEACHFILL NORTH OF 6TH ST. MUST
BE COMPLETED 15 OCT. 2024
SUBLINE LANDING
Approximately 700 feet south of the Pier
S 5
TH
ST
S 6
TH
ST
S 4
TH
ST
BEACH ACCESS RAMP #2
Upland Sand May be Required
Access Near Road to be Restored to Pre-Project Conditions
Special Conditions
1. Police Escort
2. Mats for tract equipment
Required: FDEP/DA Permit Mod
ROAD BARRICADE
Approximate Closure:
30 Sept. – 15 Oct. 2024 No Thru Traffic
PIER CONSTRUCTION
Anticipated Start: 15 Oct. 2024
PIER CONSTRUCTION TRUSSELL
Approximate Limits
ROAD CLOSURE OF A1A FOLLOWING COMPLETION OF FILL NORTH OF THE PIER
Approximate Closure: 30 Sept. – 15 Oct. 2024
ROAD BARRICADE
Approximate Closure:
30 Sept. – 15 Oct. 2024 No Thru Traffic
SECURITY FENCE
ROAD DETOUR to
7TH ST. TO FLAGLER AVE.
FILL NORTH OF 6TH ST. MUST BE COMPLETED 15 OCT 2024
SEE SLIDE 3 & 4 SEE SLIDE 5
FLAGLER AVE
ROAD BARRICADE
Approximate Closure:
30 Sept. – 15 Oct. 2024
POTENTIAL ROAD DETOUR
REDUCE SPEED
45mph to 35 mph
LOADING/OFFLOADING
AREA
1200 AM – 1000 AM
Required: ROW Permit
FENCED PEDESTRIAN
ACCESS FOR HOA
RESIDENTS
REDUCE SPEED
45mph to 35 mph
BEACH ACCESS RAMP #3
Upland Sand May be Required
GATE WITH LOCK
Provide Key to HOA President SECURITY FENCE
STAGING AND ACCESS AREA #3 AT PEBBLE BEACH HOA
Available Full Duration of the Contract
Access Near Road to be Restored to Pre-Project Conditions
STAGING AREA #4 AT WATER TOWER AREA
Available Full Duration of the Contract
Access Near Road to be Restored to Pre-Project Conditions
SECURITY FENCE
A1A
BEACH CONSTRUCTION – IN STEPS
7th St.
North
Step #1 Construct Beach
North of Pier
Veterans Park Staging/Access Area
Beach Ramp Construction
Road Closures Along A1A and Adjacent Roads
Pier
July – 15 Oct 2024
7th St.
South
Step #2 Construct Beach South of Pier
6th St. South Park Staging/Access Area
Beach Ramp Construction
Add’l. Road Closures Along A1A and Adjacent Roads
15 Oct 2024
28th St.
South
Step #3 Federal Project
7th St. South to 28th St. South
6th St. South Park Staging/Access Area transition to Pebble Beach HOA Staging/Access Area
Beach Ramp Construction at Pebble Beach HOA
Road Closures Along A1A End (Once Blue Areas Constructed)
Nov 2024 – Feb 2025
Gamble Rodgers
State Park
Step #3 28th St. South to Gamble Rodgers State
Park
Pebble Beach HOA Staging/Access Area
Reduced Speed Zoners Use of Water Tower Area Demobilize from this Site
Feb 2025 – Mar 2025
Pier Contractor Mobilizes
Mid-Oct 2024
CONTRACTING OVERVIEW
Presented by: Manuela Voicu, Contracting Officer and Team
PROCUREMENT STRATEGY
Guesley Leger, Contract Specialist
Email: guesley.leger@usace.army.mil Phone: (904) 232-3850
BUILDING STRONG®
ACQUISITION METHOD
– FAR Part 14 - Sealed bidding
Sealed bidding is a method of contracting that employs competitive bids, public opening of bids, and awards.
ACQUISITION METHOD
– FAR Part 14 - Sealed bidding
Submission of bids. Bidders must submit sealed bids to be opened at the time and place stated in the solicitation for the public opening of bids.
(d) Evaluation of bids. Bids shall be evaluated without discussions.
(e) Contract award. After bids are publicly opened, an award will be made with reasonable promptness to that responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation.
Solicitation No. W912EP24Z0005
•- Approximate Pre-Solicitation Notice Date (~15 days before advertisement): 2/14/2024
•Approximate Issue Date (Advertisement): 2/29/2024
•Approximate Bid Opening Date (30 days after advertisement):
4/01/2024
•- Anticipated Magnitude of Construction: ~$25M-$100M
•- Estimated Period of Performance (POP): ~285 Calendar Days
SOLICITATION INFO
IMPORTANT WEBSITES
System for Award Management (SAM)
• www.SAM.gov
Bidder Inquiry in ProjNet
• https://projnet.org http://www.sam.gov/ https://projnet.org/
SMALL BUSINESS OPPORTUNITIES
BUILDING STRONG®
SMALL BUSINESS OPPORTUNITIES
FAR 19.201 – Government policy
–(a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns. Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency, consistent with efficient contract performance.
– Small Business Participation
– Subcontracting Plan (Large Business concerns only)
FAR 19.701 “Subcontract”
• - Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies and/or services required for performance of the contract/or subcontract.
Breaking out contract work requirements
Performing market research Solicit early and allow sufficient time to respond Mentor-protégé program Advertising subcontracting opportunities on subnet Davis-Bacon prevailing wage rates is a FAR (contract) requirement Reach out to PTAC, SBA state, and Federal small business offices for assistance
WHAT DOES MAXIMUM PRACTICABLE
OPPORTUNITY (MPO) LOOK LIKE?
• Potential Opportunities exist for:
Various environmental monitoring requirements, such as vibration, turbidity, endangered species, etc.
Hydrographic / Beach Surveys Dune Vegetation and Planting Post / Rope / Sign Installation
SMALL BUSINESS/SUB-CONTRACTING
RESOURCES
► Systems for Award Management www.sam.gov
► Dynamic Small Business Search http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm SB firms keep profile current with bonding, past performance, and capabilities Prime contractors can use many filters to locate SDB, HUBZone, WOSB, SDVOSB specific firms and their location
Looking for Opportunities in All the Right Places!
http://www.sam.gov/ http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm
CONTACT INFORMATION
• Kimberly Danielray, Deputy for Small Business
(904) 232-1150
• Nicole Batista-Cruz, Small Business Specialist
(904) 232-3275
• Florida Procurement Technical Assistance Center ► http://www.fptac.org/contactus.htm
• Jacksonville District Website Page
• www.saj.usace.army.mil
• How do I contact Small Business?
• Upcoming Jacksonville District
Business Opportunities
• Frequently Asked Questions http://www.fptac.org/contactus.htm http://www.saj.usace.army.mil/
THANK YOU!
Corps of Engineers POC:
Jason Harrah, Senior Project Manager 904-232-1381 Jason.S.Harrah@usace.army.mil
Flagler County POC:
Amy Stroger, Project Manager 386-313-4047 astroger@flaglercounty.gov
City of Flagler Beach POC:
Dale Martin, City Manager 386-517-2000 dmartin@cityofflaglerbeach.com mailto:Jason.S.Harrah@usace.army.mil mailto:astroger@flaglercounty.gov mailto:dmartin@cityofflaglerbeach.com
CONTRACTOR SITE VISIT (11:00 – 1:00)
Staging/Access #1 Veterans Park
Staging/Access #2 6th St. South
Staging/Access #3 Pebble Beach HOA
Staging Only #4 Water Tower Area
#1 #2 #3 #4
PRIME CONTRACTOR BREAKOUT SESSIONS
1:00 – 3:00
1. What concerns do you have with the proposed accesses and road closure schedule coordinated with FDOT and Local Sponsor?
2. Will upland sand source be necessary for access and working pad construction for access off A1A?
3. Any concerns with obtaining and operating under a FDOT permit for the portions designated on A1A and FL 100?
4. Is the schedule for portion of the work north/south of the pier achievable given the road closure and access schedule provided?
5. Concerns with adjacent projects (i.e. seawall, pier construction, paving)?
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Federal Beach Project overview |
| Slide Number 5 |
| Slide Number 6 |
| FLAGLER BEACH IS GOING TO BE BUSY!!! |
| Public outreach during construction |
| Key dates |
| Slide Number 10 |
| Beach Fill Layout |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| FILL AROUND WALKOVERS |
| Dune planting – Federal Reach |
| KEY DESIGN TAKAWAYS |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
| Slide Number 26 |
| Slide Number 27 |
| Slide Number 28 |
| Slide Number 29 |
| Slide Number 30 |
| Slide Number 31 |
| Slide Number 32 |
| Slide Number 33 |
| ACQUISITION METHOD |
| ACQUISITION METHOD |
| SOLICITATION INFO |
| IMPORTANT WEBSITES |
| Slide Number 38 |
| SMALL BUSINESS OPPORTUNITIES |
| Slide Number 40 |
| SMALL BUSINESS/SUB-CONTRACTING |
| RESOURCES |
| Slide Number 43 |
| Slide Number 44 |
| Slide Number 45 |
| Slide Number 46 |