Dugway Proving Grounds Microgrid
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9123821R0045
- Agency
- ENDIST Sacramento US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Place of performance
- Dugway UT 84022, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks design and construction services for a microgrid at Dugway Proving Grounds in Utah. The Army Corps of Engineers requires a contractor to install a new battery energy storage system, supervisory control and data acquisition system, and microgrid control system to integrate an existing 12-megawatt diesel generator plant and 2-megawatt solar array at the base into a new microgrid. Proposals will be evaluated using lowest price technically acceptable criteria, with the contract awarded to the responsible offeror providing the lowest evaluated price meeting the solicitation's technical requirements. Proposals are due by June 2, 2021.
This is a total small business set-aside opportunity. The place of performance is Dugway, Utah, with the requirement for the awarded contractor to deliver a fully operational microgrid within the timeline defined in the performance work statement. Key components include integrating the existing energy assets with the new battery energy storage system and control systems to increase energy resiliency at the proving grounds.
Notice text
7 versions
Update #7 · Latest ·
****05/21/2021 - Amendment 0005 - posts updated pictures****
05/13/2021 - Amendment 0004 -Extended the propsoal due date, and includes pictures taken from the Site Visit.****
5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link
4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link
4/7/2021 - Added Site visit sign-in sheet
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #6 ·
****05/13/2021 - Amendment 0004 -Extended the propsoal due date, and includes pictures taken from the Site Visit.****
5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link
4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link
4/7/2021 - Added Site visit sign-in sheet
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #5 ·
*** Update***
5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link
4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link
4/7/2021 - Added Site visit sign-in sheet
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #4 ·
*** Update***
4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link
4/7/2021 - Added Site visit sign-in sheet
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #3 ·
*** Update***
4/7/2021 - Added Site visit sign-in sheet
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #2 ·
*** Update***
3/25/2021 - Amendment 0001- Extended proposal due date and extended question period.
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Update #1 ·
Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.
Attachments
| File | Type | Posted |
|---|---|---|
| SEL 3530.3.pdf | ||
| SEL 3530.2.pdf | ||
| SEL 3530.4.pdf | ||
| SEL 3530.1.pdf | ||
| Amendment 0005 - Updated pictures.pdf | ||
| PICTURES.pdf | ||
| Amendment 0004 - Extend Proposal Due Date.pdf | ||
| Amendment 0003 - Extend Proposal Due Date.pdf | ||
| Amendment 0002 - Extend Proposal Due Date.pdf | ||
| DPG Microgrid Site Visit sign-in Sheet.pdf | ||
| Amendment 0001 - Extend Proposal Due Date.pdf | ||
| Attachment 2 - Wage Determination.pdf | ||
| Attachment 3 - Pre-Award Survey.pdf | ||
| W9123821R0045 Dugway Microgrid Solicitation.pdf | ||
| Attachment 4 - Past Performance Questionnaire.pdf | ||
| Attachment 1 - Specifications.pdf |
Show all 16
Notice history
| Notice | Type | Posted |
|---|---|---|
| Dugway Proving Grounds Microgrid | Award Notice | |
| Dugway Proving Grounds Microgrid | Solicitation | |
| Dugway Proving Grounds Microgrid | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity