Dugway Proving Grounds Microgrid

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9123821R0045
Agency
ENDIST Sacramento US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
237130 Power and Communication Line and Related Structures Construction
PSC
Y1MZ Construction Of Epg Facilities - Other, Including Transmission
Place of performance
Dugway UT 84022, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks design and construction services for a microgrid at Dugway Proving Grounds in Utah. The Army Corps of Engineers requires a contractor to install a new battery energy storage system, supervisory control and data acquisition system, and microgrid control system to integrate an existing 12-megawatt diesel generator plant and 2-megawatt solar array at the base into a new microgrid. Proposals will be evaluated using lowest price technically acceptable criteria, with the contract awarded to the responsible offeror providing the lowest evaluated price meeting the solicitation's technical requirements. Proposals are due by June 2, 2021.

This is a total small business set-aside opportunity. The place of performance is Dugway, Utah, with the requirement for the awarded contractor to deliver a fully operational microgrid within the timeline defined in the performance work statement. Key components include integrating the existing energy assets with the new battery energy storage system and control systems to increase energy resiliency at the proving grounds.

Notice text

7 versions

Update #7 · Latest ·

****05/21/2021 - Amendment 0005 - posts updated pictures****

05/13/2021 - Amendment 0004 -Extended the propsoal due date, and includes pictures taken from the Site Visit.****

5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link

4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link

4/7/2021 -  Added Site visit sign-in sheet

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #6 ·

****05/13/2021 - Amendment 0004 -Extended the propsoal due date, and includes pictures taken from the Site Visit.****

5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link

4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link

4/7/2021 -  Added Site visit sign-in sheet

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #5 ·

*** Update*** 

5/6/2021 - Amendment 0003 - Extended proposal due date and changed point of contact for DoD Safe Link

4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link

4/7/2021 -  Added Site visit sign-in sheet

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #4 ·

*** Update***

4/22/2021 - Amendment 0002 - Extended proposal due date and change point of contact for DoD Safe Link

4/7/2021 -  Added Site visit sign-in sheet

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #3 ·

*** Update***

4/7/2021 -  Added Site visit sign-in sheet

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #2 ·

*** Update***

3/25/2021 - Amendment 0001-  Extended proposal due date and extended question period.

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Update #1 ·

Dugw ay Proving Grounds (DPG) Microgrid
The requirement is for the design and construction of a complete and operational microgrid, w hich includes a new battery energy storage system and a Supervisory Control And Data Acquisition (SCADA) system to be installed into the existing base utility grid. The existing base utility grid w ill be controlled by a new Microgrid Control System that integrates an existing 12-MW diesel generator plant to an existing 2-MW solar array, and a currently-under-construction utility-grade database system and total building energy management control system (EMCS),as well as a future 2-MW solar array.

Attachments

Show all 16

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Dugway Proving Grounds Microgrid Award Award Notice
Dugway Proving Grounds Microgrid This notice · Latest solicitation Solicitation
Dugway Proving Grounds Microgrid Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity