Computer Based Instructional Development III (CBID III)

Closed Solicitation Posted

This opportunity was awarded. See its 3 award notices in the notice history.

Solicitation number
W900KK-23-R-0005
Agency
ACC Orlando Army Contracting Command, Department of Defense
Responses due
Set-aside
Service-Disabled Veteran-Owned Small Business

Opportunity facts

NAICS code
541519 Other Computer Related Services
PSC
U099 Education/Training- Other
Place of performance
United States

Notice details come from SAM.gov. Updated .

Notice text

8 versions

Update #8 · Latest ·

SOLICITATION UPDATE - UPDATED GOVERNMENT POINTS OF CONTACT 10 July 2023

SOLICITATION AMENDMENT 0006 - 25 JAN 2023

The purpose of this Amendment A0006 is to incorporate changes to the following documents:  1) W900KK23R0005_CBID_III_conformed_at_Amd_0006_20230125;  2) W900KK23R0005_Attach_08_CBIDIII_WP_Task_Order_20230125;  3) W900KK23R0005_Attach_23_CBIDIII_Past_Performance_Questionnaire_Cover_Letter_20230125;  4) W900KK23R0005_Attach_29_CBIDIII_RFP_Price_Workbook_Rev_3_20230125; and,  5) W900KK23R0005_Attach_32_Questions_and_Answer_20230125. 

Please note Q&A changes with yellow highlight. 

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0005 - 19 JAN 2023

On 13 January 2023 the Government published Amendment 0004 to Solicitation W900KK-23-R-0005 for the Computer Based Instructional Development III procurement.  The purpose was to post Government responses to questions, comments and recommendations submitted by Industry.  Several proposal submission instructions were modified to reduce workload associated with proposal preparation.  Unfortunately some of those changes conflict with other instructions.  There is a need to make corrections.  Time will not permit revisions right now since the contract writing tool used to create the solicitation will soon be out of service for maintenance.  As an interim fix, this Amendment 0005 updates Section L at paragraph L.1.3 by removing the requirement to submit the Past Performance – Volume II separately on 23 January 2023.  All four volumes of the proposal are now due on 13 February 2023.  All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0004 13 JAN 2023

The purpose of this solicitation amendment is to address questions submitted by industry. All of the submitted questions were addressed and are shown in Attachment 32 - Questions and Answers (W900KK23R0005_Attach_32_Questions_And_Answers_20230113). The amendment also shows the changes that were made to Sections J, L, and M of the solicitation (W900KK23R0005_Amd_0004_CBID_III_20230113). Clause 52.216-19 – Order Limitations was updated and clause 52.216-32 Task-Order and Delivery-Order Ombudsman (Sept 2019) was deleted. The attachments that were updated in this amendment are Attachment 01 – CBID III PWS, Attachment 08 – CBID III WP Task Order, Attachment 10 – CBID III WP PWS, Attachment 13 – VACR IMI AEC Sample Task Order, Attachment 14 –  CBID III VACR IMI AEC Exhibit A CDRLS, Attachment 17 – CBID III VACR IMI AEC PWS, Attachment 19 - CBID III TC 3-01.80 Visual Aircraft Recognition, Attachment 21 – CBID III Compliance Matrix, Attachment 23 – CBID III Past Performance Questionnaire Cover Letter, and Attachment 29 – CBID III RFP Price Workbook Rev 2.  

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0003 - 07 DEC 2022

This notice serves as Amendment 0003 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 09 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    13 January 2023 

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   23 January 2023

Proposal Submittal Date, no later than 1:00 PM Eastern  13 February 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0003, the next milestone event in the schedule is 13 JAN 2023.

There were no other changes.

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #7 ·

SOLICITATION AMENDMENT 0006 - 25 JAN 2023

The purpose of this Amendment A0006 is to incorporate changes to the following documents:  1) W900KK23R0005_CBID_III_conformed_at_Amd_0006_20230125;  2) W900KK23R0005_Attach_08_CBIDIII_WP_Task_Order_20230125;  3) W900KK23R0005_Attach_23_CBIDIII_Past_Performance_Questionnaire_Cover_Letter_20230125;  4) W900KK23R0005_Attach_29_CBIDIII_RFP_Price_Workbook_Rev_3_20230125; and,  5) W900KK23R0005_Attach_32_Questions_and_Answer_20230125. 

Please note Q&A changes with yellow highlight. 

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0005 - 19 JAN 2023

On 13 January 2023 the Government published Amendment 0004 to Solicitation W900KK-23-R-0005 for the Computer Based Instructional Development III procurement.  The purpose was to post Government responses to questions, comments and recommendations submitted by Industry.  Several proposal submission instructions were modified to reduce workload associated with proposal preparation.  Unfortunately some of those changes conflict with other instructions.  There is a need to make corrections.  Time will not permit revisions right now since the contract writing tool used to create the solicitation will soon be out of service for maintenance.  As an interim fix, this Amendment 0005 updates Section L at paragraph L.1.3 by removing the requirement to submit the Past Performance – Volume II separately on 23 January 2023.  All four volumes of the proposal are now due on 13 February 2023.  All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0004 13 JAN 2023

The purpose of this solicitation amendment is to address questions submitted by industry. All of the submitted questions were addressed and are shown in Attachment 32 - Questions and Answers (W900KK23R0005_Attach_32_Questions_And_Answers_20230113). The amendment also shows the changes that were made to Sections J, L, and M of the solicitation (W900KK23R0005_Amd_0004_CBID_III_20230113). Clause 52.216-19 – Order Limitations was updated and clause 52.216-32 Task-Order and Delivery-Order Ombudsman (Sept 2019) was deleted. The attachments that were updated in this amendment are Attachment 01 – CBID III PWS, Attachment 08 – CBID III WP Task Order, Attachment 10 – CBID III WP PWS, Attachment 13 – VACR IMI AEC Sample Task Order, Attachment 14 –  CBID III VACR IMI AEC Exhibit A CDRLS, Attachment 17 – CBID III VACR IMI AEC PWS, Attachment 19 - CBID III TC 3-01.80 Visual Aircraft Recognition, Attachment 21 – CBID III Compliance Matrix, Attachment 23 – CBID III Past Performance Questionnaire Cover Letter, and Attachment 29 – CBID III RFP Price Workbook Rev 2.  

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0003 - 07 DEC 2022

This notice serves as Amendment 0003 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 09 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    13 January 2023 

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   23 January 2023

Proposal Submittal Date, no later than 1:00 PM Eastern  13 February 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0003, the next milestone event in the schedule is 13 JAN 2023.

There were no other changes.

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #6 ·

SOLICITATION AMENDMENT 0005 - 19 JAN 2023

On 13 January 2023 the Government published Amendment 0004 to Solicitation W900KK-23-R-0005 for the Computer Based Instructional Development III procurement.  The purpose was to post Government responses to questions, comments and recommendations submitted by Industry.  Several proposal submission instructions were modified to reduce workload associated with proposal preparation.  Unfortunately some of those changes conflict with other instructions.  There is a need to make corrections.  Time will not permit revisions right now since the contract writing tool used to create the solicitation will soon be out of service for maintenance.  As an interim fix, this Amendment 0005 updates Section L at paragraph L.1.3 by removing the requirement to submit the Past Performance – Volume II separately on 23 January 2023.  All four volumes of the proposal are now due on 13 February 2023.  All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0004 13 JAN 2023

The purpose of this solicitation amendment is to address questions submitted by industry. All of the submitted questions were addressed and are shown in Attachment 32 - Questions and Answers (W900KK23R0005_Attach_32_Questions_And_Answers_20230113). The amendment also shows the changes that were made to Sections J, L, and M of the solicitation (W900KK23R0005_Amd_0004_CBID_III_20230113). Clause 52.216-19 – Order Limitations was updated and clause 52.216-32 Task-Order and Delivery-Order Ombudsman (Sept 2019) was deleted. The attachments that were updated in this amendment are Attachment 01 – CBID III PWS, Attachment 08 – CBID III WP Task Order, Attachment 10 – CBID III WP PWS, Attachment 13 – VACR IMI AEC Sample Task Order, Attachment 14 –  CBID III VACR IMI AEC Exhibit A CDRLS, Attachment 17 – CBID III VACR IMI AEC PWS, Attachment 19 - CBID III TC 3-01.80 Visual Aircraft Recognition, Attachment 21 – CBID III Compliance Matrix, Attachment 23 – CBID III Past Performance Questionnaire Cover Letter, and Attachment 29 – CBID III RFP Price Workbook Rev 2.  

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0003 - 07 DEC 2022

This notice serves as Amendment 0003 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 09 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    13 January 2023 

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   23 January 2023

Proposal Submittal Date, no later than 1:00 PM Eastern  13 February 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0003, the next milestone event in the schedule is 13 JAN 2023.

There were no other changes.

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #5 ·

SOLICITATION AMENDMENT 0004 13 JAN 2023

The purpose of this solicitation amendment is to address questions submitted by industry. All of the submitted questions were addressed and are shown in Attachment 32 - Questions and Answers (W900KK23R0005_Attach_32_Questions_And_Answers_20230113). The amendment also shows the changes that were made to Sections J, L, and M of the solicitation (W900KK23R0005_Amd_0004_CBID_III_20230113). Clause 52.216-19 – Order Limitations was updated and clause 52.216-32 Task-Order and Delivery-Order Ombudsman (Sept 2019) was deleted. The attachments that were updated in this amendment are Attachment 01 – CBID III PWS, Attachment 08 – CBID III WP Task Order, Attachment 10 – CBID III WP PWS, Attachment 13 – VACR IMI AEC Sample Task Order, Attachment 14 –  CBID III VACR IMI AEC Exhibit A CDRLS, Attachment 17 – CBID III VACR IMI AEC PWS, Attachment 19 - CBID III TC 3-01.80 Visual Aircraft Recognition, Attachment 21 – CBID III Compliance Matrix, Attachment 23 – CBID III Past Performance Questionnaire Cover Letter, and Attachment 29 – CBID III RFP Price Workbook Rev 2.  

All other items listed in the solicitation remain unchanged.

SOLICITATION AMENDMENT 0003 - 07 DEC 2022

This notice serves as Amendment 0003 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 09 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    13 January 2023 

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   23 January 2023

Proposal Submittal Date, no later than 1:00 PM Eastern  13 February 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0003, the next milestone event in the schedule is 13 JAN 2023.

There were no other changes.

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #4 ·

SOLICITATION AMENDMENT 0003 - 07 DEC 2022

This notice serves as Amendment 0003 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 09 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    13 January 2023 

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   23 January 2023

Proposal Submittal Date, no later than 1:00 PM Eastern  13 February 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0003, the next milestone event in the schedule is 13 JAN 2023.

There were no other changes.

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #3 ·

SOLICITATION AMENDMENT 0002 - 01 DEC 2022

This notice serves as Amendment 0002 to the CBID III Solicitation/Request for Proposal posting.

The Solicitation Amendment to Address Questions will not occur on 02 DEC 2022. The Key Dates at paragraph at L.1.3 are revised as follows:

L.1.3       Key Dates.

Solicitation Release Date                 4 November 2022

Solicitation Question Due Date, no later than 1:00 PM Eastern     18 November 2022

Solicitation Amendment Posted to Address Questions    9 December 2022

Past Performance – Volume II Due Date, no later than 1:00 PM Eastern   19 December 2022

Proposal Submittal Date, no later than 1:00 PM Eastern  4 January 2023

Contract Award Goal      3rd Quarter 2023

Post Award Conference 4th Quarter 2023

As a result of this Amendment 0002, the next milestone event in the schedule is 09 DEC 2022.

There were no other changes.

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #2 ·

SOLICITATION AMENDMENT - 09 NOV 2022

This notice serves as an amendment to the CBID III Solicitation/Request for Proposal posting.

The Pre-proposal Conference scheduled for 15 November 2022 is canceled due to inclement weather in the area. Therefore, it is no longer listed in Section L.1.3.

The next milestone event in the schedule is the requirement to submit the Solicitation Questions no later than 1:00 PM Eastern on 18 November 2022.

This Amendment 0001 also addresses the identification of an artifact on the CBID III - Attachment 29 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104) that needed to be deleted prior to posting. As a result, CBID III - Attachment 29 is rescinded and replaced with CBID III - Attachment 29 – Revision 1 (W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109).

There were no other changes.

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Update #1 ·

SOLICITATION - 04 NOV 2022

This notice serves as the official/final CBID III Solicitation/Request for Proposal posting.

CBID III is a single award firm fixed priced Indefinite Delivery/Indefinite Quantity (ID/IQ) Contract. The CBID III program will be acquired as a Set-Aside for Service-Disabled Veteran-Owned Small Business concerns (SDVOSB), on a competitive basis. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. Evaluation methodology for the instant procurement consists of three Factors: Technical Approach, Past Performance, and Price.

CBID III will satisfy Government requirements for Interactive Multimedia Instruction (IMI) products and services, Desk Top Trainers (DTT) products, and Organic (Embedded) Trainers via a Single-Source Indefinite Delivery Indefinite Quantity (IDIQ) contract that will support U.S. Army, Joint community, and other Government agencies.

A virtual pre-proposal conference is tentatively scheduled for 1:00 p.m. - 3:30 p.m. EST on 15 NOV 2022 will be conducted virtually on Microsoft Teams. Please submit your request to attend listed at L.1.5. no later than 1:00 p.m. EST on 10 NOV 2022. 

Solicitation questions are due no later than 1:00 p.m. EST on 18 NOV 2022.

All communications between Offerors and the Government pertaining to this CBID III solicitation, its attachments and all amendments shall be through the Procuring Contracting Officer (PCO) and the designated Contract Specialist (CS).

Attachments

Files attached to this notice, newest first
File Type Posted
W900KK23R0005_Attach_08_CBIDIII_WP_Task_Order_20230125.pdf PDF
W900KK23R0005_Attach_23_CBID_III_Past_Performance_Questionnaire_Cover_Letter_20230125.pdf PDF
W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_3_20230125.xls XLS spreadsheet
W900KK-23-R-0005_CBID_III_Amd_0005_20230119.docx DOCX document
W900KK-23-R-0005_CBID_III_Amd_0004_20230113.docx DOCX document
W900KK23R0005_Attach_01_CBID_III_PWS_20230113.pdf PDF
W900KK23R0005_Attach_17_CBID_III_VACR_IMI_AEC_PWS_20230113.pdf PDF
W900KK23R0005_Attach_10_CBID_III_WP_PWS_20230113.pdf PDF
W900KK23R0005_Attach_19_CBID_III_TC_3-01.80_Visual_Aircraft_ Recognition_20170505.pdf PDF
W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_2_20230113.xls XLS spreadsheet
W900KK-23-R-0005_CBID_III_conformed_at_Amd_0004_20230113.docx DOCX document
W900KK23R0005_Attach_14_CBID_III_VACR_IMI_AEC_Exhibit_A_CDRLs_20230113.pdf PDF
W900KK23R0005_Attach_08_CBIDIII_WP_Task_Order_20230113.pdf PDF
W900KK23R0005_Attach_13_VACR_IMI_and_AEC_Sample_Task_Order_20230113.pdf PDF
W900KK23R0005_Attach_21_CBID_III_Compliance_Matrix_20230113.xlsx XLSX spreadsheet
W900KK23R0005_Attach_23_CBID_III_Past_Performance_Questionnaire_Cover_Letter_20230113.pdf PDF
W900KK23R0005_Attach_32_Questions_and_Answers_20230113.pdf PDF
W900KK-23-R-0005_Amd_0003_CBID_III_conformed_20221207.pdf PDF
W900KK-23-R-0005_Amd_0003_CBID_III_20221207.pdf PDF
W900KK-23-R-0005_Amd_0002_CBID_III_conformed_20221201.pdf PDF
W900KK-23-R-0005_Amd_0001_CBID_III_20221109.docx DOCX document
W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_Rev_1_20221109.xls XLS spreadsheet
W900KK23R0005_Attach_01_CBID_III_PWS_20221104.pdf PDF
W900KK23R0005_Attach_05_CBID_III_Property_Management_Plan_20221104.docx DOCX document
W900KK23R0005_Attach_15_CBID_III_VACR_IMI_AEC_Exhibit_B_CDRLs.pdf PDF
W900KK23R0005_Attach_23_CBID_III_Past_Performance_Questionnaire_Cover_Letter_20221104.pdf PDF
W900KK23R0005_Attach_24_CBID_III_Past_Performance_Questionnaire_20221104.docx DOCX document
W900KK23R0005_Attach_27_CBID_III_DCMA_Form_1619_Subordination_Agreement_20221104.pdf PDF
W900KK23R0005_Attach_28_CBID_III_DCMA_Form_1620_Guaranty_Agrmnt_for_Corp_Guarantor.docx DOCX document
W900KK23R0005_Attach_29_CBID_III_RFP_Price_Workbook_20221104.xls XLS spreadsheet
W900KK23R0005_Attach_04_CBID_III_Rate_Guide.docx DOCX document
W900KK23R0005_Attach_03_CBID_III_DD254_20221104.pdf PDF
W900KK23R0005_Attach_10_CBID_III_WP_PWS_20221104.docx DOCX document
W900KK23R0005_Attach_12_CBID_III_Reserved_20221104.docx DOCX document
W900KK23R0005_Attach_13_VACR_IMI_and_AEC_Sample_Task_Order_20221104.pdf PDF
W900KK23R0005_Attach_16_CBID_III_VACR_IMI_AEC_Exhibit_C_CDRLs.pdf PDF
W900KK23R0005_Attach_08_CBIDIII_WP_Task_Order_20221104.pdf PDF
W900KK23R0005_Attach_06_CBID_III_OCI_Mitigation_Plan_20221104.docx DOCX document
W900KK23R0005_Attach_07_CBID_III_Contractor_Proposal_20221104.docx DOCX document
W900KK23R0005_Attach_09_CBID_III_WP_Exhibit_A_CDRL_20221104.pdf PDF
W900KK23R0005_Attach_20_CBID_III_Solicitation_Comment_Form_20221104.docx DOCX document
W900KK23R0005_Attach_21_CBID_III_Compliance_Matrix.xlsx XLSX spreadsheet
W900KK23R0005_Attach_25_CBID_III_Past_Performance_Contract_Description_20221104.docx DOCX document
W900KK23R0005_Attach_30_CBID_III_DCMA_Standard_Form_1408_20221104.docx DOCX document
W900KK23R0005_Attach_31_CBID_III_Security_Self-Vetting_Form_20221104.docx DOCX document
W900KK-23-R-0005_CBIDIII_RFP_20221104.docx DOCX document
W900KK23R0005_Attach_14_CBID_III_VACR_IMI_AEC_Exhibit_A_CDRLs.pdf PDF
W900KK23R0005_Attach_17_CBID_III_VACR_IMI_AEC_PWS.docx DOCX document
W900KK23R0005_Attach_19_CBID_III_Reserved_20221104.docx DOCX document
W900KK23R0005_Attach_22_CBID_III_List_of_Past_Performance_Contracts_20221024.docx DOCX document
Show all 50

This notice has more attachments on GovTribe.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
U. S. Army Combat Capabilities Development Command (DEVCOM) Ground Vehicle Systems Center (GVSC) Latest Award Notice
Rare Earth Elements Recovery Award Notice
Rare Earth Elements Separation Award Notice
RFS rare earth elements (REE) initiatives Latest solicitation Solicitation
RFS rare earth elements initiatives Solicitation
Computer Based Instructional Development III (CBID III) This notice Solicitation
Draft RFS rare earth elements initiatives Original Special Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity