Calcasieu River and Pass, LA, Maintenance Dredging FY26, Mile 5. 0 to Mile 17. 0, Including Beneficial Use Within CWPPRA Sabine Cycle 6 Marsh Creation Areas, Calcasieu and Cameron Parishes, LA ED 23-024
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912P826BA023
- Agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KF Construction Of Dredging Facilities
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers, New Orleans District, seeks competitive bids for maintenance dredging of the Calcasieu River and Pass, Louisiana (Mile 5.0 to Mile 17.0) with beneficial reuse of dredged material in CWPPRA Sabine Cycle 6 marsh creation areas, with bids due September 18, 2026, at 10:00 a.m. local time and opening at 1:00 p.m. This is an unrestricted invitation for bid with no set-aside.
Place of performance is Calcasieu and Cameron Parishes, Louisiana. The work encompasses removal of material from the Calcasieu River Ship Channel with disposal within designated marsh creation areas in the Sabine National Wildlife Refuge and adjacent areas, retention dike construction, surveys, and optional ditching and draining of disposal areas. Optional work includes material removal from Devil's Elbow. Base work is estimated at 300 calendar days after receipt of Notice to Proceed; if optional work item 2 is exercised, the contract duration extends an additional 170 calendar days.
The contract value falls between $25 million and $100 million, structured as firm-fixed-price with unit-price bid basis. Six offerors submitted bids on September 18: Callan Marine, Ltd ($69.125 million); Great Lakes Dredge & Dock Company, LLC ($40.979 million); Inland Dredging Company, LLC ($59.375 million); Mike Hooks, LLC ($36.492 million); Orion Marine Construction, Inc. ($44.258 million); and Weeks Marine Inc. ($85.187 million). The NAICS code is 237990, Other Heavy and Civil Engineering Construction. PSC code is Y1KF, Construction of Dredging Facilities. Bidders must acknowledge amendments issued September 2, 4, and 14, 2026, on the SF1442 form. A 20 percent bid guarantee (or $3 million, whichever is less) and performance and payment bonds are required within 10 days of award.
Notice text
7 versions
Update #7 · Latest ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
4 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the attached sheets.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
--------------------------------------------------------------------------------------------------------------------
14 September 2026
The solicitation has been amended as followed:
1. Bid opening has been extended to Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission
-----------------------------------------------------------------------------------------------------------------------
15 September 2026
This Solicitation has been amended as follows:
1. To provide answers to contractors questions.
2. Bid opening remains Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
3. No further questions will be accepted.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
18 September 2026
Bid Opening held on 18 September 2026. Bid Abstract attached.
----------------------------------------------------------------------------------------------------------------------
21 September 2026
Reformatted Bid Abstract attached.
Update #6 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
4 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the attached sheets.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
--------------------------------------------------------------------------------------------------------------------
14 September 2026
The solicitation has been amended as followed:
1. Bid opening has been extended to Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission
-----------------------------------------------------------------------------------------------------------------------
15 September 2026
This Solicitation has been amended as follows:
1. To provide answers to contractors questions.
2. Bid opening remains Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
3. No further questions will be accepted.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
18 September 2026
Bid Opening held on 18 September 2026. Bid Abstract attached.
Update #5 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
4 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the attached sheets.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
--------------------------------------------------------------------------------------------------------------------
14 September 2026
The solicitation has been amended as followed:
1. Bid opening has been extended to Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission
-----------------------------------------------------------------------------------------------------------------------
15 September 2026
This Solicitation has been amended as follows:
1. To provide answers to contractors questions.
2. Bid opening remains Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
3. No further questions will be accepted.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
Update #4 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
4 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the attached sheets.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
--------------------------------------------------------------------------------------------------------------------
14 September 2026
The solicitation has been amended as followed:
1. Bid opening has been extended to Friday, 18 September 2026, at 1:00pm local time. The Contracting Officer and Contracting Specialist will begin downloading bids at 10:00am local time, which is the bid submission receipt cutoff time. All bids received at 10:00am local time on Friday, 18 September 2026, will be considered late.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission
Update #3 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
---------------------------------------------------------------------------------------------------------------------
4 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the attached sheets.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
Update #2 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
--------------------------------------------------------------------------------------------------------------------
2 September 2026
The solicitation has been amended as followed:
1. Incorporate the following changes to the bid schedule, plans, specs, and drawings.
NOTE: Please be sure to acknowledge all amendments on the SF1442 form as part of your bid submission.
Update #1 ·
THIS SOLICITATION IS ISSUED AS UNRESTRICTED. THE NAICS CODE FOR THIS PROCUREMENT IS 237990.
THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 AND $100,000,000.
THE WORK CONSISTS OF REMOVAL OF MATERIAL FROM WITHIN THE CALCASIEU RIVER SHIP CHANNEL AND SATISFACTORY DISPOSAL WITHIN THE DESIGNATED MARSH CREATION AREAS WITHIN THE SABINE NATIONAL WILDLIFE REFUGE AND ADJACENT TO THE CALCASIEU RIVER AND PASS; ALL AS SHOWN ON THE DRAWINGS. REMOVAL OF MATERIAL FROM WITHIN DEVIL’S ELBOW IS INCLUDED AS OPTIONAL WORK. THE WORK ALSO INCLUDES RETENTION DIKE CONSTRUCTION, SURVEYS, AND OPTIONAL DITCHING AND DRAINING OF DISPOSAL AREAS, AND ALL OPERATIONS INCIDENTAL THERETO. (THE ESTIMATED TIME OF COMPLETION IS 300 CALENDAR DAYS FOR BASE WORK AFTER RECEIPT OF NOTICE TO PROCEED. THE SOLICITATION WILL INCLUDE 55 DRAWINGS AND SPECIFICATIONS).
Files
Notice history
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity