CA FTNP YOSE 17(3) Tioga Road

Award Notice Posted

Solicitation number
DTFH68-14-B-00005
Agency
Awarded
to Road And Highway Builders, LLC
Set-aside
No set-aside

Opportunity facts

Contract number
DTFH68-14-C-00018 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Yosemite National Park, California, United States

Notice details come from SAM.gov. Updated .

Notice text


PROJECT DESCRIPTION: This is a 3R (rehabilitation) project in Yosemite National Park. This project has two schedules. Schedule "A" begins at the intersection of Big Oak Flat Road and Tioga Road, and proceeds east for 12.8 miles, Schedule "B" begins at the intersection of Big Oak Flat Road and Tioga Road and proceeds east 15.0 miles.


SIGNIFICANT QUANTITIES: 1,584 STATIONS of Shoulder and Ditch Reconditioning, 792 STATIONS of 6-inch depth Pulverizing, 6,500 TONS of Roadway Aggregate, 40,600 TONS of Superpave Pavement, 15,350 LN FT of Concrete Curb, 8,840 HOURS of Flagger.


RANGE: $10,000,000 to $15,000,000


CONSTRUCTION DURATION: Tentative construction duration is from June 2014 through October 31, 2015.


This project will be advertised on or about February 6, 2014.


 

Files

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity