B409 UPS

Closed Solicitation Posted

Solicitation number
W50S8R25Q0004
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Ohio 44903, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Ohio Army National Guard is seeking a contractor to replace a UPS power module and upgrade battery backup systems for an Eaton 93PM-200 UPS system located in Mansfield, Ohio. The solicitation (W50S8R25Q0004) requires the replacement of one UPS power module compatible with the existing system and two battery backup systems, totaling 144 compatible 12V 500W sealed lead acid batteries. Contractors must be OEM authorized and follow all manufacturer recommended procedures, with installation to be completed at 1947 Harrington Memorial Drive. The evaluation will be based on technical acceptability, price, delivery terms, and Supplier Performance Risk System (SPRS) information, with the government intending to award to the most technically acceptable offeror representing the best value. Quotes are due by 10:00 A.M. EST on March 4, 2025, and must be submitted via email to jeffrey.snyder.20@us.af.mil, with contractors required to provide a Field Activity Report within 5 business days of work completion.

This opportunity is a 100% small business set-aside under NAICS code 335999, with a business size standard of 600 employees, utilizing simplified acquisition procedures for a firm-fixed-price purchase order. The contract will result in a single award to a qualified offeror, with work to be performed in Ontario, OH 44903. Contractors must complete Antiterrorism Awareness Level I training within 15 calendar days of contract start and comply with base access and security requirements, including background checks and personal identity verification. The old batteries will be turned over to 179 CW Environmental for disposal, and the contractor must ensure compatibility with the government's current infrastructure without additional government expense. Contractors must follow FCC, Public Utility Commission, Department of Defense, Air Force, and industry standards throughout the project.

Notice text

2 versions

Update #2 · Latest ·

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. This solicitation W50S8R25Q0004 is being issued as a Request for Quotation (RFQ). The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2024-07. This solicitation is being solicited as 100% small business set-aside. The NAICS code that applies is 335999 and business size is 600 employees. This action will result in a FFP purchase order, utilizing simplified acquisition procedures.

The contractor shall provide all labor, equipment, materials, tools, parts, shipping, and all other items necessary to provide and install the following items:

CLIN

Description

Quantity

Unit of Issue

Salient Characteristics

0001

UPS Power Module Replacement

1

EA

  • UPS power module replacement on Eaton UPS
  • Must be compatible with the EATON 93PM-200 UPS system
  • Current EATON UPM ASSY P/N 744-A4535

0002

UPS Battery Upgrade

2

EA

  • Replacement of two battery backup systems to support EATON 93PM-200 UPS system.
  • Each system needs 72 batteries for a total of 144 compatible 12V 500W sealed lead acid batteries
  • Old batteries shall be turned over to 179 CW Environmental for disposal
  • These services shall include any equipment, wiring, or infrastructure to ensure the Contractor's proposed solution is compatible with the Government's current infrastructure without additional Government expense. The Contractor shall follow all Federal Communications Commission (FCC), Public Utility Commission (PUC), Department of Defense (DoD), AF, and industry standards for this requirement.
  • Following the completion of work, contractor shall provide a Field Activity Report containing observations, conditions, and recommendations sent to the customer within 5 business days.
  • Installation shall be performed by OEM authorized party. The Contractor shall use manufacturer recommended procedures and products to perform all associated replacement work to ensure the UPS system is operating properly

Base access Requirement:

  • The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
  • When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Integrated Defense, and DODMAN5200.02_AFMAN 16-1405, Air Force Personnel Security Program.
  • Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the contracting officer within 15 calendar days after completion of training by each employee or subcontractor personnel.

Location - 1947 Harrington Memorial Drive, Mansfield, Ohio 44903 utilizing FOB Destination

Transmittal and Cover Letter

The offeror’s transmittal and cover letter for the quote must contain the name, phone number, and email address of the person to be contacted concerning any matter related to this solicitation.  Include the following information in your quote:

  1. CAGE Code and Unique Entity ID
  2. Company Name, mailing address, & website
  3. Date submitted and quote expiration date
  4. Delivery time/terms
  5. Warranty

***Offerors shall include with their proposal a filled out 52.204-24 representation.***

ADDENDUM TO 52.212-2

1 BASIS FOR CONTRACT AWARD: This solicitation is for a Firm Fixed Price Contract. The Government intends to award a single contract to a qualified Offeror deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose quote conforms to all solicitation requirements and is judged to represent the Best Value to the Government. Best value is expected to result from the evaluation of technical acceptability, price, delivery, and information contained in the Supplier Performance Risk System (SPRS).

2 EVALUATION FACTORS FOR AWARD: The evaluation factors are (1) Technical, (2) Price, (3) Delivery, and (4) SPRS. To arrive at a Best Value decision, the Contracting Officer will integrate the evaluation of Technical, Price, Delivery, and SPRS.

  1. Technical Evaluation. Technical Capability will be evaluated on an Acceptable/Unacceptable basis. An offeror shall obtain an “Acceptable” rating to continue further in the competition. Offerors who are deemed to merit an “Unacceptable” rating in the Technical Capability Factor will be removed from further consideration for award. Once the minimum requirements are established, the team shall evaluate the offeror's quote against these requirements to determine whether the quote is acceptable or unacceptable, using the description outlined below. Quotes are evaluated for acceptability, but not ranked using the non-price factors/subfactors.
  1. Technical Documentation:

    1. Offeror shall provide a product specification sheet, adequate enough for the government to evaluate that the proposed products meet all requirements of this solicitation.
    2. Offeror shall provide a sufficiently detailed technical approach to perform the installation/replacement work requested within this RFQ and shall not simply restate RFQ requirements
  2. Standard: A technically acceptable rating is met when the offeror provides product specification sheets and a technical approach that clearly demonstrates the ability to perform the requested work IAW all requirements of this solicitation
  1. Price. The total quoted price from offerors determined technically acceptable will be evaluated.
  1. Delivery. Delivery terms contained in the offer will be evaluated. In general, quicker lead times are considered more favorable to the Government.
  1. SPRS. The Government shall utilize information contained in SPRS, if available, as described in DFARS 252.204-7024. Offerors or quoters without a risk assessment in SPRS shall not be considered favorably or unfavorably.

(End of provision)

For more information regarding this solicitation please contact MSgt Jeffrey Snyder via email at jeffrey.snyder.20@us.af.mil

Offers are due by 10:00 A.M. EST 10 March 2025: email jeffrey.snyder.20@us.af.mil

List of Attachments:

Attachment 1: Clauses and Provisions

NG Agency Protest Program is intended to encourage interested parties to seek resolution of their concerns with the National Guard (NG) as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum.

Contract award or performance is suspended during the protest to the same extent, and within the same time periods as if filed at the GAO. The NG protest decision goal is to resolve protests within 35 calendar days from filing. An agency protest may be filed with either the Contracting Officer or the NG Agency’s Protest Decision Authority, but not both, in accordance with NG protest procedures.

To be timely, the protests must be filed with the periods specified in FAR 33.103. To file a protest under the NG Agency Protest Program, the protest must request resolution under that program and be sent to the address below:

National Guard Bureau

Office of the Director of Acquisitions/ Head of Contracting Activity

ATTN: NGB-AQ-O

111 S. George Mason Dr. Arlington, VA 22204

Email: ng.ncr.ngb-arng.mbx.ngb-task-order-ombudsman@mail.mil

All other agency-level protests should be sent to the Contracting Officer for resolution at the address in the solicitation. See FAR clause 52.233-2.

Update #1 ·

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. This solicitation W50S8R25Q0004 is being issued as a Request for Quotation (RFQ). The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2024-07. This solicitation is being solicited as 100% small business set-aside. The NAICS code that applies is 335999 and business size is 600 employees. This action will result in a FFP purchase order, utilizing simplified acquisition procedures.

The contractor shall provide all labor, equipment, materials, tools, parts, shipping, and all other items necessary to provide and install the following items:

CLIN

Description

Quantity

Unit of Issue

Salient Characteristics

0001

UPS Power Module Replacement

1

EA

  • UPS power module replacement on Eaton UPS
  • Must be compatible with the EATON 93PM-200 UPS system
  • Current EATON UPM ASSY P/N 744-A4535

0002

UPS Battery Upgrade

2

EA

  • Replacement of two battery backup systems to support EATON 93PM-200 UPS system.
  • Each system needs 72 batteries for a total of 144 compatible 12V 500W sealed lead acid batteries
  • Old batteries shall be turned over to 179 CW Environmental for disposal
  • These services shall include any equipment, wiring, or infrastructure to ensure the Contractor's proposed solution is compatible with the Government's current infrastructure without additional Government expense. The Contractor shall follow all Federal Communications Commission (FCC), Public Utility Commission (PUC), Department of Defense (DoD), AF, and industry standards for this requirement.
  • Following the completion of work, contractor shall provide a Field Activity Report containing observations, conditions, and recommendations sent to the customer within 5 business days.
  • Installation shall be performed by OEM authorized party. The Contractor shall use manufacturer recommended procedures and products to perform all associated replacement work to ensure the UPS system is operating properly

Base access Requirement:

  • The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
  • When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Integrated Defense, and DODMAN5200.02_AFMAN 16-1405, Air Force Personnel Security Program.
  • Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the contracting officer within 15 calendar days after completion of training by each employee or subcontractor personnel.

Location - 1947 Harrington Memorial Drive, Mansfield, Ohio 44903 utilizing FOB Destination

Transmittal and Cover Letter

The offeror’s transmittal and cover letter for the quote must contain the name, phone number, and email address of the person to be contacted concerning any matter related to this solicitation.  Include the following information in your quote:

  1. CAGE Code and Unique Entity ID
  2. Company Name, mailing address, & website
  3. Date submitted and quote expiration date
  4. Delivery time/terms
  5. Warranty

***Offerors shall include with their proposal a filled out 52.204-24 representation.***

ADDENDUM TO 52.212-2

1 BASIS FOR CONTRACT AWARD: This solicitation is for a Firm Fixed Price Contract. The Government intends to award a single contract to a qualified Offeror deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose quote conforms to all solicitation requirements and is judged to represent the Best Value to the Government. Best value is expected to result from the evaluation of technical acceptability, price, delivery, and information contained in the Supplier Performance Risk System (SPRS).

2 EVALUATION FACTORS FOR AWARD: The evaluation factors are (1) Technical, (2) Price, (3) Delivery, and (4) SPRS. To arrive at a Best Value decision, the Contracting Officer will integrate the evaluation of Technical, Price, Delivery, and SPRS.

  1. Technical Evaluation. Technical Capability will be evaluated on an Acceptable/Unacceptable basis. An offeror shall obtain an “Acceptable” rating to continue further in the competition. Offerors who are deemed to merit an “Unacceptable” rating in the Technical Capability Factor will be removed from further consideration for award. Once the minimum requirements are established, the team shall evaluate the offeror's quote against these requirements to determine whether the quote is acceptable or unacceptable, using the description outlined below. Quotes are evaluated for acceptability, but not ranked using the non-price factors/subfactors.
  1. Technical Documentation:

    1. Offeror shall provide a product specification sheet, adequate enough for the government to evaluate that the proposed products meet all requirements of this solicitation.
    2. Offeror shall provide a sufficiently detailed technical approach to perform the installation/replacement work requested within this RFQ and shall not simply restate RFQ requirements
  2. Standard: A technically acceptable rating is met when the offeror provides product specification sheets and a technical approach that clearly demonstrates the ability to perform the requested work IAW all requirements of this solicitation
  1. Price. The total quoted price from offerors determined technically acceptable will be evaluated.
  1. Delivery. Delivery terms contained in the offer will be evaluated. In general, quicker lead times are considered more favorable to the Government.
  1. SPRS. The Government shall utilize information contained in SPRS, if available, as described in DFARS 252.204-7024. Offerors or quoters without a risk assessment in SPRS shall not be considered favorably or unfavorably.

(End of provision)

For more information regarding this solicitation please contact MSgt Jeffrey Snyder via email at jeffrey.snyder.20@us.af.mil

Offers are due by 10:00 A.M. EST 4 March 2025: email jeffrey.snyder.20@us.af.mil

List of Attachments:

Attachment 1: Clauses and Provisions

NG Agency Protest Program is intended to encourage interested parties to seek resolution of their concerns with the National Guard (NG) as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum.

Contract award or performance is suspended during the protest to the same extent, and within the same time periods as if filed at the GAO. The NG protest decision goal is to resolve protests within 35 calendar days from filing. An agency protest may be filed with either the Contracting Officer or the NG Agency’s Protest Decision Authority, but not both, in accordance with NG protest procedures.

To be timely, the protests must be filed with the periods specified in FAR 33.103. To file a protest under the NG Agency Protest Program, the protest must request resolution under that program and be sent to the address below:

National Guard Bureau

Office of the Director of Acquisitions/ Head of Contracting Activity

ATTN: NGB-AQ-O

111 S. George Mason Dr. Arlington, VA 22204

Email: ng.ncr.ngb-arng.mbx.ngb-task-order-ombudsman@mail.mil

All other agency-level protests should be sent to the Contracting Officer for resolution at the address in the solicitation. See FAR clause 52.233-2.

Files

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
B409 UPS Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
6973GH-26-r-00177 - miniature UPS kits – SIR Oklahoma City, Oklahoma 73169, United States · NAICS 221122 Franchise Acquisition Servies No set-aside
FTG247 Replace UPS at IDT1, Fort Greely, Alaska Fort Greely, Alaska 99731, United States · NAICS 237130 ENDIST Alaska Total Small Business
J059--Uninterruptible Power Supply (UPS) Preventive Maintenance Base 4 Option Years (VA-27-00009247) Oklahoma City VA Medical Center Oklahoma City OK 73104 · NAICS 811210 Veterans Integrated Service Network 19 No set-aside
Power supply, uninterru NAICS 335999 Land and Maritime HUBZone
6135--UPS Battery Replacement VA San Diego Healthcare System San Diego CA 92161 · NAICS 335910 Veterans Integrated Service Network 22 No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities