B-21 Fuels System Maintenance Dock

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9128F24R0019
Agency
ENDIST Omaha US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1AZ Construction Of Other Administrative Facilities And Service Buildings
Place of performance
Ellsworth AFB, South Dakota 57706, United States
More information

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks proposals to design and construct a B-21 Fuels System Maintenance Dock at Ellsworth Air Force Base in South Dakota. The U.S. Army Corps of Engineers Omaha District will evaluate proposals and make award based on best value using past performance, project management plan, key personnel qualifications, small business participation plan, and price as the primary factors. Proposals are due by February 9, 2024.

There are no set-aside designations for this opportunity. The work involves construction services under NAICS 237310 and PSC C-421 with an estimated value between $25-100 million to be completed by 2026. The facility will be located at 1940 EP Howe Drive on Ellsworth Air Force Base and serve as the maintenance dock for the fuel systems of B-21 bombers stationed at the 28th Bomb Wing.

Notice text

10 versions

Update #10 · Latest ·

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #9 ·

Am 0006 - 2FEB24

See attachments

Am-0006_W9128F24R0019

Am-0006_W9128F24R0019_Attachments

---

---

Am 0005 - 26JAN24

See attachments

Am-0005_W9128F24R0019

Am-0005_W9128F24R0019_Attachments

---

Am 0004 - 22JAN24

See attachments

W9128F24R0019_Am0004

Am-0004_W9128F24R0019_Attach_Specs&Draws

---

Am 0003 - 14DEC23

See attachments

-W9128F24R0019_Am_0003

-Am-0003_W9128F24R0019_Attachments

---

Am 0002 -  1DEC23

See attachments

-W9128F24R0019__Am0002

-Am_0002_ELB1_EAFB_B21_Fuel_Sys_Maint_Dock_100_Perc_Spec

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part3

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part4

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part5

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part3

---

Am_0001  21NOV23

-W9128F24R0019_ Am0001

-Pre-bid Site Visti Roster

---

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #8 ·

Am 0005 - 26JAN24

See attachements

Am-0005_W9128F24R0019

Am-0005_W9128F24R0019_Attachments

---

Am 0004 - 22JAN24

See attachements

W9128F24R0019_Am0004

Am-0004_W9128F24R0019_Attach_Specs&Draws

---

Am 0003 - 14DEC23

See attachments

-W9128F24R0019_Am_0003

-Am-0003_W9128F24R0019_Attachments

---

Am 0002 -  1DEC23

See attachments

-W9128F24R0019__Am0002

-Am_0002_ELB1_EAFB_B21_Fuel_Sys_Maint_Dock_100_Perc_Spec

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part3

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part4

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part5

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part3

---

Am_0001  21NOV23

-W9128F24R0019_ Am0001

-Pre-bid Site Visti Roster

---

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #7 ·

Am 0004 - 22JAN24

See attachements

W9128F24R0019_Am0004

Am-0004_W9128F24R0019_Attach_Specs&Draws

---

Am 0003 - 14DEC23

See attachments

-W9128F24R0019_Am_0003

-Am-0003_W9128F24R0019_Attachments

---

Am 0002 -  1DEC23

See attachments

-W9128F24R0019__Am0002

-Am_0002_ELB1_EAFB_B21_Fuel_Sys_Maint_Dock_100_Perc_Spec

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part3

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part4

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part5

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part3

---

Am_0001  21NOV23

-W9128F24R0019_ Am0001

-Pre-bid Site Visti Roster

---

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #6 ·

Am 0003 - 14DEC23

See attachments

-W9128F24R0019_Am_0003

-Am-0003_W9128F24R0019_Attachments

---

Am 0002 -  1DEC23

See attachments

-W9128F24R0019__Am0002

-Am_0002_ELB1_EAFB_B21_Fuel_Sys_Maint_Dock_100_Perc_Spec

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part3

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part4

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Per_Des_Vol_I_Part5

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part1

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part2

-Am_0002_ELB1_Fuel_System_Maint_Dock_100_Perc_Des__Vol II_Part3

---

Am_0001  21NOV23

-W9128F24R0019_ Am0001

-Pre-bid Site Visti Roster

---

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #5 ·

Questions and Answers

Question:

  • Follow up to RFI 10506429:  Understood that the ATH Boilers are considered FRCS.  Will the Government then please modify the Project Specification to include a 25 05 11 spec for the ATH Boiler FRCS?  There are currently only four 25 05 11 subsections, for: HVAC, Lighting, ESS, and Fire.  Or are the ATH Boilers perhaps considered a component of one of those other FRCS? 
  • Follow up to RFI 10506441: will the Government please direct the offerors to the specific section of the project specifications that identifies the C-I-A levels of the FRCS for this project?  A search for the term “Confidentiality” in all project specifications/documents did not turn up any results, except for the PL-8 control identifier that requires the description of the approach taken to protect Confidentiality…
  • Follow up to RFI 10506443: are we to assume that because each 25 05 11 section of the specification lists the “Security Controls for Control Systems”, that the Government has already performed the cybersecurity design for these FRCS?  Will the contractors have any requirements to interact with eMASS at all as part of this project?
  • Will the Government keep the questions open or re-open questions prior to the Volume II (Price) proposal submission for offerors to ask additional questions particularly those that could arise from the 100% RTA drawings?

Answer:

    • Yes, Government will re-open inquiries once the Government issue the RTA package for pricing.
    • Please review the RTA package for pricing, because revisions may have been made from the Vol I package.
    • Any of these follow-on technical questions can be added at that time,
      • Boilers would be subject to HVAC cyber requirements.
      • PM will need to check on the CIA ratings. They are not sure they provide those, but the associated specs provide the appropriate level of scoping for the respective systems.
        • If we’re required to provide, we’ll clarify via future amendment.

---

21 NOV 2023

Am_0001

Posted 21Nov23 Proposasl Due 30Nov23

1. See Attached SF 30 _ W9128F24R0019_Am_0001

2. See Attached 24R0019_Pre-bid Site Visit Roster_R

***

1 NOV 2023

Question and Answer:

Question: File ELB1_EAFB_Fuel_Dock_80_100_Backcheck_Vol_1_Dwgs.pdf has a file size nearly twice the size of the Volume 2 set.  This has created difficulty in processing, viewing, sharing and communicating the information.  Will the Government ask the designers to reduce or flatten the file size (similar to Volume 2) to allow for a more manageable document?

Answer:

  1. Please assure you’re fully downloading the documents from PIEE and viewing them in a PDF viewing application/software. Viewing them through a viewer app on a web browser may result in reduced performance.
  2. File performance was checked on Government computers in both Adobe Acrobat Professional and Bluebeam Revu 20. In both cases, the PDF was easily navigable on Government hardware.
  3. Once downloaded, a contractor could consider (at their own risk) using a ‘reduce file size’ function in an appropriate software. I believe both Adobe Acrobat and Bluebeam applications have this capability. The Government does not intend to do this as part of this solicitation.
  4. If file functionality/accessibility remains an issue due to corrupted files, omission of sheets, etc.; please provide a new inquire with further details via ProjNet.

***

Solicitation

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #4 ·

21 NOV 2023

Am_0001

Posted 21Nov23 Proposasl Due 30Nov23

1. See Attached SF 30 _ W9128F24R0019_Am_0001

2. See Attached 24R0019_Pre-bid Site Visit Roster_R

***

1 NOV 2023

Question and Answer:

Question: File ELB1_EAFB_Fuel_Dock_80_100_Backcheck_Vol_1_Dwgs.pdf has a file size nearly twice the size of the Volume 2 set.  This has created difficulty in processing, viewing, sharing and communicating the information.  Will the Government ask the designers to reduce or flatten the file size (similar to Volume 2) to allow for a more manageable document?

Answer:

  1. Please assure you’re fully downloading the documents from PIEE and viewing them in a PDF viewing application/software. Viewing them through a viewer app on a web browser may result in reduced performance.
  2. File performance was checked on Government computers in both Adobe Acrobat Professional and Bluebeam Revu 20. In both cases, the PDF was easily navigable on Government hardware.
  3. Once downloaded, a contractor could consider (at their own risk) using a ‘reduce file size’ function in an appropriate software. I believe both Adobe Acrobat and Bluebeam applications have this capability. The Government does not intend to do this as part of this solicitation.
  4. If file functionality/accessibility remains an issue due to corrupted files, omission of sheets, etc.; please provide a new inquire with further details via ProjNet.

***

Solicitation

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #3 ·

1 NOV 2023

Question and Answer:

Question: File ELB1_EAFB_Fuel_Dock_80_100_Backcheck_Vol_1_Dwgs.pdf has a file size nearly twice the size of the Volume 2 set.  This has created difficulty in processing, viewing, sharing and communicating the information.  Will the Government ask the designers to reduce or flatten the file size (similar to Volume 2) to allow for a more manageable document?

Answer:

  1. Please assure you’re fully downloading the documents from PIEE and viewing them in a PDF viewing application/software. Viewing them through a viewer app on a web browser may result in reduced performance.
  2. File performance was checked on Government computers in both Adobe Acrobat Professional and Bluebeam Revu 20. In both cases, the PDF was easily navigable on Government hardware.
  3. Once downloaded, a contractor could consider (at their own risk) using a ‘reduce file size’ function in an appropriate software. I believe both Adobe Acrobat and Bluebeam applications have this capability. The Government does not intend to do this as part of this solicitation.
  4. If file functionality/accessibility remains an issue due to corrupted files, omission of sheets, etc.; please provide a new inquire with further details via ProjNet.

***

Solicitation

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #2 ·

1 NOV 2023

Question and Answer:

Question: File ELB1_EAFB_Fuel_Dock_80_100_Backcheck_Vol_1_Dwgs.pdf has a file size nearly twice the size of the Volume 2 set.  This has created difficulty in processing, viewing, sharing and communicating the information.  Will the Government ask the designers to reduce or flatten the file size (similar to Volume 2) to allow for a more manageable document?

Answer:

  1. Please assure you’re fully downloading the documents from PIEE and viewing them in a PDF viewing application. Viewing through a viewer app on a web browser may result in reduced performance.
  2. It was tested in both Adobe Acrobat Professional and Bluebeam Revu 20. In both cases, the PDF was easily navigable on the hardware.

***

Solicitation

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Update #1 ·

Designed Bid Build Construction of the B21 Fuels System Maintenance Dock at Ellsworth AFB, SD.

Attachments

Show all 20

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
B-21 Fuels System Maintenance Dock Award Award Notice
B-21 Fuels System Maintenance Dock This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity