ARS Woodward Embankment Rehabilitation
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 12FPC322R0007
- Agency
-
Farm Production and Conservation
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Woodward, Oklahoma 73801, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to rehabilitate the ARS Field Station Dam in Woodward County, Oklahoma. Work will involve boring and jacking a new 30-inch principal spillway pipe through the existing dam, building a new principal spillway tower, constructing a roller compacted concrete auxiliary spillway over the top of the existing dam, disposing of and filling in the existing concrete auxiliary spillway, and clearing and grubbing trees and vegetation from designated areas. The Department of Agriculture Under Secretary for Farm Production and Conservation seeks to award a fixed-price contract to the responsible offeror whose offer conforms to the solicitation and is most advantageous to the government considering technical approach and price. Proposals are due by May 5, 2022.
The set-aside is designated for total small business. The NAICS code is 237110 and PSC code is C211. There is no incumbent listed. The dam was constructed in 1937 and must be rehabilitated to meet current high hazard criteria due to reclassification. Work will be performed in Woodward, Oklahoma and is estimated to take one year to complete from notice to proceed.
Notice text
3 versions
Update #3 · Latest ·
Amendment 2, provides a correction to Q&A item number 15 response regarding draining and maintain water levels prior to and during construction.
Amendment 1, is to provide 9 attachments and extend solicitation due date.
Rehabilitate the ARS Field Station Dam, Woodward County, Oklahoma, this dam is a single purpose, high hazard, earthfill embankment constructed in 1937 with a drainage area of 14.4 square miles. The dam is not a floodwater retention structure, it is primarily used for irrigation and recreation. The site was reclassified as high hazard and must be rehabilitated to meet current high hazard criteria. The project will consist of boring and jacking a new 30” principal spillway pipe through the existing dam, building a new principal spillway tower, building a roller compacted concrete auxiliary spillway over the top of the existing dam, disposing of and filling in existing concrete auxiliary spillway – and includes clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from designated areas.
Update #2 ·
Amendment 1, is to provide 9 attachments and extend solicitation due date.
Rehabilitate the ARS Field Station Dam, Woodward County, Oklahoma, this dam is a single purpose, high hazard, earthfill embankment constructed in 1937 with a drainage area of 14.4 square miles. The dam is not a floodwater retention structure, it is primarily used for irrigation and recreation. The site was reclassified as high hazard and must be rehabilitated to meet current high hazard criteria. The project will consist of boring and jacking a new 30” principal spillway pipe through the existing dam, building a new principal spillway tower, building a roller compacted concrete auxiliary spillway over the top of the existing dam, disposing of and filling in existing concrete auxiliary spillway – and includes clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from designated areas.
Update #1 ·
Rehabilitate the ARS Field Station Dam, Woodward County, Oklahoma, this dam is a single purpose, high hazard, earthfill embankment constructed in 1937 with a drainage area of 14.4 square miles. The dam is not a floodwater retention structure, it is primarily used for irrigation and recreation. The site was reclassified as high hazard and must be rehabilitated to meet current high hazard criteria. The project will consist of boring and jacking a new 30” principal spillway pipe through the existing dam, building a new principal spillway tower, building a roller compacted concrete auxiliary spillway over the top of the existing dam, disposing of and filling in existing concrete auxiliary spillway – and includes clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from designated areas.
Files
Show all 14
Notice history
| Notice | Type | Posted |
|---|---|---|
| ARS Woodward Embankment Rehabilitation | Award Notice | |
| This notice | Solicitation | |
| ARS Woodward Embankment Rehabilitation | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Arcadia Wet Well Rehabilitation | ENDIST Tulsa | No set-aside | |
| Webbers Falls Excitation System Replacements | ENDIST Tulsa | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity