6145--Install OR Isolation Power and Upgrade Critical (VA-24-00006336)
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 36C24624B0004
- Agency
-
Veterans Integrated Service Network 6
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- PSC
- 6145 Wire And Cable, Electrical
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals to provide construction services for the installation of operating room isolation power and upgrading of critical panels at the Hampton VA Medical Center in Hampton, Virginia. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6 will evaluate proposals submitted in response to plans and specifications included with the solicitation notice. Electronic bids are due by February 27, 2024 at 5:00PM EST, with bid opening to be held virtually on February 29, 2024 at 11:00AM.
The opportunity is set aside 100% for total service-disabled veteran-owned small businesses. The projected award value is between $1 million and $5 million. Work will involve installing isolation power and upgrading critical panels in Building 110A of the Hampton VA Medical Center according to included drawings and specifications, with an estimated value of $6,145. The NAICS code is 238210 and PSC code R499. The period of performance involves alterations, construction and electrical upgrades with all work to be completed by December 2024.
Notice text
3 versions
Update #3 · Latest ·
The purpose of this amendment is to extend the hour and date for the bid submission date specified on the RFP to March 12th, 2024 at 5:00 PM EST.
Update #2 ·
Is this project sales tax exempt? If the project is sales tax exempt, can the Government provide a sales tax exemption certificate?
A: The tax exemption for this is not authorized. You will have to pay sales tax.
Can the required SSHO and QA/QC positions be fulfilled by the qualified superintendent?
A: There is a reason for having SSHO, QA and a Site Superintendent as individuals. If there is a safety issue, the Super would have to write himself up and it usually is not very effective. Same goes for QA. If he finds the wrong material being used, he d have to write himself up for allowing that to happen.
The Project requires hard ICRA barriers but cannot tie into existing duct work for neg air/hepa ventilation. Is the Government going to specify where we can vent?
A: The way you ll vent is up to you in your proposed solutions. The Gov t will not specify where to vent.
Can the VA clarify requirements to work in the OR? For example, will the workers have to wear operating room clothing covers, head covers, and shoe covers during work.
A: The OR space given to the contractor to work nights/weekends will be the contractor s space. You will not need to gown up once inside this area to get the panels/receptacles installed.
Will the Owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project?
A: We have no issue with ProCore. We use Submittal Exchange and ProCore for managing other projects.
How soon after the award is NTP expected to be issued?
A: We are aiming for a post-award meeting, to include issuing the NTP, no later than two weeks after the bid opening date of 2/29/24.
The SF 1442, page 1, states that electronic bids are due by 2/27/24 at 5 pm, however, RFP page 7, #3 states that electronic bids are due no later than 5 pm EDT one (1) day prior to the established Bid Opening Date identified. Please confirm the correct due date and time for electronic bids.
A: Electronic bids are due by 2/27.24 at 5PM EST.
RFP, page 3, Supplement B Statement of Work references Bid Item 1 and Bid Item 2 (Deduct Alternate 1), however, the specs on pages 3-4 reference Bid Items I and II, and Alternates Deducts 1, 2 and 3. Please confirm the correct Bid Items and Alternate Deducts
A: The correct bid items are references Bid Item 1 and Bid Item 2 (Deduct Alternate 1), as referenced in the SOW in Supplement B.
Please provide the Microsoft Teams information for the virtual bid opening on 2/29/24 at 11 am.
A: A meeting invite will be sent to all parties who submit a proposal on time. Expect an invite the morning of 2/28/24.
Since the proposed work schedule has been changed to primarily weekday night hours, is there a corresponding change for this NOTE? Are these two barriers even still necessary?
A: The detail showing temporary dust barriers near stairway 7 are only there for doing work to install the panel for the isolation power for the laser receptacles yes they re required. If this work is finished in one weekend, the walls can come down.  If this cannot be done on one shift, they would remove them at the end of the shift. If this were me doing the work, I d plan it for starting on a Friday and finishing the work over a weekend and then the dust barriers are removed for the rest of the contract.
Who is responsible for providing clean room apparel, such as suits, shoe covers, etcetera?
A: The VA will not provide gowns. They need to be properly gowned to get into their workspace each day. Once inside, they don t have to stay gowned.
Is the use a self-contained dust collection system an acceptable alternative to utilizing exhaust ducting out of the building?
A: We must have negative air scrubbing machines in the work environment. This can only be done w/ hepafiltered exhaust fans. They will exhaust this filtered air to the outside.
Update #1 ·
Scope: Provide construction services, alterations necessary for the installation of Operating Rooms isolation power and upgrading of critical panels in Bldg. 110A per included plans and specifications at Hampton, Hampton, VA Veterans Affair Center.
Files
| File | Type | Posted |
|---|---|---|
| 36C24624B0004 0002.docx | DOCX document | |
| 36C24624B0004 0001.docx | DOCX document | |
| 100pct Construction Drawing.pdf | ||
| 100 pct Combined Specs install OR Isolation power.pdf | ||
| 36C24624B0004 IFB.docx | DOCX document | |
| WAGE-RATES.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z1DA--Install OR Isolation Power | Award Notice | |
| This notice | Solicitation | |
| 6145--Install OR Isolation Power and Upgrade Critical (VA-24-00006336) | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Z1DA--Sources Sought Notice/Market Research Project: Renovate SPS Phase 3 | Veterans Integrated Service Network 6 | No set-aside | |
| Y1DA--590-27-120 Replace Pneumatic Tube System | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| Y1DA--561-26-103 Upgrade Electrical and Plumbing in Building 18B | Veterans Integrated Service Network 2 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009) | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| N048-- B41 Isolation Valve Installation | Veterans Integrated Service Network 16 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity