183 Construct BCE Complex

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W50S7U-22-B-0002
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Springfield, Illinois 62707, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks to award a firm fixed price contract for construction services to build a new Base Civil Engineer Complex for the 183rd Wing of the Illinois Air National Guard in Springfield, Illinois. The Department of the Army National Guard is procuring these services in accordance with the specifications, plans, statements of work, and addendums detailed in the solicitation documentation. Bids are due by August 11, 2022 and will be evaluated based on price and price related factors to select the most advantageous proposal to the government. Mandatory site visits were held on July 14th and August 2nd for interested offerors.

This requirement has a 100% set-aside for small businesses with a size standard of $39.5 million in average annual receipts. The primary NAICS code is 237990 and PSC code S206 for construction of general building projects. The period of performance is 730 calendar days and the estimated value is between $5-10 million. The construction will take place at 3101 J David Jones Parkway in Springfield, Illinois. Three bids were received in response, with a low bid of $14.7 million. Clarification was provided through several requests for information and amendments to ensure thorough understanding of the requirement.

Notice text

6 versions

Update #6 · Latest ·

This update on 10 August 2022 posts RFI 3 CES Construct BCE Complex responses to the attachments section here of this posting. 

This update on 03 August 2022 issues the amendment 0004 for Solicitation W50S7U-22-B-0003 to incorporate Addendum #7 dated 03 August 2022, update wage determination,  and issues RFI 2 responses. Amendment, Addendum #7 documents, RFI 2 CES Construct BCE Complex with applicable attachments, as well as sign-in sheet from site walk on 02 Aug 22 are added to attachments section here of this posting.

This update on 01 August 2022 issues the amendment 0003 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #6 dated 29 July 2022 and issue Request for Information (RFI)1 responses.  Amendment, Addendum #6 documents and RFI1 CES Construct BCE Complex with applicaple attachments are added to the attachments section here of this posting.

This update on 27 July 2022 issues the amendment 0002 for Solicitation W50S7U-22-B-0002 to amend the solicitation close/Bid opening date to 11 August 2022 as well as add an additional "Site Walk Only" for the project location on 02 August 2022 at 1:00PM CDT. Please see attached amendment 0002 for details.

This update on 22 July 22 issues the amendment 0001 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #5 dated 18 July 2022.  Amendment and Addendum # 5 documents are added to the attachments section here of this posting.

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Update #5 ·

This update on 03 August 2022 issues the amendment 0004 for Solicitation W50S7U-22-B-0003 to incorporate Addendum #7 dated 03 August 2022, update wage determination,  and issues RFI 2 responses. Amendment, Addendum #7 documents, RFI 2 CES Construct BCE Complex with applicable attachments, as well as sign-in sheet from site walk on 02 Aug 22 are added to attachments section here of this posting.

This update on 01 August 2022 issues the amendment 0003 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #6 dated 29 July 2022 and issue Request for Information (RFI)1 responses.  Amendment, Addendum #6 documents and RFI1 CES Construct BCE Complex with applicaple attachments are added to the attachments section here of this posting.

This update on 27 July 2022 issues the amendment 0002 for Solicitation W50S7U-22-B-0002 to amend the solicitation close/Bid opening date to 11 August 2022 as well as add an additional "Site Walk Only" for the project location on 02 August 2022 at 1:00PM CDT. Please see attached amendment 0002 for details.

This update on 22 July 22 issues the amendment 0001 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #5 dated 18 July 2022.  Amendment and Addendum # 5 documents are added to the attachments section here of this posting.

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Update #4 ·

This update on 01 August 2022 issues the amendment 0003 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #6 dated 29 July 2022 and issue Request for Information (RFI)1 responses.  Amendment, Addendum #6 documents and RFI1 CES Construct BCE Complex with applicaple attachments are added to the attachments section here of this posting.

This update on 27 July 2022 issues the amendment 0002 for Solicitation W50S7U-22-B-0002 to amend the solicitation close/Bid opening date to 11 August 2022 as well as add an additional "Site Walk Only" for the project location on 02 August 2022 at 1:00PM CDT. Please see attached amendment 0002 for details.

This update on 22 July 22 issues the amendment 0001 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #5 dated 18 July 2022.  Amendment and Addendum # 5 documents are added to the attachments section here of this posting.

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Update #3 ·

This update on 27 July 2022 issues the amendment 0002 for Solicitation W50S7U-22-B-0002 to amend the solicitation close/Bid opening date to 11 August 2022 as well as add an additional "Site Walk Only" for the project location on 02 August 2022 at 1:00PM CDT. Please see attached amendment 0002 for details.

This update on 22 July 22 issues the amendment 0001 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #5 dated 18 July 2022.  Amendment and Addendum # 5 documents are added to the attachments section here of this posting.

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Update #2 ·

This update on 22 July 22 issues the amendment 0001 for Solicitation W50S7U-22-B-0002 to incorporate Addendum #5 dated 18 July 2022.  Amendment and Addendum # 5 documents are added to the attachments section here of this posting.

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Update #1 ·

This notice issues the Invitation for Bids, Solicitation # W50S7U-22-B-0002, 183 Construct Base Civil Engineer (BCE) Complex.  Please refer to the attached Solicitation, Specifications (Project Manual), Plans (Drawings), Addendums, Statement of Work (SOW), and SF 1705 (needed for site visit).  Site visit date, time, and location is identified in the subject solicitation.  Please read the solicitation and other documents thoroughly and abide by the solicitation requirements.

Files

Show all 16

Notice history

Notice Type Posted
183 Construct BCE Complex Award Award Notice
This notice Latest solicitation Solicitation
183 Construct BCE Complex Pre-Solicitation
183 Construct BCE Complex Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Construct Egress Maintenance Facility, F-22 Jbphh, Hawaii 96853, United States · NAICS 236220 Army National Guard Total Small Business
Adal building 78, BCE and fire facility Middletown, Pennsylvania 17057, United States · NAICS 236220 Pennsylvania National Guard No set-aside
Z2DA--537-24-106 Create Contractor Lie-Down Zone NAICS 236220 Veterans Integrated Service Network 12 No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity