This solicitation requests proposals to replace the roof and counterpoise on the Yakutat VHF Omnidirectional Range facility in Alaska. Offerors must propose to furnish all materials, equipment, labor, transportation, insurance, and supervision to complete the work described in the specifications, drawings, and attachments. A firm-fixed price construction contract will be awarded. Site visits must be scheduled by March 26th and all questions must be submitted in writing by this date. Proposals are due by March 31st. Offerors must be registered in the System for Award Management. The Federal Aviation Administration will evaluate proposals and reserves the right to communicate with offerors during the solicitation process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Yakutat (YAK) VOR Building Install EPDM Roofing System Yakutat, Alaska
Technical Specifications
Revision 0
Prepared By: Federal Aviation Administration Infrastructure Engineering Center - Anchorage 222 West 7th Avenue Anchorage, AK 99513-7587
DIVISION 1: GENERAL REQUIREMENTS
SECTION 01110: SUMMARY
SECTION 01310: COORDINATION
SECTION 01320: CONSTRUCTON SCHEDULES AND REPORTING
SECTION 01330: SUBMITTALS
SECTION 01450: QUALITY CONTROL
SECTION 01500: TEMPORARY FACILITIES
SECTION 01600: MATERIALS AND EQUIPMENT
SECTION 01710: CONSTRUCTION LAYOUT
SECTION 01720: WORK PLACE SAFETY & HEALTH
SECTION 01730: OSHA SAFETY REQUIREMENTS
SECTION 01750: PROTECTION OF EXISTING CONDITIONS
SECTION 01760: ORDERLY WORKSITE & SITE CLEANUP
SECTION 01770: CLOSEOUT PROCEDURES
DIVISION 6: CARPENTRY
SECTION 06100: ROUGH CARPENTRY
DIVISION 7: THERMAL & MOISTURE PROTECTION
SECTION 07532 EPDM ROOFING MEMBRANE
SECTION 07620: SHEET METAL FLASHING AND TRIM
DIVISION 10: SPECIALITIES
SECTION 10100 ANTENNA SHELTER (TEEPEE)
SECTION 10200 AZIMUTH POSITIONER BRACKETS
SECTION 10300 COUNTERPOISE
END OF SECTION
SECTION 01110
SUMMARY
PART 1 GENERAL
1.1 Section Includes
A. These Specifications, together with the referenced specifications, standards, and drawings specified in the Contract Documents, cover the contract requirements of the Federal Aviation Administration (FAA) for the Work to be performed.
1.2 Related Sections
A. Drawings and General Conditions of the Contract, Division 1 through Division 16 Specification Sections, and any attachments to this Contract apply to this Section and to the Contractor’s performance of the Work.
1.3 Definitions, Acronyms, Abbreviations, and References
GFM/GFE/GFP Government Furnished Material/Equipment/Property.
NTP Notice To Proceed.
Project Manager (PM) Refers to the FAA’s representative as identified in the Documents to monitor the performance of the Contract and progress of construction, and to identify, advise of, and assist in resolving any discrepancies that may arise during the course of construction. The PM or his/her RE acts as the on-site “eyes and ears” of the FAA, as well as the liaison for coordination of the Work.
Provide The word “provide” as it appears in contract specifications and drawings means, “furnish and install”.
Quality Conformance to the requirements established by the contract specifications and drawings.
Record Documents Drawings, Specifications, Addenda, Change Orders and other Modifications; also approved Shop Drawings, Product Data, Samples, and similar submittals required to be provided by the Contractor.
Record Drawings Drawing’s submitted by the Contractor to show the construction of a particular structure or Work as actually completed under the Contract.
Request for Information (RFI) The method used by the Contractor and FAA to document and transmit field generated technical issues relating to design and construction of the Project.
Resident Engineer (RE) FAA’s Representative identified and assigned to monitor the performance of the Contract and progress of construction on site.
Risk Management Plan (RMP) Comprehensive plan that identifies, and mitigates risk associated with Safety, Security, and Quality.
Schedule of Values The method used by the Contractor and FAA to allocate values to various portions of the Work that, when approved by the FAA, provides the basis for Contractor’s application for payment.
Shop Drawings Specific drawings, schedules, diagrams, and other data prepared for this Contract by the Contractor, their lower tier subcontractors, manufacturers, suppliers, or distributors, to illustrate a portion of the Work.
Submittal A submittal is a Contractor's or manufacturer's drawing, brochure, sample, certificate, warranty, or other material which provides detail for construction and quality control of the permanent Work and includes deliverables such as schedules, product cut sheets, Work procedures, or product samples that are required under the terms of the Contract.
Test Plan A detailed step-by-step procedure for testing major equipment and systems.
Test Results Documentation of specified quality assurance test results.
1.4 Summary of Work
A. General:
This project includes all work associated with the roof replacement of the Yakutat VHF Omnidirectional Range (VOR) facility in Yakutat, Alaska. The work will be performed in conjunction with the FAA. The Contractor is responsible for performing all work not specifically identified for the FAA.
B. Background:
The YAK VOR roof was replaced with a new EPDM roof and copper mesh counterpoise in July 2017. VOR operation has been restricted since then. This project is to replace the copper mesh counterpoise with a fully soldered copper counterpoise in order to improve facility performance. The existing roofing will be removed to the extent necessary to access and replace the counterpoise. A new EPDM roofing system will be installed reusing some of the items already installed on the roof. VOR antennae brackets and supports are surveyed and reinstalled to specified standards and tolerances.
C. Major Items of Work:
The following items are a brief summary of the project and are provided solely for the purpose of revealing the general nature of the work involved. The Contractor is responsible for accomplishing all items of work in accordance with the applicable drawings, specifications and conditions of the Contract. Any additional labor, materials, equipment, and/or appurtenances not specifically detailed or specified, but required to complete the project, must be provided by the Contractor as an integral part of the scope of work specified.
Contractor Plan Approval:
1. Prior to construction, Contractor shall submit a Risk Management Plan in accordance with these specifications. Contractor will allow FAA two business weeks to review initial plan submissions and one business week to review resubmissions from Contractor. Plan approval required before Notice To Proceed (NTP) will be issued.
2. Contractor must submit a COVID-19 Safety Plan (CVSP) in accordance with the supplemental document Special Contract Requirement: COVID-19 (Construction Only) attached to and made a part of these specifications. This is in addition to the Risk Management plan. Contractor will allow FAA two business weeks to review initial plan submission and one business week to review resubmissions from Contractor. Plan approval required before NTP will be issued or site access granted.
3. FAA submitted a Construction Safety and Phasing Plan (CSPP) to the State of Alaska in its application for a building permit. Contractor must submit a Safety Plan Compliance Document (SPCD) detailing how Contractor will comply with the requirements of the FAA CSPP. Contractor will allow FAA two business weeks to review initial plan submissions and one business week to review resubmissions from Contractor. Plan approval required before Notice To Proceed (NTP) will be issued. FAA CSPP has full force and effect of this contract.
4. Two NTP’s will be issued. A restricted NTP will be issued to allow for mobilization, staging, inventory, and inspection of materials on site. A second NTP will permit construction to start.
Survey:
1. Prior to demolition, survey and record the following: center location, elevation, and orientation of the VOR antennae pedestal plate inside the teepee; location, elevation, distance from center of pedestal plate, and angle between 16 VOR monitor antenna azimuth positioner brackets; and location and orientation of the teepee prior to removal. Survey accuracy is 1/16th inch. Deliver data to RE. Teepee is reinstalled to its original location and orientation (elevation may change slightly). VOR pedestal plate and azimuth positioner brackets are reinstalled to specified tolerances.
2. Following roof demolition, survey radius of existing plywood decking from center of pedestal plate to determine roundness at 10 degree intervals from center of pedestal plate. Deliver data to RE. Inform RE if roof decking is out of round. Provide position references with survey data so measurement locations are readily known viewing roof.
Roof Demolition:
1. Prior to start of the VOR outage and demolition of the existing roof, all new project materials are to be staged on site for ready installation of the new roof. This includes, but is not limited to, dimensional lumber, metal fascia flashing, vapor barrier, copper counterpoise sheeting/segments/rolled angle, cover board, fasteners, nylon washers, EPDM, adhesives, caulking, paint, tarpaulin, plastic sheeting, and other materials and equipment necessary for constructing the new roof. Contractor shall inventory and inspect all materials prior to the start of demolition to ensure all materials are on hand in sufficient quantity and satisfactory condition to replace the counterpoise and EPDM roofing without delay.
2. The VOR building contains hazardous materials, but all hazardous materials associated with the roofing were abated when the roof was replaced in 2017. Adhering to the scope of work will avoid hazardous materials on the project.
3. Pick-up GFM at the FAA shop in Yakutat and transport to the site. GFM will consist of new base and top gaskets for reinstalling the teepee. Contractor responsible for securing materials and equipment during project to include GFM.
4. Erect scaffolding completely around roof for fall protection and access to roof. Scaffolding is complete and in good order meeting all applicable codes and regulations.
5. FAA will shut-down VOR and DME for project. All other facility equipment will remain in service during project.
6. Seal and protect VOR building against dust, water, and debris intrusion. The VOR building contains highly sensitive electronic equipment. No dust, water, or other intrusions in the building will be acceptable. Protect antennae, panel boxes, exhaust hoods, air intakes, lights, alarms, A/C units, load banks, cabling, and all other equipment in, on, or around the building during construction. Protection of the building and equipment takes precedence over construction. FAA concern for damage or impacts to operational equipment will result in project shutdown at Contractor expense until situation is remedied to FAA satisfaction.
7. Provide sealed containers on site for all project wastes to prevent debris from being blown from site. Loose or torn material packaging must also be kept in sealed containers. Absence of wind will not preclude this requirement.
8. FAA will remove the VOR and DME antennae inside the teepee and 16 VOR monitor antennae from around the perimeter of the roof. Monitor antennae cabling will be left suspended at the roof perimeter and must not be damaged. Antennae cabling inside the teepee will be removed to below the pedestal plate and must not be damaged. Provide FAA 5 days notification to disconnect and remove antennae and cabling. Allow FAA 3 days to perform work.
9. Remove teepee from the roof as a unit. Fabricate hoist attachment utilizing all the bolt holes at the top of the teepee. Hoist attachment must reinforce top flange of teepee. Set the teepee on blocking so as not to torque the structure and secure against tipping in the wind. Protect teepee from damage or dirt. Do not disassemble teepee wall panels. Retain 18 fastener strips for reuse. Copper ground wire soldered to fastener strips is to be removed and discarded. Cold galvanize strips prior to reinstallation.
10. Roofing underneath the teepee is not weather proof. Provide a tarpaulin to protect the building from rain and the elements once teepee base flashing is cut. Tarpaulin shall meet the requirements of these specifications and be of sufficient size to extend down and cover the fascia. Protect water from pooling on roof, particularly at pedestal plate opening in center of roof. Continually secure and protect the exposed roof decking and building interior against inclement weather with the tarpaulin during course of work. Secure tarpaulin against loss, wind damage, and leaks with sand bags. Repair leaks immediately. Shield tarp from E/G exhaust pipe to avoid melting or fire. Provide 200 sf of 2mil plastic sheeting and 60ft all weather duct tape for FAA to cover equipment in case of emergency.
11. Remove monitor antennae azimuth positioner brackets from perimeter of roof. Protect brackets against damage or loss.
12. Remove and dispose of existing EPDM roofing membranes and termination bar, teepee octagon, monitor antennae bracket pads, cover board, copper mesh counterpoise and fasteners down to existing vapor barrier on decking. DO NOT remove or damage four copper ground plates at roof edge near the corners of the building. New counterpoise will be connected and grounded to existing ground plates at roof edge.
13. Remove eight pedestal plate hold-down clips. Retain clips for reinstallation.
14. Remove copper bonding segments on pedestal plate. Protect plate from damage. Discard segments.
15. Remove and retain monitor antennae mast support brackets on fascia for reinstallation. Retain pinch bolts for reuse.
16. Remove and retain ladder bracket attached to fascia for reinstallation.
17. Remove and retain Caution sign attached to fascia for reinstallation.
18. Engine generator exhaust support bracket is attached to fascia. Disconnect bracket and temporarily support exhaust pipe. Engine generator will remain in service and may start without notice.
19. Remove sheet metal fascia flashing. Protect plywood fascia from damage. DO NOT remove fascia bottom angle flashing.
20. DO NOT remove antennae cabling, conduit, or soffit. Protect from damage. Cabling is newer and will be reused.
21. All demolition work shall be completed prior to installing new roofing system.
Roof Construction:
1. At no time can openings be left around pedestal plate where water can pool in the protective tarp.
2. Install new vapor barrier over existing per the drawings. Cut new vapor barrier at roof edge.
3. Install new sheet metal fascia flashing. Sheet metal flashing is hemmed and rolled to roof radius.
4. Fully solder new copper counterpoise per the drawings. Continuously solder all copper sheets and rolled angle seams at roof perimeter together. Rolled angle radius about center point of pedestal plate is consistent +/- 1/4”. Protect vapor barrier from heat damage.
5. Ground new copper counterpoise to existing counterpoise ground plates at roof edge near four corners of the building. Fabricate 16oz. copper jumper plates as necessary to make positive connection.
6. Survey pedestal plate to magnetic north. Ensure plate is centered on roof, level, and at correct elevation prior to survey.
7. Ground copper counterpoise to pedestal plate per the drawings. Continuously solder copper segments to each other and copper counterpoise. Reinstall 8 hold-down clip with new lag screws.
8. Fasten new copper counterpoise to roof decking and fascia with stainless steel screws per the drawings.
9. Install and fasten 1/2“ high density cover board over copper counterpoise and pedestal plate per the drawings. Cut cover board flush with pedestal mounts and hold-down clips.
10. Survey and install (16) 9”x12” plywood azimuth positioner bracket pads at roof perimeter. Center each pad on its respective magnetic heading aligned radially to center of roof. Install pads same distance from center of pedestal plate +/-1/4”. Shim pads level within 1 degree. Create cant transition at pad edges using caulk.
11. Install new fully adhered EPDM over roof per drawings. Use new fasteners and nylon plates. Fold EPDM membrane over roof edge and secure to fascia with new termination bar. Roof shall have minimum 20-year, no dollar limit warranty, with no exclusions for ponding water, and a 120 mph wind warranty. EPDM shall be installed by a manufacturer authorized installer.
12. Survey and install teepee octagon on top of new EPDM roofing per the drawings. Ensure octagon is oriented correctly under teepee door. Ensure door is in approximate location as existing. Flash octagon with EPDM to new roofing making it watertight.
13. Reinstall teepee on octagon using refurbished fastening strips and new lag bolts and GFM gaskets. Flash outside base of teepee with pressure sensitive EPDM and sealant.
14. Reinstall pedestal risers on pedestal plate. Allow FAA 3 days to check alignment.
15. Fabricate neoprene gaskets and reinstall azimuth positioner brackets on pads +/-1/4” radially from center of pedestal plate and each other per the drawings. Caulk brackets.
16. Reconnect E/G exhaust pipe bracket to fascia using new hardware.
17. Reinstall existing ladder bracket and “Caution – Slippery When Wet” sign on fascia in same locations. Fascia is reinforced at that location for bracket.
18. FAA will reinstall VOR and DME antennae on roof using existing cabling.
19. Contractor to secure monitor antennae masts to fascia with existing angle brackets. Antennae masts are plumb.
20. Stencil monitor antennae magnetic headings on fascia per drawings.
21. Cut opening in existing soffit and install new soffit vents. Protect soffit, cable conduit, and building siding from damage.
22. FAA will tune and test equipment.
23. FAA will flight check VOR and return to service.
24. Provide two 12” square self-adhesive EPDM patch materials and primer to FAA for emergency roof repair.
25. At project completion, regrade potholes and ruts created in access road during construction with 10 yards new ¾”-minus crushed gravel.
26. Provide binder with executed roofing warranty information.
Building Siding Repair
1. Approximately 30sf of vinyl siding is missing or damaged on the south side of the building. See Detail 1 on Drawing YAK-D-VOR-C001. Contractor to repair and replace missing siding. Contractor to determine and match existing siding to greatest extent possible to include thickness, locking type, color, pattern or texture, and width. Siding panels must span from building corner to door without end laps. Work performed according to standard practice using correct tools for quality finish. Siding repair includes insulation, vapor barrier, and backing as required for complete wall repair.
1.7 Risk Management Plan
A. Contractor must develop and submit a RMP for approval within 5 days from Contract Award. RMP template to be provided after award. Construction must not commence until the RMP has been approved by the FAA. The Contractor must comply with all safety, health, and emergency response provisions of this Contract.
1.8 Project Schedule
A. Planned construction window for project is June 14, 2021, to July 17, 2021. A long term outage on the VOR and DME was requested for the planned project dates. All plan and material submittals, coordination meetings, material purchases and shipments to Yakutat, are to have been accomplished prior to the construction start date. Contractor must develop and submit to the FAA a preliminary Construction Progress Schedule (Schedule) and preliminary Schedule of Values for approval within 5 days from Contract award. The Contractor’s approved Schedule of Values and Schedule are conditions for payment. The Contractor’s Schedule must comply with the requirements of Section 01320, Construction Schedules and Reports. The Contractor must provide the following information with the Schedule: Time of Performance, Project Duration in Calendar Days and Work Schedule/Work Hours.
| 1.9 | Pre-Construction Meeting |
| A. | The FAA will schedule a Pre-Construction meeting after Notice of Award. Required attendance includes Contractor, Contractor’s Superintendent, and major lower tier subcontractors. An agenda will be provided which will include at a minimum a review of the RMP, Schedule, and Schedule of Values. The Contractor must submit other items identified in Section G.3 Progress payments or Payment Procedures at the Pre-Construction Conference for review at the meeting. Acknowledgements of all the reviews made at the session will be noted in the meeting minutes. |
| 1.10 | Pre-Deployment Meeting |
| A. | The FAA will schedule a Pre-Deployment meeting approximately two weeks prior to construction. Required attendance includes Contractor and Contractor’s Superintendent. The purpose of the meeting will serve a final review and coordination with the FAA prior to the start of construction. Contractor’s project plans must be approved prior to the meeting being scheduled. |
| 1.11 | Working Hours |
| A. | All work shall be performed between the hours of 7:00am and 6:00pm Monday through Saturday. Maximum number of hours worked per week is 60. No work on federal holidays unless otherwise requested and approved in writing 5 days in advance. Contractor shall make their work schedule known to the FAA prior to the start of work on site. |
| 1.12 | Site Access Requirements |
| A. | Project site is in the secured area of Yakutat Airport. No Contractor or lower tier subcontractor employees are allowed in the secured area of the airport without being properly badged or under direct escort of a properly badged Contractor employee. This includes all movement between the airport security gate and project site. Contractor shall have a minimum of three employees properly badged with escort and driving privileges for the project. FAA must authorize and submit Contractor employee badging applications online. Allow FAA Authorized Signatory 10 business days to submit Contractor employee online applications. Contractor employees designated as escorts must personally travel to Yakutat with two forms of identification to apply for a background investigation and complete all training necessary for badging, escort, and driving privileges on the airport. Background investigations take a few days to two plus weeks depending on the history of the individual. Contractor employees must return in person to pick-up their badges. Contractor is responsible for all fees associated with badging and vehicle permits necessary for working on Yakutat Airport. All contractor badges must be returned at the end of the project. Contractor responsible for fines due to badges not returned or lost. FAA will not be held responsible for delays associated with Contractor meeting State requirements for accessing and working on site. |
| B. | Access to certain locations of the project may be restricted due to facility operations. Contractor may be required at various times to yield to facility operations that may require use of the Site. Upon receiving such a notice, Contractor must vacate the subject area. Unless otherwise indicated, Contractor will have complete and exclusive use of the premises within the construction staging area limits for the execution of the Work. |
1.13 Contractor and Government Furnished Property
A. These Specifications identify labor, materials, plant and equipment to perform the Work. All material not specifically indicated as furnished by FAA must be furnished by Contractor. Contractor to pick-up GFM at the FAA Shop near the Yakutat Airport and transport to the project site. For the purposes of this Contract, GFE, GFM, and GFP are all used interchangeably.
B. Government Furnished Material will be provided by the FAA: The Contractor will be accountable for all GFM acquired under this Contract. The Contractor must not accept any GFM without documentation signed by both the Contractor and FAA indicating actual items and quantities received/transferred. GFM furnished but not installed will be returned to the FAA with documentation signed by both the Contractor and FAA indicating actual items and quantities received/transferred. The Contractor must adequately control, preserve, protect and maintain all GFM and contractor acquired property. GFM includes the following:
· Teepee top and base gaskets.
| 1.14 | Compliance with Local and Other Codes |
| A. | The Contractor will be responsible for coordination of all work at the Worksite, and for obtaining local permits. The Contractor must obtain and comply with any necessary licenses/permits that comply with applicable Federal, State, and Municipal regulations in connection with the scope of the work. The FAA will not be required to pay any amount for any action taken by a state or political subdivision. The following Contractor licensing and employee certifications will be required and submitted for approval: |
1. Surveying
2. Soldering
3. Equipment operators
4. EPDM roofing installers
| 1.15 | FAA Right of Access |
| A. | The FAA reserves the right to enter the premises during the term of the Contract for quality assurance work inspections and/or maintenance of existing navigational and communication facilities. |
| 1.16 | Site Inspection |
| A. | After NTP and prior to initiating Work, Contractor and RE must conduct joint inspections of the jobsite to determine the existing conditions and note any existing damage or defects. Existing damage or defects will be used as the basis for determination of damages caused by the Contractor's operations. |
1.17 Site Damage
A. Contractor will be responsible for the cost of any repair caused by Contractor’s operations or the operations of its lower tier subcontractors. All damage to the existing Site including, but not limited to, existing utilities and cables, facilities, equipment, buildings, and vegetation must be repaired. All such repairs must match the original finish and must be made utilizing materials, equal to or greater than the original materials, as approved by RE. All repairs must be made with no additional cost to FAA.
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION
3.1 Special Scheduling Requirements
A. The VOR is a critical navigational aid to pilots. Long term outages will be necessary to complete the demolition and construction at this site. The FAA will request a long term outage for the VOR and DME in advance of the project for the specified construction window in paragraph 1.8 – Project Schedule.
| 3.2 | Inspection of Work |
| A. | FAA retains the right to inspect all Work on the project, but has no obligation to do so. FAA’s inspections and tests are for the sole benefit of FAA and do not: |
1. Relieve the Contractor or its lower tier subcontractors of the responsibility to provide adequate quality control measures.
2. Relieve the Contractor or its lower tier subcontractors of the responsibility for damage to or loss of material before acceptance.
3. Constitute or imply acceptance.
B. The presence or absence of the RE does not relieve the Contractor or its lower tier subcontractors from any Contract requirement, nor is the RE authorized to change any requirement of the Contract.
3.3 Submittals
A. Contractor must submit document, data, and/or material submittals in accordance with Section 01330, Submittal Procedures, and/or as specified elsewhere in the Technical Specifications.
| 3.4 | Contract Closeout |
| A. | The Contractor is responsible for Contract closeout in accordance with Section 01770, Closeout Procedures. |
3.5 Project Specific Work Plans
A. Required Work Plans: The Contractor shall submit the below written Work Plans in accordance with these Technical Specifications. No Notice to Proceed will be issued until all the Plans have been submitted and approved by the FAA. The FAA will have 10 business working days to review and approve or reject the Plans. Necessary changes to the Plans for acceptance will restart the review clock. The FAA is not responsible for the submission of acceptable Work Plans. Failure, and any impacts resulting thereof, by the Contractor to submit acceptable Plans in a timely manner will not be held against the FAA.
1. Risk Management Plan (RMP)
2. Fall Protection Plan
3. COVID-19 Safety Plan (CVSP)
4. CSPP Safety Plan Compliance Document (SPCD)
*** THIS PAGE INTENTIONALLY LEFT BLANK ***
| Replace YAK VOR Roof | Summary | ||
| Yakutat, Alaska | Rev. 0 | 01110-9 |
SECTION 01310
COORDINATION
PART 1 GENERAL
1.1 Section Includes
A. This section specifies requirements for requests for information as well as special and regularly scheduled progress meetings.
1.2 Related Sections
A. General Conditions; Section 01110, Summary; Section 01320, Construction Schedules and Reports; and Section 01330, Submittals.
1.3 Request for Information (RFI) Procedures
A. Contractor to use their company’s form for submitting RFI’s. Provide FAA a sample RFI form at the Pre-Construction Meeting. Accurately complete the form for any RFI and submit two copies of the RFI to the Project Engineer and one copy to the CO.
B. RFIs identifying a technical question relating to the design or construction of the project shall be submitted to the RE for disposition by the Project Engineer. Copies of the RFI are to be provided to the Project Engineer and CO in accordance with subparagraph 1.3.A. Attach drawings, sketches, and other clarifying documents along with recommended resolution if known. Project Engineer will respond and transmit FAA’s response to the Contractor with copies to the RE and CO.
| C. | If Contractor determines that FAA’s response to the RFI may impose a cost or a schedule impact on the Work, Contractor must inform the Project Engineer in writing with copies to the RE and CO within (3) working days from receipt. Contractor is not to proceed with any Work that incurs additional cost or time on the basis of an RFI. If no cost or schedule impact notification is received from Contractor within the specified time, Contractor will be deemed to have accepted FAA’s response and responsibility for Work described therein. |
| D. | Contractor must maintain its own RFI log. The RFI number must be prefixed by FAA assigned number followed by a dash followed by a sequential number starting at 001. |
| 1.4 | Weekly Progress Meetings |
| A. | Contractor shall attend weekly meetings with date, time and location to be specified by Project Engineer. The purpose of these meetings will be to conduct a joint review, review the quality of the on-going Work, and agree on project progress and subsequent submittals of updated and actual progress schedules. |
| 1.5 | Pre-installation/Pre-work Meetings |
| A. | When required in individual specification sections, convene a pre-installation meeting at Worksite before starting work requiring a written work plan. The purpose of the meeting will be to review the Contractor’s work plan, determine acceptability of the Contractor’s work plan, and provide authorization to proceed with the Work if the work plan is acceptable. Require attendance of parties directly affecting, or affected by, work of the specific section and RE. Notify the RE and Project Engineer a minimum of two (2) days prior to the meeting. |
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION [Not Used]
| Replace YAK VOR Roof | Coordination | ||
| Yakutat, Alaska | Rev. 0 | 01310-2 |
SECTION 01320
CONSTRUCTION SCHEDULES AND REPORTS
PART 1 GENERAL
1.1 Section Includes
A. This section specifies requirements for scheduling and monthly progress reporting.
1.2 Related Sections
A. Section 01110, Summary; Section 01310, Coordination; and Section 01330, Submittals.
1.3 General Requirements for Construction Schedule
A. Within two weeks following contract award, and on a monthly basis thereafter, Contractor must submit three copies of the updated Schedule to the PM. After all Contract Work items are complete, and as a condition of final payment, Contractor must submit three copies of an "Asbuilt Contract Schedule" in same format as the Schedule showing actual start and finish dates for all Work activities and milestones, based on the accepted monthly updates.
B. Update the Schedule bi-weekly and provide copy to the Project Engineer and RE. Schedule updates must be the product of joint review meetings between the Contractor and RE. Enter actual progress on Schedule as agreed upon by the FAA. If in the opinion of the FAA the Contractor falls behind the approved Schedule, the Contractor must take steps necessary to improve its progress without additional cost to the FAA.
1.4 Monthly Progress Reporting
A. Monthly Schedule updates shall be the product of joint review meetings between the Contractor, the RE, and major active subcontractors. The joint review must focus on actual progress for the preceding month, planned progress for the upcoming month supported by a Contractor prepared 2-Week Look-ahead Schedule if required by the Project Engineer, impact to Schedule due to change notices issued, adverse weather, and any effected changes to the construction Schedule. The agreed upon progress and changes shall be incorporated in the Schedule update to be submitted. The update must always represent the actual history of accomplishment of all activities.
B. The monthly Schedule update shall form the basis for the Contractor's progress payments. The progress payment for an activity must be based on its agreed upon percentage of completion. On unit priced contracts, the approval of the Contractor's monthly requisition is contingent on the submittal of a satisfactory monthly Schedule update, however, the basis of payment will be the actual measurement of FAA accepted in place units of Work.
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION [Not Used]
| Replace YAK VOR Roof | Construction Schedules and Reports | ||
| Yakutat, Alaska | Rev. 0 | 01320-2 |
SECTION 01330
SUBMITTALS
PART 1 GENERAL
1.1 Section Includes
A. Submittals shall be provided to the FAA for approval as required by the Specifications, drawings, or as recommended by a manufacturer. This Section specifies the requirements for providing submittals required under the Contract.
1.2 Related Sections
A. Section 01320, Construction Schedules and Reports; Section 01450, Quality Control.
1.3 Submittal Schedule
A. The Contractor is solely responsible for creating a Submittal Schedule identifying whether the submittals are samples, cut sheets, certified test results, and adding additional submittals as required by specifications, drawings, or as recommended by a manufacturer. As applicable, the Submittal Schedule must state the action required for testing and inspection with the name of the persons authorized to review the submittal. The Contractor shall submit one electronic and three hard copies of the Submittal Schedule to the Project Engineer for approval within 10 calendar days of Contract Award.
| 1.4 | Warranties and Guarantees |
| A. | Contractor must provide warranties/guarantees executed by the respective manufacturers, suppliers, and lower tier subcontractors for all installations as required in the Contract or as is customarily provided with the particular piece of equipment or system. All warranties are to be executed, in writing, for the benefit of the FAA. Contractor must enforce all warranties for the benefit of the FAA if so directed by the FAA. In the event the Contractor's warranty has expired, the FAA may bring suit at its expense to enforce a Contractor's, manufacturer’s, or supplier's warranty. Contractor must provide complete information for each item as follows: |
1. Product or work item.
2. Firm, with name of principal, address and telephone.
3. Scope.
4. Date of beginning of warranty.
5. Duration of warranty.
6. Proper procedure to evoke the warranty in case of failure.
7. Instances that might affect the validity of warranty (example for roofing: wind, ponding water, chemical).
8. Contractor name or responsible principal, address and telephone number.
9. Extended warranties normally provided by manufacturers that are beyond the warranty of construction shall be specifically noted.
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION
| 3.1 | Submittal Submission Requirements |
| A. | Four (4) complete sets, one (1) original and three (3) copies, of all submittal data shall be submitted for review and acceptance. One (1) set will be marked and returned to the Contractor. All submittals must be accompanied by dated transmittal letters identifying the contents of the submittals. Transmittal letters must consist of one original and one copy. Facsimile copies will not be accepted. |
B. The Contractor must ensure that all submittals are made with adequate time for review and acceptance, including re-submittals, so as not to delay the job. The FAA will coordinate submittal review and return initial submittals within 10 business days and re-submittals within five (5) business days. Work must not commence prior to acceptance of required submittals by FAA.
C. Contractor must check and approve submittals prior to delivery to the FAA. The Contractor is cautioned that the time period stipulated in this Section does not include any allowance for re-submittal in cases where the Project Engineer determines that the Contractor’s approval of the submittal is not adequately justified. Any delay caused by inadequacies in the Contractor’s submittal will not entitle the Contractor to an extension of time or additional compensation. Lack of completeness or inadequate description will be justification for disapproval.
| 3.2 | Submittal Evaluation |
| A. | The FAA will evaluate all submittals requiring FAA responsive action. The Contractor remains responsible for complying with Contract requirements, referenced standards, and regulations. The FAA’s evaluation will not relieve the Contractor of the responsibility for any error that may exist. Unsolicited submittals not required by the Contract Documents will be returned with the notation that the submittal is not required by the Contract and that the FAA has not reviewed and has no comment on the submittal. The FAA’s evaluation will result in only one of four responses as follows: |
1. Approved: Work covered by the submittal may proceed provided Contractor complies with requirements of the Contract Documents.
2. Approved as Noted: Work covered by the submittal may proceed contingent upon Contractor acceptance of the corrections and/or notations and provided Contractor complies with the requirements of the Contract Documents.
3. Revise and Resubmit: Work covered by the submittal may not proceed until the submittal is revised in accordance with the corrections and/or notations and resubmitted.
4. Rejected: The submittal does not conform to the intent and requirements of the Contract Documents and the Contractor must resubmit.
| Replace YAK VOR Roof | Submittals | ||
| Yakutat, Alaska | Rev. 0 | 01330-3 |
SECTION 01450
QUALITY CONTROL
PART 1 GENERAL
1.1 Section Includes
A. This section specifies requirements for quality control of the Work including, but not limited to, certificates of compliance, inspections and testing by the Contractor, and surveillance by the FAA.
| 1.2 | Related Sections |
| A. | General Conditions of the Contract; Section E Inspection and Acceptance; Section 01110, Summary; Section 01320, Construction Schedules and Reports; Section; 01330, Submittals; and Section 01770, Closeout Procedures. |
1. Contractor’s Risk Management Plan A. Contractor’s RMP must identify Contract quality requirements for each activity and describe how Contractor intends to furnish control testing, certifications, and records in order to provide quality Work. The RMP must include procedures verifying equipment, workmanship, fabrication, construction, operations, and inspections comply with the Contract Documents. Minimum RMP requirements are as follows:
1. Name, resume, authority, and responsibility of QC Representative responsible for monitoring the quality of construction activities.
2. List of outside organizations including testing laboratories, architects, or consulting engineers that will be employed by the Contractor. Include a description of services to be provided.
3. List of definable features of work that have distinct and separate control requirements.
4. An inspection and test plan keyed to the construction schedule, following the order of the specification technical sections, indicating which inspections and tests will be performed, the names of persons responsible for the inspection and testing of each segment of work, and the time schedule and frequency for each inspection and test.
| 7. | Contractor’s procedure by which to identify, segregate, disposition, and correct nonconforming product and services. |
| 8. | Contractor’s procedure for initiating requests, control, and implementation of changes to the Contract’s scope of work, specifications, or requirements. |
| B. | The Contractor’s RMP must address the 4-step inspection process for each Definable Feature Of Work (DFOW) that includes: preparatory inspections, initial inspections, follow-up inspections, and final inspections. Minimum requirements are as follows: |
1. Contractor must develop checklists to document the 4-step inspection process for each DFOW
2. A copy of the completed checklists must be provided to the FAA RE on a weekly basis.
| 1.4 | FAA Quality Monitoring |
| A. | FAA may perform such inspections, test, and monitoring as necessary to determine or verify Contractor’s compliance with Contract requirements. Contractor must provide such facilities and assistance for FAA monitoring as may be reasonably required and must ensure that all quality control records and places of Work are open and available to FAA. FAA’s monitoring activities may consist of review, observation, inspection of Contractor personnel, material, equipment, processes, and test results including off-site inspections. FAA may perform quality audits of records and performance of Contractor or its lower tier subcontractors and suppliers. The Contractor, lower tier subcontractor or supplier being audited must be available during the audit as required by the FAA. Testing or inspecting by the FAA does not relieve the Contractor or its subcontractors from performing Work according to Contract requirements. |
| B. | The Project Engineer or RE will notify Contractor of any detected non-compliance with the requirements of this Section or other technical specification sections. Such notice, when delivered to Contractor at the Work site, shall be deemed sufficient for the purpose of notification. Contractor must take immediate corrective action after receipt of a non-compliance notice and maintain a detailed record of every non-compliance and corrective action taken. The Contractor must make no part of time lost due to non-compliance and/or stop orders the subject of a request for extension of time or compensation. Cost incurred by FAA to correct defective work will be deducted from the total amount due the Contractor. |
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION
3.1 Quality Reports
Contractor must provide forms to be used in conjunction with RMP reporting. A copy of all forms must be included with the RMP. The following requirements are listed for specific reports:
A. Test Reports: Contractor must be responsible for establishing a system that will record all tests results. Information on test designation, location, date of test, specification requirements, results and retest results, causes for rejection and recommended remedial actions shall be documented. A copy of test results must be sent directly from the agency performing the testing services to Project Engineer or RE. A copy of any failing report must be sent immediately. All test reports provided by a testing agency must be reviewed and signed by a competent, qualified individual in the related discipline of the test subject matter.
B. Construction Reports: Contractor must submit duplicate copies via e-mail to RE by 9:00 a.m. on the business day following day of report. At a minimum, daily construction reports must include the following information:
1. List of subcontractors at the site.
2. List of separate contractors at the site.
3. Approximate count of personnel at the site.
4. High and low temperatures, general weather conditions.
5. Accidents.
6. Meetings and significant decisions.
7. Unusual events.
8. Stoppages, delays, shortages, losses.
9. Meter readings and similar recordings.
10. Emergency procedures.
11. Orders and requests of governing authorities.
12. Change Orders received, implemented.
13. Services connected, disconnected.
14. Equipment or system tests and startups.
15. Inspections.
16. Partial Completions/Occupancies.
17. Substantial Completions authorized.
18. Number of days used in the Contract period to date.
C. Construction Photos: Provide copies of Contractor date stamped construction photos of salient items of work. Provide photos on USB or CD.
3.2 Record Drawings
A. The QC Representative shall ensure the Record Drawings (Redlines) required by the Contract are scalable, kept current on a daily basis, and marked to show deviations from the Contract drawings. QC Representative must ensure each deviation has been identified with appropriate modifying documentation.
3.3 Inspections and Testing Laboratory
A. All inspections and testing on and off site required by the Contract must be performed as specified in individual specification sections by a certified independent firm employed by the Contractor at Contractor’s expense. Inspecting, testing, and source quality control may occur on or off the Site. Contractor must submit qualifications and certifications of the independent inspections and testing firm for FAA approval. Contractor must submit testing reports by the independent firm to the Project Engineer and RE, in duplicate, indicating observations and results of tests and indicating compliance or noncompliance with Contract Documents. Contractor must furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested. Any retesting required because of nonconformance to specified requirements must be performed by the same independent firm at Contractor’s expense.
TS 5
Pjt.loc, Alaska NORTHWAY communication facility Section 00000 Section Title
| Replace YAK VOR Roof | Quality Control | ||
| Yakutat, Alaska | Rev. 0 | 01450-3 |
SECTION 01500
TEMPORARY FACILITIES
PART 1 GENERAL
| 1.1 | Section Includes |
| A. | This section specifies requirements for temporary services and facilities, including utilities, construction and support facilities, security and protection. |
| B. | Due to COVID-19, use of FAA facilities will not be permitted. |
1.2 Related Sections
A. Section 01110, Summary; Section 01450, Quality Control.
| 1.3 | Temporary Utilities and Support Facilities |
| A. | Temporary construction and support facilities required include but are not limited to: |
1. Field Offices.
2. FAA Field Office.
3. Temporary heat.
4. Temporary electrical power.
5. Sanitary facilities, including drinking water.
6. Waste disposal services.
7. Construction aids and miscellaneous services and facilities.
| B. | Security and protection facilities required include but are not limited to: |
| 1. | Temporary fire protection. |
2. Barricades, warning signs, lights.
3. Temporary security fencing
1.4 Contractor Responsibilities
A. The Contractor must confine all operations (including storage of materials) to areas set out in the Contract or otherwise authorized or approved by the FAA.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Project Engineer, and must be built with labor and materials furnished by the Contractor without expense to FAA. The temporary buildings and utilities shall remain the property of the Contractor and must be removed by the Contractor at its expense upon completion of the Work. With the written consent of the CO, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor must use only established roadways in performance of the Contract. When transporting materials in prosecution of the Work, vehicles must not be loaded beyond the loading capacity of the vehicle or as prescribed by any laws or regulation. When it becomes necessary to cross curbs or sidewalks, the Contractor must protect them from damage; and must repair or pay for the repair of any damaged curbs, sidewalks, or roads.
1.5 Temporary Utility Installation
A. In accordance with the Special Requirements for COVID-19, Contractor use of FAA building space, power, toilets, or other facilities will not be permitted.
B. The Contractor must provide, maintain, and remove temporary electrical power, drinking and project water, and sanitary facilities as necessary for the proper and expeditious execution of work. If these facilities are not available on-site for use by the Contractor, then these facilities must be installed and maintained to comply with all federal, state, and local regulations governing such installations.
C. Locations of such facilities will be approved by the RE.
D. Contractor must provide and pay for all temporary services and facilities as specified herein and as necessary for the proper and expeditious execution of the Work.
E. Contractor must make, or have made, all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for same.
F. Contractor must provide all labor, materials, equipment and appurtenances necessary for the complete installation, operation and maintenance of all temporary service systems and facilities.
G. All Work under this Section must comply with applicable laws, rules, regulations, codes, ordinances and orders of all federal, state and local authorities having jurisdiction for the safety of persons, materials, and property.
| 1.7 | Temporary Water |
| A. | Contractor must make arrangements to transport all necessary water for construction and drinking purposes in accordance with CFR 29 Part 1926, Subpart D. |
| 1.8 | Temporary Toilets and Sanitation |
| A. | Contractor must provide ample and suitable on-site sanitary conveniences with proper enclosures and hand washing facilities in accordance with CFR Part 1926, Subpart D for the use of the workers employed on the Work. Temporary toilets must be properly maintained and serviced on a regular basis. Secure temporary toilets to prevent possible overturning. |
1.9 Temporary Electric Lighting and Power
A. Contractor must provide and maintain a temporary lighting and power system in accordance with CFR 29 Part 1926 Subpart K for construction and inspection purposes.
B. Contractor must make all necessary arrangements for temporary electrical services with the local power company to provide and pay for all temporary work or, at Contractor's option, provide an approved temporary engine generator at the project site for construction support.
1.10 Temporary Heat
A. Provide heating devices and heat as needed to maintain specified conditions for construction operations.
B. Maintain minimum 50 degree F ambient temperature in enclosed areas where construction is in progress.