Fredrick Douglas Building Window Replacement Project

This is a specification document for the Fredrick Douglas Building Window Replacement project (Y26-743) issued by Orange County, Florida Capital Projects Division. The project involves the removal of existing windows and installation of new aluminum storefront systems at the Fredrick Douglas Building located at 6565 Willow Street in Zellwood, Florida. The scope of work includes selective demolition of existing windows, installation of new non-impact or impact-resistant aluminum storefronts with glazing, joint sealants, gypsum board patching, and painting of affected areas. Three bid options are available: a base bid for non-impact storefront systems with security film at both entrances, Bid Additive #1 for impact-resistant systems at both entrances, and Bid Additive #2 for a mixed approach with impact-resistant storefront at the west (public) entrance and non-impact with security film at the east (employee) entrance. Sealed bids are due by 4:00 p.m. EST on Tuesday, June 9, 2026, submitted electronically through the OpenGov e-Procurement Platform. The estimated project cost is $319,428.00. Work must be performed during night shifts between 8:00 p.m. and 6:00 a.m., Monday through Friday, as the facility remains occupied during construction. All work is on a lump-sum contract basis with a single general contractor responsible for coordination with the owner and maintenance of the building's security and fire alarm systems during construction.

The contractor is responsible for all submittals, equipment delivery, construction scheduling, and coordination with Orange County's Project Manager prior to commencing work. Mobilization costs shall not exceed 5 percent of the contract price. The contractor must provide a detailed schedule of values, construction schedule, submittal schedule, and emergency contact list at the pre-construction meeting. All employees and subcontractors require background investigations at the contractor's expense, and personnel must comply with Orange County's tobacco-free policy, safety requirements, and conduct standards. The contractor assumes responsibility for all damage to furniture and equipment during construction, provides daily cleanup of work areas, takes pre-construction photographs documenting existing conditions, and maintains all submittals, change orders, and project documents at the site. Payment applications are submitted monthly with 5 percent retainage held until final completion. A Certificate of Substantial Completion must be obtained from local building officials before partial occupancy. All warranties must be provided at substantial completion, and final payment is contingent upon completion of all closeout requirements including project record documents, operation and maintenance manuals, and final inspections.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

605 E. ROBINSON STREET SUITE 750 ORLANDO, FL 32801 www.rbarchitects.com 407.648.7288 AR0014284

ORANGE COUNTY GOVERNMENT

FREDRICK DOUGLAS BLDG.

WINDOW REPLACEMENT

6565 WILLOW ST.

ZELLWOOD, FLORIDA

SPECIFICATIONS December 11, 2025

PREPARED FOR

Client:

ORANGE COUNTY CAPITAL PROJECTS DIVISION

400 SOUTH ST. � 5TH FLOOR

ORLANDO, FLORIDA 32801

rhodes+brito

A R C H I T E C T S

605 E. Robinson Street, Suite 750 Orlando, FL 32801 phone: 407-648-7288

AR0014284

STRUCTURAL

C&S Companies 605 E. Robinson St., Suite 210 Orlando, FL 32801 phone: 407-422-1118

BID DOCUMENTS

Orange County Capital Projects Division

Fredrick Douglas Bldg. � Window Replacement

Zellwood, FL.

Table of Contents

RHODES+BRITO ARCHITECTS TABLE OF CONTENTS - 1

R+B Error! Unknown document property name.-0077

TABLE OF CONTENTS

DIVISION 1 GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 12 00 MULTIPLE CONTRACT SUMMARY

01 21 00 ALLOWANCES

01 22 00 UNIT PRICES

01 23 00 BID ADDITIVES

01 25 00 SUBSTITUTION PROCEDURES

01 26 00 CONTRACT MODIFICATON PROCEDURES

01 29 00 PAYMENT PROCEDURES

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 31 19 PROJECT MEETINGS

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

01 32 33 PHOTOGRAPHIC DOCUMENTATIONS

01 33 00 SUBMITTAL PROCEDURES

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 60 00 PRODUCT REQUIREMENTS

01 73 00 EXECUTION

01 73 29 CUTTING AND PATCHING

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 CLOSEOUT PROCEDURES

01 78 00 WARRANTIES AND BONDS

01 78 39 PROJECT RECORD DOCUMENTS

DIVISION 2 EXISTING CONDITIONS

02 41 13 SELECTIVE DEMOLITION

DIVISION 7 THERMAL AND MOISTURE PROTECTION

07 92 00 JOINT SEALANTS

DIVISION 8 ALUMINUM STOREFRONTS AND ENTRANCES

08 41 19 ALUMINUM STOREFRONT (NON-IMPACT)

08 41 20 ALUMINUM STOREFRONT (IMPACT RATED)

08 80 00 GLASS AND GLAZING

DIVISION 9 FINISHES

09 29 00 GYPSUM BOARD

09 91 00 PAINTING

END OF TABLE OF CONTENTS

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 1

R+B #18019-0054 CONSTRUCTION DOCUMENTS

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. When titles such as Engineer, Project Engineer, or Owner are used throughout the specification, this implies Orange County as property Owner and/or an officially appointed County Representative.

1.2 PROJECT INFORMATION

A. Project Identification:18019-0077

B. Project Description: F r e d r i c k D o u g l a s B u i l d i n g W i n d o w R e p l a c e m e n t

C. Architect: Rhodes+Brito Architects

1.3 SCOPE OF WORK

A. Summary Of Work:

A. Removal of all existing windows and the Installation of new storefront windows.

1.4 CONTRACTOR RESPONSIBILITIES

A. The contractor shall have all submittals approved by the Engineer and accepted by the Owner prior to the start of active construction.

B. The contractor shall have all equipment and material onsite prior to the start of active construction.

C. The contractor shall submit to the Owner prior to the project pre-construction meeting the following:

• Schedule of Values

• Construction Schedule

• Submittal Schedule

• Emergency Telephone List including subcontractors and suppliers.

D. The contractor shall verify existing conditions of construction prior to start of active construction.

E. The contractor shall coordinate with the Owner on the operation of the existing fire alarm system prior to the start of active construction. There shall be an action plan for the operation of the fire alarm system during construction submitted by the contractor to the Owner for acceptance. This action plan shall be in place prior to the start of active construction. Any false fire alarms that occur during construction and are deemed by the Owner to be the fault of the contractor, the contractor shall pay all costs incurred from the local fire department for responding to a false alarm.

F. The contractor is responsible for moving furniture and/or equipment if necessary to perform the work included in the contract. The contractor is responsible for placing the

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 2

R+B #18019-0054 CONSTRUCTION DOCUMENTS

furniture and/or equipment back in its original location. The contractor is responsible for any damage to furniture, equipment, etc., which occur during construction. The contractor shall provide protection for floors, walls, furniture, equipment and any other items that may be subject to damage during the construction periods and shall be required to repair or replace them to original or better condition.

G. The contractor shall coordinate with the Owner on the operation of the security alarm system prior to the start of active construction. The contractor shall submit an action plan for operation of the security alarm system during construction to the Owner for acceptance prior to start of active construction. This action plan shall be in place prior to the start of active construction. Any false security alarms that occur during construction and deemed by the Owner to be the fault of the contractor, the contractor shall pay all cost incurred from the local police and/or sheriff department for responding to a false alarm.

H. The contractor shall take digital pictures or video of pre-existing conditions of the interior and exterior of the building prior to the start of active construction. Failure to provide digital pictures or video prior to start of construction places the responsibility on the Contractor to complete the necessary replacement, repairs, and/or cleaning as determined by the Owner, at no additional cost to the Owner. One CD copy of digital pictures or video of the existing site conditions shall be submitted to the Owner.

I. The contractor shall always maintain daily cleanup of construction areas. Costs for work areas that are not cleaned by the contractor shall be cleaned by the Owner and those costs shall be charged back to the contractor via a change order.

J. The contractor shall provide a construction schedule to the Owner�s Project Manager prior to the pre-construction meeting.

K. The contractor shall update the construction schedule weekly and submit it to the Owner�s Project Manager for review.

1.5 WORK COVERED BY CONTRACT DOCUMENTS

A. Type of Contract:

1. Lump Sum Cons t ruc t ion Con t rac t .

1.6 WORK UNDER OTHER CONTRACTS

A. Separate contracts may be issued to perform certain construction operations at the site.

The contractor of this project shall allow reasonable access and coordination to the other contractors.

1.7 WORK SEQUENCE

A. The facility shall remain occupied and operational while work is in progress. All work shall be fully coordinated in writing with Orange County Project Manager prior to commencement of work. All work shall be performed between the hours of 9:00 pm and 6:00 am, Monday through Friday. Work performed after normal business hours shall be done provided the area where work is done is fully operational and back in original condition prior to beginning of the next business day.

B. The contractor may work on the weekends at his or her discretion with prior written approval from Orange County Project Manager. Weekend work shall not be an additional cost to the Owner. The contractor shall coordinate with the Orange County

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 3

R+B #18019-0054 CONSTRUCTION DOCUMENTS

Project Manager for access to the building on weekends and after hours work.

1.8 CONTRACTOR USE OF PREMISES

A. General: During the construction period, the Contractor shall have limited use of the Project site for construction operations, as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. The Contractor shall coordinate which areas are acceptable to Staff for use during the life of the project. The Contractor�s use of the premises is limited only by the Owner�s right to perform construction operations with its own forces or to employ separate contractors on portion of the project.

B. General: Limited use of the Project site to construction activities in areas indicated within the limit of the premises. The Contractor may only use portion(s) of the site for storage or work areas only with prior approval from Orange County Project Manager.

A. Confine operations to areas within Contract limits indicated on the Drawings.

Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.

B. Keep driveways, loading areas, and entrances serving the premises clear and available to the Owner and the Owner�s employees at all times and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a) Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.

b) Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.

D. Where appropriate, maintain portions of the existing building affected by construction operations in a watertight condition throughout the construction period.

Repair damage caused by construction operations. Take all precautions necessary to protect the building and its occupants during the construction period.

E. Work Restrictions, General: Confine construction operations to the areas permitted by the contract documents and other Owner directives.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

2. All work may be carried out without time restrictions, unless otherwise directed by the Owner.

3. Unless otherwise directed by the Owner, work shall be scheduled as Night Shift between the hours of 8PM and 6AM each day.

F. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 4

R+B #18019-0054 CONSTRUCTION DOCUMENTS

G. Provide protection and safekeeping of material and equipment stored on premises.

H. Contractor shall move any stored material and equipment, which interfere with operations of the Owner or other contractors at no additional cost to the Owner.

I. Comply with Owner�s requirements for ingress and egress procedures, prohibitions against firearms, procedures for transportation of workers, safety and fire prevention requirements and all applicable pollution control requirements. Refer to the following reference requirements:

a) Orange County Safety and Health Manual http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHealt hManual.aspx#.Wql6OU2oupo

b) Orange County Policy Manual page 96 regarding Firearms http://www.orangecountyfl.net/portals/0/resource%20library/employment%20- %20volunteerism/Policy%20Manual.pdf

J. Contractor to require all employees and subcontractors to wear non-objectionable clothing; prohibit revealing clothing and articles of clothing with offensive writings displayed. The contractor shall require offending personnel to leave the premises until such clothing is changed.

K. Contractor employees and subcontractors shall not fraternize with County employees or the general public during the entire construction period.

L. Use of sound equipment (such as boom boxes, stereos, radios, etc.) is not allowed.

M. Contractor and their personnel shall abide to Orange County Tobacco free policy while on any Orange County property. This policy shall apply to building, parking lots, parks, break areas and worksites. Tobacco is defined as tobacco products, including but not limited to: Cigars, cigarettes, pipes, chewing tobacco and snuff.

Failure to abide by the policy may result in civil penalties levied under Chapter 386, Florida Statutes and/or Contract enforcement remedies. Refer to the following documents:

a) Orange County Smoking Policy:

http://www.orangecountyfl.net/Portals/0/resource%20library/employment%20- %20volunteerism/Employee%20Handbook.pdf

N. Conduct that is disrespectful, abusive or otherwise objectionable to the Owners� employees or general public will not be allowed at any time during the construction period. Repetitive complaints and violations of the requirements listed above will be cause for dismissal and or permanent removal of offending personnel from the project.

O. Contractor to coordinate with the Owner the site location for storage of equipment, machinery, materials, tools and a construction waste dumpster.

P. Contractor shall at all times keep the premises free of all waste or surplus materials, rubbish and debris, which is caused by contractor employees or subcontractors resulting from their work. Contractor shall maintain a safe work environment to all building occupants during the construction period.

1.9 SECURITY AND IDENTIFICATION

A. All costs for background investigations will be Contractor�s responsibility. The County shall have the right to request any additional investigative background information

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 5

R+B #18019-0054 CONSTRUCTION DOCUMENTS

including, but limited to, the employment record, Right-To-Know records, E-Verify system records (if the Contractor uses this service as a means to determine employment eligibility, available through www.uscis.gov), training records, payroll records, position for which hired including site location of any personnel assigned to perform the services.

The Contractor shall furnish, in writing, such information to the extent allowed by law, prior to commencement of services. The County reserves the right to conduct its own investigation of any employee of the Contractor.

B. Background checks are required for all Contracted and Sub-contracted employees. For Orange County Courthouse projects, background checks will be performed by the Orange County Sheriff�s Office. Instructions will be provided after contract award.

1. For security purposes and to maintain privacy when submitting Background Check information via e-mail the subject line of the email must contain the following

**EXEMPT**.

2. The County shall inform the contractor of their Background Check results.

C. Contractor�s employees will not be allowed in Orange County facilities without completed and approved background investigations.

1.10 OWNER OCCUPANCY

A. Owner Occupancy: The Owner will be occupying the building during construction.

Normal occupancy hours are 7:00 a.m. to 6:00 p.m. Monday through Friday, however this may vary with show activity.

A. A Certificate of Substantial Completion shall be executed for each specific portion of the Work to be occupied prior to Owner occupancy.

B. Obtain a Certificate of Occupancy from local building officials prior to Owner occupancy.

C. Prior to partial Owner occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon occupancy, the Owner will provide operation and maintenance of mechanical and electrical systems in occupied portions of the building.

1.11 DISTRIBUTION OF RELATED DOCUMENTS

A. The Contractor is solely responsible for the distribution of ALL related documents/drawings to ALL appropriate vendors/subcontractors to ensure proper coordination of all aspects of the project and its related parts during bidding and construction.

1.12 CONTRACT DOCUMENT FILE

A. Copies of the Contract Documents, Plans, Specifications, Addenda, Change Orders, Engineers Supplemental Instructions, approved Shop Drawings, Substitution Acceptances, etc. shall be placed and maintained at the project site by the Contractor throughout the entire contract period. These said documents shall be filed in a manner that allows for ease of retrieval. Documents shall be made available to the Engineer and the County's representatives throughout this same period.

1.13 SPECIFICATION AND DRAWING CONVENTIONS

Zellwood, FL.

01 11 00 Summary of Work

RHODES + BRITO 01 11 00 - 6

R+B #18019-0054 CONSTRUCTION DOCUMENTS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by the Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

PART 2 - PRODUCTS

2.1 ASBESTOS FREE MATERIAL

A. The contractor shall provide a written and notarized statement on company letterhead(s) to certify and warrant that ONLY ASBESTOS FREE MATERIALS AND PRODUCTS were provided AS REQUIRED BY THE Engineer. Such a statement shall be submitted with the final payment request. Final payment shall not be made until such statement is submitted. Contractor agrees that if materials containing asbestos are subsequently discovered at any future time to have been included in the construction, the Contractor shall be liable for all costs related to the redesign or modification of the construction of the project so that materials containing asbestos are removed from the facility. If construction has begun or has been completed pursuant to a design that includes asbestos containing materials, the Contractor shall also be liable for all costs related to the abatement of such asbestos.

PART 3 - EXECUTION (Not applicable).

END OF SECTION 01 11 00

01 12 00 Multiple Contract SummaryOrange County Capital Projects Division

Zellwood, FL.

RHODES + BRITO 01 12 00 - 1

R+B #18019-0054 Multiple Contract Summary

SECTION 011200 - MULTIPLE CONTRACT SUMMARY

PART 1 -

PART 2 - GENERAL

2.1 SUMMARY

A. Section includes a summary of each contract, including responsibilities for coordination and temporary facilities and controls.

B. Specific requirements for work of each contract are also indicated in individual Specification Sections and on Drawings.

C. Related Requirements:

1. Section 011000 "Summary" for the Work covered by the Contract Documents, restrictions on use of Project site, phased construction, coordination with occupants, and work restrictions.

2.2 DEFINITIONS

A. Permanent Enclosure: As determined by Architect, the condition at which roofing is insulated and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures equivalent in weather protection to permanent construction.

2.3 PROJECT COORDINATOR

A. Project coordinator shall be responsible for coordination between the General

Construction Contract and Orange County (OC).

B. Mechanical/electrical coordinator, who shall be under the direction of the Project coordinator, shall be responsible for coordination between the Plumbing Contract, HVAC Contract, Electrical Contract and Orange County (OC).

2.4 COORDINATION ACTIVITIES

A. Coordination activities of Project coordinator include, but are not limited to, the following:

1. Provide overall coordination of the Work.

2. Coordinate shared access to workspaces.

3. Coordinate product selections for compatibility.

4. Provide overall coordination of temporary facilities and controls.

5. Coordinate, schedule, and approve interruptions of permanent and temporary utilities, including those necessary to make connections for temporary services.

6. Coordinate construction and operations of the Work with work performed by each

Contract and separate contracts.

7. Prepare coordination drawings in collaboration with each contractor to coordinate work by more than one contract.

8. Coordinate sequencing and scheduling of the Work including a combined contractors' construction schedule for entire Project.

9. Provide photographic documentation.

10. Provide quality-assurance and quality-control services specified in

Section 014000 "Quality Requirements."

11. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections.

12. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction.

Zellwood, FL.

RHODES + BRITO 01 12 00 - 2

R+B #18019-0054 Multiple Contract Summary

13. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site.

14. Provide field surveys of in-progress construction and site work and final property survey.

15. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked.

16. Coordinate cutting and patching.

17. Coordinate protection of the Work.

18. Coordinate firestopping.

19. Coordinate completion of interrelated punch list items.

20. Coordinate preparation of Project record documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record.

21. Print and submit record documents if installations by more than one contractor are indicated on the same contract drawing or shop drawing.

22. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set.

23. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record.

B. Responsibilities of Project coordinator for temporary facilities and controls include, but are not limited to, the following:

1. Provide common-use field office for use by all personnel engaged in construction activities.

2. Provide telephone service for common-use facilities.

2.5 GENERAL REQUIREMENTS OF CONTRACTS

A. Extent of Contract: Unless the Agreement contains a more specific description of the

Work of each Contract, requirements indicated on Drawings and in Specification Sections determine which contract includes a specific element of Project.

1. Unless otherwise indicated, the work described in this Section for each contract shall be complete systems and assemblies, including products, components, accessories, and installation required by the Contract Documents.

2. Trenches and other excavation for the work of each contract shall be the work of the General Construction Contract.

3. Blocking, backing panels, sleeves, and metal fabrication supports for the work of each contract shall be the work of the General Construction Contract.

4. The furnishing of access panels for the work of each contract shall be the work of each contract for its own work. Installation of access panels shall be the work of the General Construction Contract.

5. Equipment pads for the work of each contract shall be the work of the General Construction Contract.

6. Roof-mounted equipment curbs for the work of each contract shall be the work of the General Construction Contract.

7. Painting for the work of each contract shall be the work of the General Construction Contract.

8. Cutting and Patching: Provided by the General Construction Contract.

9. Through-penetration firestopping for the work of each contract shall be provided by the General Construction Contract.

10. Contractors' Startup Construction Schedule: Within five working days after startup horizontal bar-chart-type construction schedule submittal has been

Zellwood, FL.

RHODES + BRITO 01 12 00 - 3

R+B #18019-0054 Multiple Contract Summary received from Project coordinator, submit a matching startup horizontal bar-chart schedule showing construction operations sequenced and coordinated with overall construction.

B. Substitutions: Each contractor shall cooperate with other contractors involved to coordinate approved substitutions with remainder of the work.

1. Project coordinator shall coordinate substitutions.

C. Temporary Facilities and Controls: In addition to specific responsibilities for temporary facilities and controls indicated in this Section and in Section 015000 "Temporary Facilities and Controls," each contractor is responsible for the following:

1. Installation, operation, maintenance, and removal of each temporary facility necessary for its own normal construction activity, and costs and use charges associated with each facility, except as otherwise provided for in this Section.

2. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities.

3. Its own field office, complete with necessary furniture, utilities, and telephone service.

4. Its own storage and fabrication sheds.

5. Temporary enclosures for its own construction activities.

6. Staging and scaffolding for its own construction activities.

7. General hoisting facilities for its own construction activities, up to 2 tons (2000 kg).

8. Waste disposal facilities, including collection and legal disposal of its own hazardous, dangerous, unsanitary, or other harmful waste materials.

9. Progress cleaning of work areas affected by its operations on a daily basis.

10. Secure lockup of its own tools, materials, and equipment.

11. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities.

D. Temporary Heating, Cooling, and Ventilation: The HVAC Contract is responsible for temporary heating, cooling, and ventilation, including utility-use charges, temporary meters, and temporary connections.

E. Temporary Heating, Cooling, and Ventilation: The HVAC Contract is responsible for temporary heating, cooling, and ventilation before weathertight enclosure of building is complete. The HVAC Contract is responsible for temporary heating, cooling, and ventilation after permanent enclosure of building is complete.

F. Use Charges: Comply with the following:

1. Sewer Service: Include the cost for sewer service use by all parties engaged in construction activities at Project site in the General Construction Contract.

2. Water Service: Include the cost for water service, whether metered or otherwise, for water used by all entities engaged in construction activities at Project site in the General Construction Contract.

3. Electric Power Service: Include the cost for electric power service, whether metered or otherwise, for electricity used by all entities engaged in construction activities at Project site in the General Construction Contract.

2.6 GENERAL CONSTRUCTION CONTRACT

A. Work in the General Construction Contract includes, but is not limited to, the following:

1. The remaining work not identified as work under other contracts.

B. Temporary facilities and controls in the General Construction Contract include, but are not limited to, the following:

Zellwood, FL.

RHODES + BRITO 01 12 00 - 4

R+B #18019-0054 Multiple Contract Summary

1. Temporary facilities and controls that are not otherwise specifically assigned to the Plumbing Contract, HVAC Contract or Electrical Contract.

2.7 PLUMBING CONTRACT

A. Work in the Plumbing Contract includes, but is not limited to, the following:

1. Plumbing connections to equipment furnished by the Plumbing Contract.

B. Temporary facilities and controls in the Plumbing Contract include, but are not limited to, the following:

1. Plumbing connections to existing systems and temporary facilities and controls furnished by the Plumbing Contract.

2.8 HVAC CONTRACT

A. Work in the HVAC Contract includes, but is not limited to, the following:

1. Mechanical connections to equipment furnished by the HVAC Contract.

2.9 ELECTRICAL CONTRACT

A. Work in the Electrical Contract includes, but is not limited to, the following:

1. Electrical connections to equipment furnished by the Electrical Contract.

B. Temporary facilities and controls in the Electrical Contract include, but are not limited to, the following:

1. Electrical connections to existing systems and temporary facilities and controls furnished by the Electrical Contract.

PART 3 - EXECUTION (Not Used)

END OF SECTION 011200

Zellwood, FL.

01 21 00 Allowances

RHODES+BRITO 01 21 00 -1R+B

#18019-0054

SECTION 012100 - ALLOWANCES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

B. Types of allowances include the following:

1. Lump-sum allowances.

2. Unit-cost allowances.

3. Quantity allowances.

4. Contingency allowances.

5. Testing and inspecting allowances.

C. Related Requirements:

1. Section 012200 "Unit Prices" for procedures for using unit prices.

2. Section 014000 "Quality Requirements" for procedures governing the use of allowances for testing and inspecting.

1.2 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.

B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.

C. Purchase products and systems selected by Architect from the designated supplier.

1.3 ACTION SUBMITTALS

A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.

1.4 INFORMATIONAL SUBMITTALS

A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.

B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.

Zellwood, FL.

01 21 00 Allowances

RHODES+BRITO 01 21 00 -2R+B

#18019-0054

C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

1.5 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

1.6 LUMP-SUM, UNIT-COST AND QUANTITY ALLOWANCES

A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site.

B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.

C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted.

1. If requested by Architect, retain and prepare unused material for storage by Owner. Deliver unused material to Owner's storage space as directed.

1.7 CONTINGENCY ALLOWANCES

A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance.

B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.

C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit margins.

D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.

1.8 TESTING AND INSPECTING ALLOWANCES

A. Testing and inspecting allowances include the cost of engaging testing agencies, actual tests and inspections, and reporting results.

Zellwood, FL.

01 21 00 Allowances

RHODES+BRITO 01 21 00 -3R+B

#18019-0054

B. The allowance does not include incidental labor required to assist the testing agency or costs for retesting if previous tests and inspections result in failure. The cost for incidental labor to assist the testing agency shall be included in the Contract Sum.

C. Costs of services not required by the Contract Documents are not included in the allowance.

D. At Project closeout, credit unused amounts remaining in the testing and inspecting allowance to Owner by Change Order.

1.9 ADJUSTMENT OF ALLOWANCES

A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.

1. Include installation costs in purchase amount only where indicated as part of the allowance.

2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.

3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances.

4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.

1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.

2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

Zellwood, FL.

01 21 00 Allowances

RHODES+BRITO 01 21 00 -4R+B

#18019-0054

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

END OF SECTION 01 21 00

01 22 00 Unit PricesOrange County Capital Projects Division

Zellwood, FL.

RHODES+BRITO 01 22 00 - 1

R+B 18019-0054

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Requirements:

1. Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders.

1.2 DEFINITIONS

A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 22 00

Zellwood, FL.

01 23 00 Bid Additives

RHODES+BRITO ARCHITECTS 01 23 00 - 1

R+B 18019-0054

SECTION 01230 � BID ADDITIVES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for alternates.

1.2 DEFINITIONS

A. Additive: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added or deducted to/from the base bid amount if Owner decides to accept one of the Bid Additives shown in the drawings.

1. Additives described in this Section are part of the Work only if enumerated in the Agreement.

2. The cost for each additive is the net addition or deduction to the Contract Sum to incorporate the additive into the Work. No other adjustments are made to the Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the additive into Project.

1. Include as part of each additive, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of additive.

B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each additive. Indicate if an additive has been accepted.

Include a complete description of negotiated revisions to alternates.

C. Execute accepted additive under the same conditions as other work of the Contract. D.

Schedule: A schedule of additives is included at the end of this Section.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Base Bid: Installation of a non-impact storefront system with security film at both the East and West entrances.

Zellwood, FL.

01 23 00 Bid Additives

RHODES+BRITO ARCHITECTS 01 23 00 - 2

R+B 18019-0054

B. Bid Additive #1: Installation of an impact resistant storefront system on both the East and West entrances.

C. Bid Additive #2: Installation of an impact resistant storefront system at the West Entrance (Public entrance) and a non-impact resistant storefront system with security film at the East entrance (Employee entrance)

Note: refer to sheet A201 for additional information.

END OF SECTION 01 23 00

01 25 00 Substitution ProceduresOrange County Capital Projects Division

Zellwood, FL.

RHODES+BRITO ARCHITECTS 01 25 00 - 1

R+B 18019-0054

SECTION 01 25 00 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling request for substitutions made after award of the Contract.

B. The Contractor�s Installation Schedule and the Schedule of Submittals are included under Section �Submittal Procedures�.

1.3 DEFINITIONS

A. Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.

B. Substitutions: The Contract will be awarded based on the design, methods, materials and/or equipment as addressed in the Contract Drawings and/or described in the Contract Specifications. Addressing, describing or naming an item is intended to establish the type, function, characteristics and quality required in order to establish a base for bidding.

1. Contractor may submit for approval of substitutes for any equipment and/or material. In addition to the product documents, a written certification shall accompany the documentation indicating that the proposed substitute will have the same characteristics, will perform in accordance with the design requirements and that complies with all the requirements set for in the Contract. Any additional information required by the Owner or County Representative shall be provided by the Contractor. Rejection of any proposed substitute will be considered final and the Contractor shall not get into any agreement with manufacturers or providers until the submittal has been finally approved.

2. The basis design shall establish the minimum standard of quality.

3. Substitution requests are only allowed after contract award.

1.4 SUBMITTALS

A. Substitution Request Submittal: Request for substitution will be considered if received within thirty (30) days after contract award, as long as this time allowance will not impact the construction schedule.

1. Submit three (3) copies of each request for substitution for consideration.

Submit requests in the form and in accordance with procedures required for Change Order proposals.

2. Identify the product, or the fabrication or installation method to be

Zellwood, FL.

RHODES+BRITO ARCHITECTS 01 25 00 - 2

R+B 18019-0054 replaced in each request. Include related Specification Section number and Drawing numbers and titles. Provide complete documentation showing compliance with the requirements for substitution, and the following information, as appropriate:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c.. Product Data, including Drawings, and descriptions of products, fabrication, and installation procedures.

d. Samples, where applicable or requested.

e A detailed comparison of the significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include elements such as size, weight, durability, performance and visual effect.

f. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Owner and separate Contractors that will become necessary to accommodate the proposed substitution.

g. A statement indicating the substitution�s effect on the Contractor�s construction schedule compared to the schedule without approval of the substitution. Indicate the effect of the proposed substitution on overall Contract Time.

h. Cost information, including a proposal of the net change, if any in the Contract Sum.

i. Certificates and qualification data, where applicable or requested.

Certification by the Contractor that the Substitution proposed is equal to or better in every significant respect to that required by the Contract Documents, and that it will perform adequately in the application indicated. Include the contractor�s waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.

j. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

k. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

l. Research reports evidencing compliance with building code in effect for Project.

m. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of

Zellwood, FL.

RHODES+BRITO ARCHITECTS 01 25 00 - 3

R+B 18019-0054 availability, or delays in delivery.

n. Cost information, including a proposal of change, if any, in the

Contract Sum.

o. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

p. Contractor�s waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Engineer�s Action: Within two weeks of receipt of the request for substitution, the Engineer shall request additional information or documentation necessary for evaluation of the request if needed. Within two (2) weeks of receipt of the request, or one week of receipt of the additional information or documentation, whichever is later, the Engineer shall notify the Contractor of acceptance or rejection of the proposed substitution. If a decision on use of a proposed substitute cannot be made or obtained within the time allocated, use the project specified by name. Decision on the use of a product substitution or its rejection by the Engineer is considered final. Acceptance will be in the form of a Change Order.

4. Architect's Action: If necessary, Architect shall request additional information or documentation for evaluation within 10 days of receipt of a request for substitution. Architect shall notify Contractor of acceptance or rejection of proposed substitution within 5 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Conditions: The Contractor�s substitution request will be received and considered

Zellwood, FL.

RHODES+BRITO ARCHITECTS 01 25 00 - 4

R+B 18019-0054 by the Engineer when one or more of the following conditions are satisfied, as determined by the Engineer; otherwise, request will be returned without action except to record noncompliance with these requirements.

1. Extensive revisions to Contract Documents are not required.

2. Proposed changes are in keeping with the general intent of Contract

Documents.

3. The request is timely, fully documented and properly submitted.

4. The specified product or method of construction cannot be provided within the Contract Time. The request will not be considered if the product or method cannot be provided as a result of failure to pursue the work promptly or coordinate activities properly.

5. The specified product or method of construction cannot receive necessary approval by a governing authority, and the requested substitution can be approved.

6. A substantial advantage is offered to the Owner, in terms of cost, time, energy conservation or other considerations of merit, after deducting offsetting responsibilities the Owner may be required to bear. Additional responsibilities for the Owner may include additional compensation to the Engineer for redesign and evaluation services, increased cost of other construction by the Owner or separate Contractors, and similar consideration.

7. The specified product or method of construction cannot be provided in a manner that is compatible with other materials, and where the Contractor certifies that the substitution will overcome the incompatibility.

8. The specified product or method of construction cannot be coordinated with other materials, and the Contractor certifies that the proposed substitution can be coordinated.

9. The specified product or method of construction cannot provide a warranty required by the Contract Documents and where the Contractor certifies that the proposed substitution provide the required warranty.

B. The Contractor's submittal and Project Manager's acceptance of Shop Drawings, Product Data or Samples that relate to construction activities not complying with the Contract Documents does not constitute an acceptable or valid request for substitution, nor does it constitute approval.

C. Substitution request constitutes a representation that the Contractor:

1. Has investigated proposed product and determined that it meets or exceeds, in all respects, specified product.

2. Will provide the same warranty for substitution as for specified product.

3. Will coordinate installation and make other changes which may be required for work to be complete in all respects.

4. Waives claims for additional costs which may subsequently become apparent. All costs associated with the substitution will be paid by the Contractor regardless of approvals given, and regardless of subsequent difficulties experienced as a result of substitutions.

END OF SECTION 01 25 00

Zellwood, FL.

01 26 00 Contract Modification Procedures

RHODES+BRITO ARCHITECTS 01 26 00 - 1

R+B 18019-0054

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this section.

1.2 SUMMARY

A. This section specifies administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections: The following sections contain requirements that relate to this section:

1. Division 1 Section 01 25 00 Substitution Procedures for administrative procedures for handling requests for substitutions made after award of the Contract.

2. Division 1 Section 01 29 00 Payment Procedures for administrative procedures governing applications for payment.

3. Division 1 Section 01 33 00 Submittals for requirements for the Contractor�s Construction Schedule.

1.3 MINOR CHANGES IN THE WORK

A. Supplemental instructions authorizing minor changes in the work, not involving an adjustment to the Contract Sum or Contract Time, will be issued by the Project Manager.

B. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving…