Y25-762_Supplemental_Conditions.pdf
PDF 329 KB Posted
- Solicitation number
- Y25-762
- Issued by
- Orange County, Orlando City, Florida
About this file
This document is a set of Supplemental Conditions for the Orange County Convention Center Campuswide Floor Boxes and Sump Pump Upgrades project in Florida. The project has an anticipated construction duration of 730 consecutive calendar days from the official Notice to Proceed, with a final completion deadline 30 consecutive calendar days after substantial completion. Work is restricted by convention center events, with work hours anticipated to be from 6:00 PM to 6:00 AM, and contractors required to schedule around show activities. Liquidated damages will be applied at $500 per day for substantial completion and $250 per day for final completion if deadlines are not met.
The document outlines extensive requirements for contractor operations, including mandatory FDLE background checks for all staff, security protocols, daily reporting requirements, and specific guidelines for working in an active convention center environment. Contractors must utilize the county's e-Builder platform for communications, submit daily and monthly construction reports, and adhere to strict safety and work restriction protocols. The project's estimated cost is $5,008,903.00, with electronic bid submissions required through the OpenGov e-Procurement Platform by 4:00 PM EST on Tuesday, April 29, 2025. Contractors will need to provide their own equipment, waste disposal methods, and comply with detailed fire protection and safety protocols throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART C: SUPPLEMENTAL CONDITIONS
1. SECURITY AND IDENTIFICATION:
A. A Level 1 (5 years) FDLE Background check for the Contractor’s staff and its Subcontractors must be approved by Orange County’s Security team prior to working in any County facility.
Contractors are responsible for obtaining the necessary forms for background checks for work at the Convention Center. All background check results will be sent to the OCCC Project Manager.
The Contractor’s staff and its Subcontractors will not be allowed in Orange County facilities without a completed and approved background investigation.
The Convention Center Capital Planning Division will inform the Contractor of their Access Badge approval results.
B. The contractor shall be responsible for all costs for background investigations. Background checks must be renewed annually. The County shall have the right to request any additional investigative background information including, but limited to, the employment record, Right-To-Know records, E-Verify system records (if the Contractor uses this service as a means to determine employment eligibility, available through www.uscis.gov), training records, payroll records, position for which hired including site location of any personnel assigned to perform the services. The Contractor shall furnish, in writing, such information to the extent allowed by law, prior to commencement of services. The County reserves the right to conduct its own investigation of any employee of the Contractor.
For security purposes and to maintain privacy when submitting FDLE Background Checks via e-mail the subject line of the email must contain the following **EXEMPT**
C. Upon Background Check approval, the Contractor’s staff shall arrange an appointment with the Convention Center staff to obtain an Orange County photo ID badge. An affidavit of Identity form (issued by the Contractor) and a State of Florida ID or Driver’s License will be required from the staff. All badges must be returned at the end of the project. The cost associated with stolen, lost, or unreturned badges is $35.00 for each. Additionally, if the Contractor and/or Subcontractor staff checkout and use the Electronic Key FOB to access OCCC facilities they are required to return it at the end of the work shift to the place it was checked out. The cost associated with stolen, lost, or unreturned Electronic Key FOBs is $200.00 for each.
D. The Contractor shall arrange an appointment with the OCCC Project Manager to receive, when applicable, keys to the project areas the Contractor requires access. The Contractor shall be responsible for returning all the keys to OCCC Project Manager at the project close-out phase. If any of the keys are lost, the Contractor shall reimburse OCCC for replacement of the core associated with the key that was lost. The cost for each core is $35.00. The Contractor shall also request OCCC parking hang tags for Contractor’s staff to park on OCCC designated parking lots during construction work hours. The Contractor shall submit the required forms given by the OCCC Project Manager for the issuance of hang tags. All hang tags must be returned at the end of the project. The cost associated with lost, stolen, or unreturned parking hang tags is $35.00.
2. CONTRACTORS SUBMITTALS: The Contractor shall submit all submitals, product data, shop drawings, mockups and samples documenta�on and other submitals via e-Builder to the A/E Design Team. All submitals will be returned to the Contractor and all responses shall also be (filed) in the e-Builder. All approved submitals shall bear the A/E Design Team’s stamp. The Owner Project Team will manage and monitor at all �mes the Submital log in conjunc�on with the A/E Design Team. The status of the log will be reviewed by the Owner Project Team as a part of each Construc�on Progress Mee�ng.
3. CONSTRUCTION SCHEDULE / LIQUIDATED DAMAGES: This work has an anticipated construction substantial duration of 730 consecutive calendar days from the OCCC official Notice to Proceed, and a final completion of 30 consecutive calendar days from the date of substantial completion. On-Site work availability is limited due to convention center events. Work is required to be scheduled around show activity. If substantial and final completion is not met by the required time, liquidated damages will be applied at a rate of $500.00 per day for substantial and a rate of $250.00 per day for final completion, as per the provisions in the Contract governing liquidated damages. If applicable, liquidated damages for Substantial Completion and Final Completion may run concurrently, if Substantial is not reached prior to the Final deadline.
4. CONSTRUCTION SCHEDULE WITH EVENTS: The Conven�on Center is an occupied and ac�ve space that is opera�onal at all �mes. On-Site work availability is limited due to conven�on center scheduled show events and Orange County holidays. The project site is an�cipated to be available to the contractor seven (7) days per week. Contractor work hours are an�cipated to be from 6:00 PM to 6:00 AM. Any noise generated ac�vity off hours and/or any excep�ons to the agreed upon work hours must be approved in advance by the OCCC Project Manager, unless approved otherwise by the OCCC Project Manager at least 48 hours in advance for work outside those hours. Work shall be sequenced to accommodate the OCCC events/shows during the project dura�on.
Any permissible work activities during the non-workdays will be determined at the OCCC Project Manager’s discretion. With the advanced approval of the OCCC Project Manager, specific dates may be coordinated with the Contractor for their work schedule.
5. COMMUNICATION AND GENERAL OVERSIGHT: The Contractor shall communicate with all the project participants during all phases of pre-construction, construction, project close out and other project activities to include the following:
A. Communicate daily or periodically with the OCCC Project Manager and its Project Team as needed. The Contractor shall submit a report daily on concerns related to design and construction efforts, activities, costs, scope, and schedule.
B. The Contractor shall have a Supervisor/qualified person present onsite for the entire duration when performing their own work or any of their sub-contractors, suppliers or any other project team members.
C. The Contractor shall include in its bid a minimum of one (1) license in order to utilize the
County’s adopted e-BuilderTM program for all communications with the A/E Design Team, and other members of Owner Project Team. This is to include but not limited to: changes orders, RFI’s, submittals, daily reports or any other correspondence deemed to be necessary by the county project management team. The cost of a single license is approximately $2,050 per year. The Contractor is responsible for the costs of their e-Builder licenses and renewals throughout the duration of construction and closeout phases.
D. The Contractor shall conduct the project progress meetings and any other workshops with the OCCC Capital Planning Team and the Architect/Engineer of Record including preparation of the agenda, record meeting minutes, and distributing the meeting minutes to the attendees and uploaded to the E-Builder under Daily Reports Process within three (3) business days from the date of the meeting. The project progress meeting minutes shall include at the minimum following items as applicable:
1. Deliveries
2. Off-site Fabrica�on challenges/updates
3. Site Access Protocols
4. Hours of work
5. Hazards and risks
6. Housekeeping
7. Payment Requests Status
8. Submitals Status
9. Correc�on of Deficient Items
10. Request for Informa�on (RFI’s) Status
11. Project Schedule
12. Pending Change Orders, Claims and Disputes Status
6. CONSTRUCTION REPORTS: The Contractor shall submit and File in e-Builder Daily Construction
Reports within 48 hours. These reports shall contain information on construction activities, manpower, equipment, materials, deliveries, safety, and other pertinent information. Each construction daily report shall include:
A. The date, �me on and off site, weather condi�ons and temperature B. General discussion of the daily work and progress, including a description of the activities completed and started and an assessment of the work accomplished by location.
C. Project accidents, deficiencies, changes or corrective action to maintain schedule.
D. Damage to existing facilities E. Project delays, reason for delay and corrective action to maintain schedule.
F. Record when Contractor is on site, number of workers by craft and list of equipment items by type G. Construction testing activities, results, and observations H. Where possible and appropriate, the quantities of work should be put into place.
I. Description of potential disputes between the Contractor and Orange County and/or A/E Design
Team J. Description of any direction or corrective action given to the Contractor K. Description of non-conforming work
L. Detailed record of materials, equipment and number of works by craft used in connection with extra work, or in situations where there is reason to suspect a request for a change order or claim may be submitted by the Contractor.
M. Photographic documentation and associated log with description. These photographs should be capturing daily project progress, overall site conditions, job accidents, deficiencies noted, deviations or changes from drawings or technical specifications, items that could cause delays (i.e., weather conditions, unforeseen conditions) and staged materials/equipment.
N. The Contractor is responsible for completing the Maximo equipment decommissioning and replacement documentation in accordance with the OCCC Facilities Maximo system requirements. The County Project Manager will be responsible for documentation of the Asset Tags for New Capital Equipment installed as part of the project.
O. Incident Reports (if applicable)
Monthly reports shall be submitted to the Owner Project Team by the first of every month, detailing construction progress during the month, costs, safety remarks, schedule milestones, manpower and upcoming events. Each monthly report shall be Filed in e-Builder.
7. WORK RESTRICTIONS: The Contractor shall be responsible for covering exposed work areas. The work areas shall be covered to prevent visible exposure.
The Contractor is responsible prior to demolition of ceilings to survey the above ceiling and ensure existing wiring is not damaged during demolition.
The Contractor is responsible for providing their own equipment and method of construction waste disposal. The Contractor shall have a designated location for their waste disposal containers. The Contractor shall be responsible for ensuring these containers are used for disposal of project specific debris. The Contractor is also responsible for securing the waste disposal containers from unauthorized use.
Battery operated lifts shall have gel cell batteries. Accessibility for equipment such as scissor lifts or electric powered maintenance carts shall be permitted with limited access areas, as coordinated, and approved with the OCCC Project Manager.
Availability of space for staging/lay down area will determine whether County will permit the
Contractor to set up a staging area. The OCCC Project Manager will make reasonable staging/storage accommodations on property. The Contractor staging area on site will depend on availability of space; however, relocation of staging area may be required during project.
The OCCC facilities’ designated restrooms can be used by the Contractor with previous coordination and approval of the OCCC Project Manager. If deemed necessary by the OCCC Project Manager, the Contractor will be required to provide their own restroom facilities at no additional cost.
After completion of the work, the Contractor shall replace or restore to the original condition all affected areas within the project limits. The Contractor is required to provide all materials for patching and painting.
8. FIRE PROTECTION SYSTEM INSTALLATION PROTOCOL: The Contractor and their Sub-Contractors are responsible for reviewing and following the atached Fire Protec�on Protocol for Installing, Downloading the Program, Pretes�ng, and Final Tes�ng. Any devia�ons from the atached protocol will need writen authoriza�on from the OCCC Project Manager.
9. FIRE WATCH: The Contractor shall provide a 24/7 fire watch for all inac�ve areas during the construc�on phase. The fire watch is the ac�on of an onsite person whose sole duty is to watch for the occurrence of fire the en�re �me the fire sprinkler system and/or fire alarm system (includes but is not limited to smoke detectors, duct detectors, sprinkler risers, etc.) is disabled. Fire watch personnel shall be a fire watch trained security guard, they must be competent, equipped with a cell phone to contact OCCC Security (OCCC Security line 407-685-9828), have a thorough understanding of the purpose and responsibili�es of their assignment, and shall know the loca�on and opera�on of all portable fire ex�nguishers onsite. Fire watch personnel shall conduct con�nuous hourly rounds by walking throughout the affected area, looking for evidence of smoke, fire or any abnormal condi�ons. The specific route shall be laid out so that the fire watch person is required to pass through the en�re area to be covered. A separate log iden�fying each building, or area, under the fire watch by name and address shall be kept. Log entries shall be made hourly at the comple�on of each round. Log entries shall consist of the date, the �me the round was completed, a summary of what was observed, and the name and signature of the individual conduc�ng the fire watch. The fire watch log shall be kept readily accessible for review by the Fire Marshal and submited daily through the E- Builder system. The personnel must be a fire watch trained security guard. The onsite OCCC Fire Inspector will check to ensure that the fire watch security guards are properly trained.
10. OCCC SAFETY PROTOCOL: For any life threatening or medical emergencies, the Contractor should immediately call 911. The Contractor shall report any safety incidents (examples: damage to building;
injury to personnel; impact to building opera�ons) or equipment failures to OCCC Security and the County Project Manager immediately.
11. TRANSPORT DEVICES: Personal transport equipment such as rollerblades, razor scooters, skates, hover-boards, and skateboards are not permited on OCCC premises.
The Contractor shall obtain prior approval from the OCCC Project Manager for operation of electric motor vehicles (e.g. Segways®) on the show floor. Safe operating practices shall be used at all times.
Segways® and electric scooter-style wheelchairs are currently the only personal transport equipment with rubber wheels allowed in OCCC concourses, lobbies, and registration areas. Non-gasoline powered motorized vehicles, such as electric carts and bicycles, may be operated in OCCC’s exhibit halls during move-in and move-out days only. Bicycles shall be walked, not ridden, across any OCCC concourse, lobby, or registration area. All vehicles, transport devices, and equipment shall be operated in a safe manner.
Motorized vehicles, such as personnel carts, forklifts, pallet jacks, and other related motorized vehicles with steel and/or hard metallic wheels are not permitted on the OCCC’s concourses, lobbies, and registration areas. Lifts or other wheeled vehicles approved for use in carpeted areas shall have non-marking tires, or tires that are covered with carpet tape or heavy-duty polyethylene sheeting.
Carpeted areas shall be protected by Rhino board or similar products in concourse/high traffic areas.
The use of Masonite is not permitted in concourse/high traffic areas. Gasoline or propane motorized vehicles are not permitted on the OCCC’s concourses, lobbies, tunnels, and registration areas.
The on-site staging areas shall be coordinated and approved by the OCCC Project Manager. Any vehicle or equipment that requires charging of lead acid or similar battery type, shall be done outside of the exterior of the building.
Contractor vehicle parking is in a specific parking lot to be coordinated with OCCC Project Manager.
12. OWNER PROVIDED EQUIPMENT / CONTRACTOR INSTALLED: If the Contractor is provided with owner equipment/material, Contractor shall be responsible for costs associated with receiving the material from the shipper, storing material in designated loca�on, provide security for the stored material, relocate the material from staging area to jobsite, and to install, connect, erect, use, clean and condi�on, as required, in accordance with the instruc�ons of the applicable manufacturer instruc�ons/warranty. Contractor shall schedule and coordinate with the OCCC Project Manager the inspec�ons and reloca�on to the jobsite of equipment/material. Any request for access to materials stored by OCCC managed loca�ons outside of normal business hours would need to be approved by the OCCC Project Manager at least forty-eight (48) hours in advance. The contractor shall inspect the equipment/material prior to accep�ng it from the OCCC Warehouse or other OCCC managed loca�ons. A�er acceptance, Contractor shall be responsible for the condi�on of the equipment/material un�l final acceptance of the project. Any delivered equipment/material found to be damaged shall be reported to OCCC Project Manager within 48 hours (via email with pictures and serial number and descrip�on of damages). The owner will be responsible for contac�ng suppliers regarding any warranty issues.
13. UTILITY COORDINATION: The Contractor shall coordinate any u�lity improvements and / or reloca�ons for this project. The Contractor shall not use u�lity delays as a basis for addi�onal compensa�on. The Contractor shall be responsible for all coordina�on with u�li�es and the OCCC Project Manager and shall cooperate fully with u�lity companies in the reloca�on of their u�li�es.
14. TEMPORARY POWER: Where possible, the owner can provide temporary power with minimum of 48 hours no�ce request to the County Project Manager. The Contractor is responsible for connec�on to the owner provided power and also arrange for temporary power in the event of any Emergency events when the OCCC power system is not available (e.g., Storm Events).
15. WORK INVOLVING ELECTRICAL HAZARDS: When possible, OCCC will endeavor to accommodate the electrical system(s) shutdown request(s). Requests need to be submited in wri�ng 2 weeks prior to actual shutdown and shall clearly indicate shutdown start �mes and end �mes. Pre-shutdown mee�ngs will be required to determine poten�al impacts to exis�ng Electrical and Ligh�ng system and the usage of OCCC facili�es. The Contractor shall design the installa�on of electrical system work to minimize the need to shut down electrical systems. If OCCC Capital Planning determines the Contractor must perform work without a panel shutdown due to equipment design or opera�onal limita�ons, the Contractor shall be responsible for providing workers with proper personal protec�on equipment to complete the scope of work at no addi�onal cost to owner. This would be the case for working around any energized equipment or circuits within the OCCC campus. The Contractor is also responsible for complying with the requirements outlined in the latest versions of the applicable electrical codes and licensing requirements pertaining to the project, including required field verifica�on of exis�ng electrical panels power configura�on within the project limits.
16. LICENSES/PERMITS/FEES: Refer to “Invita�on for Bids”, Item 2 “COUNTY PAID LICENSES/PERMITS
AND FEES”.
The Contractor is responsible for cost associated with permit lapse renewal. The Contractor is also responsible for cost associated with failed inspections and expired permits.
The Orange County Building Division has assigned the following Building Permit Numbers:
West Bldg. B25900402 North South Bldg. B25900403
17. REQUEST FOR ADDITIONAL INFORMATION (RFI): The County will require a reasonable amount of
�me, no more than 5 (five) business days, to respond to any RFI submited by the Contractor. Any delays in responding to the RFI shall not be the basis for reimbursement of any addi�onal compensa�on, including delay claims. The Contractor shall submit all Requests for Informa�on (RFI) through the e-Builder to request technical interpreta�on of the plans/drawings and specifica�ons.
The A/E Team will evaluate requested devia�on from the approved design or specifica�on; will review and respond to RFIs. Any supplementary sketches will be provided using e-builder for clarifica�on of construc�on plans and assist in resolving actual field condi�ons encountered e-Builder. The Owner Project Team will monitor and manage at all �mes an RFI log of all RFI’s submited by the Contractor in conjunc�on with the A/E Design Team. The status of RFI log will be reviewed as part of each Project Progress Mee�ng.
Attachment:
1. OCCC Fire Protec�on System Protocol for Capital Planning Projects - Version 1 Dated 08/19/2024
V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 1 | 3
OCCC Fire Protection System Protocol for Capital Planning Projects
Location: Orange County Convention Center
Procedure for installing:
1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm Company technicians arrive onsite.
2. The OCCC designated Fire Alarm Company technician checks in with prime contract holder.
3. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital Planning staff will inform OCCC Security/Life safety.
4. The OCCC Designated Fire Alarm Company technician arrives at the TSW in command and confirms number of existing alarms, troubles, supervisory, and bypasses on the system and documents in a debrief report.
5. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.
6. The OCCC Designated Fire Alarm Company technician disables any points needed and document disabled points.
7. The OCCC Designated Fire Alarm Company technician starts installation of scope.
8. The OCCC Designated Fire Alarm Company technician will reenable any disabled points disabled by
The OCCC Designated Fire Alarm Company.
9. Once the scope of work is complete The OCCC Designated Fire Alarm Company technician will verify the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.
10. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.
11. A debrief report that includes the system status will be signed and a copy left with the prime contract holder to be submitted to OCCC Capital Planning.
12. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.
Procedure for downloading a program:
1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm Company technicians arrive onsite.
2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the download at the specific node(s).
3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.
4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed.
Capital Planning staff will inform OCCC Security/Life safety.
5. The OCCC Designated Fire Alarm Company technician arrives at the TSW in command and confirms number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.
6. The OCCC Designated Fire Alarm Company technician also confirms all panels being downloaded are communicating with the network and no known troubles are found that will hinder the ability to download.
7. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X;XX as needed.
8. The OCCC Designated Firm Alarm Company technician turns on any bypasses as needed.
V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 2 | 3
9. The OCCC Designated Fire Alarm Company technician completes the download at each panel and does not move on to the next until the panel is completely back up on the network.
10. Once the scope of work is complete The OCCC Designated Fire Alarm Company technician will check the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.
11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.
12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.
13. A debrief report that includes the system status will be signed and a copy left with the prime contract holder to be submitted to OCCC Capital Planning.
14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.
Procedure for the OCCC Designated Fire Alarm Company pretesting:
1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm Company technicians arrive onsite.
2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the testing of the device(s).
3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.
4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital
Planning staff will inform OCCC Security/Life safety.
5. The OCCC Designated Fire Alarm Company technicians arrive at the TSW in command and confirm the number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.
6. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.
7. The OCCC Designated Fire Alarm Company technician turns on any bypasses as needed.
8. The OCCC Designated Fire Alarm Company technician starts required testing.
9. When testing the OCCC Designated Fire Alarm Company technician confirms points triggered are received at the TSW in command center.
10. Once the scope of work is complete the OCCC Designated Fire Alarm Company technician will check the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.
11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.
12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.
13. A debrief report that includes the system status will be signed and a copy left with the prime contract holder to be submitted to OCCC Capital Planning.
14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.
Procedure for final testing with the AHJ:
1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm
Company technicians arrive onsite.
2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the testing of the device(s).
3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.
4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital
Planning staff will inform OCCC Security/Life safety.
5. The OCCC Designated Fire Alarm Company technicians arrive at the TSW in command and confirm the number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.
6. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.
7. The OCCC Designated Fire Alarm Company technician turns on any bypasses as needed.
8. The OCCC Designated Fire Alarm Company technician starts required testing with AHJ.
9. When testing the OCCC Designated Fire Alarm Company technician confirms points triggered are received at the TSW in command center.
10. Once the scope of work is complete the OCCC Designated Fire Alarm Company technician will check
V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 3 | 3 the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.
11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.
12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.
13. A debrief report that includes the system status will be signed and a copy left with the prime contract holder to be submitted to OCCC Capital Planning.
14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.
File details come from the government source that posted it. Updated .