This document is a comprehensive set of construction specifications and contract documents for the Orange County Convention Center (OCCC) Campuswide Floor Box and Sump Pump Upgrades project in Florida. The project encompasses upgrades to floor boxes and sump pump systems in both the West and North-South Buildings, with an estimated total cost of $5,008,903.00. Sealed bids are due electronically through the OpenGov e-Procurement Platform by 4:00 pm EST on Tuesday, April 29, 2025. The project involves replacing valves for domestic water and compressed air in approximately 1,042 floor boxes in the North-South Building and upgrading sump pumps in both buildings' tunnel levels - specifically converting 12 simplex sump pumps to 12 duplex pump assemblies in the North-South building and 15 simplex sump pumps to 15 duplex pump assemblies in the West Building.
The solicitation requires electronic bid submissions only, with potential bidders required to create a free account on the OpenGov platform. Questions regarding the solicitation must be submitted by Thursday, April 3, 2025, at 5:00 pm EST through the platform's question and answer module. Technical support is available via chat, email, and phone. The project specifications detail extensive requirements for installation, materials, testing, documentation, and compliance with various building and electrical codes. Bidders will need to provide comprehensive documentation, including shop drawings, product data, operation and maintenance manuals, and comply with specific technical specifications for electrical, plumbing, and structural work across multiple building areas.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
FOR
Campuswide Floor Box and Sump Pump Upgrades
AT
CIP Project No. 0960-96 Hanson No. 23G1066
January 27, 2025
Prepared By:
Hanson Professional Services, Inc.
2300 Maitland Center Pkwy, Suite 310 Maitland, FL 32751
100% CDs
OCCC Campuswide Floor Box and Sump Pump Upgrades 100% CDs
OCCC Project #: 0960-96
Hanson Project #: 24G0030
TABLE OF CONTENTS 000110 - 1
Division Section Title
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
000110 TABLE OF CONTENTS
000115 LIST OF DRAWING SHEETS
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01 - GENERAL REQUIREMENTS
011100 SUMMARY OF WORK
012300 ADDITIVES
012500 SUBSTITUTION PROCEDURES
012600 CONTRACT MODIFICATION PROCEDURES
012900 PAYMENT PROCEDURES
013100 PROJECT MANAGEMENT AND COORDINATION
013119 PROJECT MEETINGS
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013230 PHOTOGRAPHIC DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017329 CUTTING AND PATCHING
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017800 WARRANTIES AND BONDS
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
Facility Construction Subgroup
DIVISION 02 - EXISTING CONDITIONS
NOT APPLICABLE
DIVISION 03 - CONCRETE
NOT APPLICABLE
Hanson Project #: 24G0030
TABLE OF CONTENTS 000110 - 2
DIVISION 04 - MASONRY
NOT APPLICABLE
DIVISION 05 - METALS
055000 METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
NOT APPLICABLE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
NOT APPLICABLE
DIVISION 08 - OPENINGS
NOT APPLICABLE
DIVISION 09 - FINISHES
099600 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
NOT APPLICABLE
DIVISION 11 - EQUIPMENT
NOT APPLICABLE
DIVISION 12 - FURNISHINGS
NOT APPLICABLE
DIVISION 13 - SPECIAL CONSTRUCTION
NOT APPLICABLE
DIVISION 14 - CONVEYING EQUIPMENT
NOT APPLICABLE
DIVISION 15 - RESERVED
NOT APPLICABLE
DIVISION 16 - RESERVED
NOT APPLICABLE
DIVISION 17 - RESERVED
NOT APPLICABLE
DIVISION 18 - RESERVED
NOT APPLICABLE
bradf02299 Snapshot
Hanson Project #: 24G0030
TABLE OF CONTENTS 000110 - 3
DIVISION 19 - RESERVED
NOT APPLICABLE
Facility Services Subgroup
DIVISION 20 - RESERVED
NOT APPLICABLE
DIVISION 21 - FIRE SUPPRESSION
NOT APPLICABLE
DIVISION 22 - PLUMBING
220513 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
220523.12 BALL VALVES FOR PLUMBING PIPING
220523.14 CHECK VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
221116 DOMESTIC WATER PIPING
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE PIPING SPECIALTIES
221329 SANITARY SEWERAGE PUMPS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
NOT APPLICABLE
DIVISION 24 - RESERVED
NOT APPLICABLE
DIVISION 25 - INTEGRATED AUTOMATION
NOT APPLICABLE
DIVISION 26 - ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262726 WIRING DEVICES
262813 FUSES
262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
bradf02299 Snapshot bradf02299 Snapshot
Hanson Project #: 24G0030
TABLE OF CONTENTS 000110 - 4
262913.03 MANUAL AND MAGNETIC MOTOR CONTROLLERS
DIVISION 27 - COMMUNICATIONS
NOT APPLICABLE
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
NOT APPLICABLE
DIVISION 29 - RESERVED
NOT APPLICABLE
Site and Infrastructure Subgroup
DIVISION 30 - RESERVED
NOT APPLICABLE
DIVISION 31 – EARTHWORK
NOT APPLICABLE
DIVISION 32 - EXTERIOR IMPROVEMENTS
NOT APPLICABLE
DIVISION 33 - UTILITIES
NOT APPLICABLE
DIVISION 34 - TRANSPORTATION
NOT APPLICABLE
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
NOT APPLICABLE
DIVISION 36 - RESERVED
NOT APPLICABLE
DIVISION 37 - RESERVED
NOT APPLICABLE
DIVISION 38 - RESERVED
NOT APPLICABLE
DIVISION 39 - RESERVED
Hanson Project #: 24G0030
TABLE OF CONTENTS 000110 - 5
Process Equipment Subgroup
DIVISION 40 - PROCESS INTERCONNECTIONS
NOT APPLICABLE
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
NOT APPLICABLE
DIVISION 42 - PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
NOT APPLICABLE
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE
EQUIPMENT
NOT APPLICABLE
DIVISION 44 - POLLUTION AND WASTE CONTROL EQUIPMENT
NOT APPLICABLE
DIVISION 45 - INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
NOT APPLICABLE
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT
NOT APPLICABLE
DIVISION 47 - RESERVED
NOT APPLICABLE
DIVISION 48 - ELECTRICAL POWER GENERATION
NOT APPLICABLE
DIVISION 49 - RESERVED
END OF TABLE OF CONTENTS
Hanson Project #: 24G0030
LIST OF DRAWING SHEETS 00 01 15 - 1
SECTION 00 01 15 - LIST OF DRAWING SHEETS
PART 1 - GENERAL
1.1 LIST OF DRAWINGS
List of Drawings: Drawings consist of the following Contract Drawings and other drawings of type indicated:
WEST BUILDING
G-001 - COVER SHEET
S-101 - STRUCTURAL OVERALL WEST BUILDING
S-102 - STRUCTURAL WEST HALL - HALL WA1
S-103 - STRUCTURAL WEST HALL - HALL WA2
S-104 - STRUCTURAL WEST HALL - HALL WA3
S-105 - STRUCTURAL WEST HALL - HALL WA4
S-106 - STRUCTURAL WEST HALL - HALL WB1
S-107 - STRUCTURAL WEST HALL - HALL WB2 & WB3
S-108 - STRUCTURAL WEST HALL - HALL WB4
S-109 - STRUCTURAL WEST HALL - HALL WC
S-110 - STRUCTURAL WEST HALL - HALL WD1
S-111 - STRUCTURAL WEST HALL - HALL WD2
S-112 - STRUCTURAL WEST HALL - HALL WE1
S-113 - STRUCTURAL WEST HALL - HALL WE2
S-201 - FLOOR BOX CORROSION REPAIR DETAILS
S-202 - FLOOR BOX LID SUPPORT REPAIR DETAILS
P-001 - PLUMBING NOTES, LEGENDS, AND ABBREVIATIONS – WEST BUILDING
P-100 - PLUMBING OVERALL WEST BUILDING
P-101 - PLUMBING WEST HALL - HALL WA1
LIST OF DRAWING SHEETS 00 01 15 - 2
P-102 - PLUMBING WEST HALL - HALL WA2
P-103 - PLUMBING WEST HALL - HALL WA3
P-104 - PLUMBING WEST HALL - HALL WA4
P-105 - PLUMBING WEST HALL - HALL WB1
P-106 - PLUMBING WEST HALL - HALL WB2 & WB3
P-107 - PLUMBING WEST HALL - HALL WB4
P-108 - PLUMBING WEST HALL - HALL WC
P-109 - PLUMBING WEST HALL - HALL WD1
P-110 - PLUMBING WEST HALL - HALL WD2
P-111 - PLUMBING WEST HALL - HALL WE1
P-112 - PLUMBING WEST HALL - HALL WE2
P-301 - WEST TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-302 - WEST TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-303 - WEST TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-501 - TYPICAL FLOOR BOX DETAILS
P-502 - TYPICAL FLOOR BOX DETAILS
P-601 - SCHEDULES
E-001 - GENERAL ELECTRICAL NOTES, LEGEND AND ABBREVIATIONS
E-100 - ELECTRICAL OVERALL WEST BUILDING
E-101 - ELECTRICAL WEST HALL - HALL WA1
E-102 - ELECTRICAL WEST HALL - HALL WA2
E-103 - ELECTRICAL WEST HALL - HALL WA3
E-104 - ELECTRICAL WEST HALL - HALL WA4
E-105 - ELECTRICAL WEST HALL - HALL WB1
E-106 - ELECTRICAL WEST HALL - HALL WB2 & WB3
E-107 - ELECTRICAL WEST HALL - HALL WB4
LIST OF DRAWING SHEETS 00 01 15 - 3
E-108 - ELECTRICAL WEST HALL - HALL WC
E-109 - ELECTRICAL WEST HALL - HALL WD1
E-110 - ELECTRICAL WEST HALL - HALL WD2
E-111 - ELECTRICAL WEST HALL - HALL WE1
E-112 - ELECTRICAL WEST HALL - HALL WE2
E-113 - ELECTRICAL OVERALL WEST TUNNEL LEVEL – ADDITIVE 2
E-114 - ELECTRICAL WEST HALL - SUMP PUMPS – ADDITIVE 2
E-115 - ELECTRICAL WEST HALL - SUMP PUMPS – ADDITIVE 2
E-501 – ELECTRICAL PANEL SCHEDULES
E-502 – ELECTRICAL PANEL SCHEDULES
E-503 – ELECTRICAL PANEL SCHEDULES
E-504 – ELECTRICAL PANEL SCHEDULES
E-505 – ELECTRICAL PANEL SCHEDULES
E-506 – ELECTRICAL PANEL SCHEDULES
E-507 – ELECTRICAL PANEL SCHEDULES
E-508 – ELECTRICAL PANEL SCHEDULES
E-509 – ELECTRICAL PANEL SCHEDULES
NORTH-SOUTH BUILDING
G-001 - COVER SHEET
P-001 - PLUMBING NOTES, LEGENDS, AND ABBREVIATIONS – NORTH-SOUTH BUILDING
P-100 - PLUMBING OVERALL NORTH-SOUTH BUILDING – ADDITIVE 1 & 2
P-101 - PLUMBING NORTH-SOUTH HALL - HALL NA1/NA2 1 – ADDITIVE 1
P-102 - PLUMBING NORTH-SOUTH HALL - HALL NA1/NA2 2 – ADDITIVE 1
P-103 - PLUMBING NORTH-SOUTH HALL - HALL NA2 – ADDITIVE 1
P-104 - PLUMBING NORTH-SOUTH HALL - HALL NB 1 – ADDITIVE 1
P-105 - PLUMBING NORTH-SOUTH HALL - HALL NB 2 – ADDITIVE 1
LIST OF DRAWING SHEETS 00 01 15 - 4
P-106 - PLUMBING NORTH-SOUTH HALL - HALL SA1/SA2 1 – ADDITIVE 1
P-107 - PLUMBING NORTH-SOUTH HALL - HALL SA1/SA2 2 – ADDITIVE 1
P-108 - PLUMBING NORTH-SOUTH HALL - HALL SA2 – ADDITIVE 1
P-109 - PLUMBING NORTH-SOUTH HALL - HALL SB1 – ADDITIVE 1
P-110 - PLUMBING NORTH-SOUTH HALL - HALL SB2 – ADDITIVE 1
P-301 - NORTH-SOUTH TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-302 - NORTH-SOUTH TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-303 - NORTH-SOUTH TUNNEL LEVEL ENLARGED PLANS - SUMP PUMPS – ADDITIVE 2
P-501 - TYPICAL FLOOR BOX DETAILS – ADDITIVE 1
E-001 – GENERAL ELECTRICAL NOTES, LEGEND, AND ABBREVIATIONS
E-100 - ELECTRICAL OVERALL N/S TUNNEL LEVEL – ADDITIVE 1 & 2
E-101 - ELECTRICAL N/S HALL - SUMP PUMPS – ADDITIVE 2
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
END OF SECTION 000115
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 1
SECTION 011100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
B. When the titles such as Engineer, Project Engineer, or Owner are used throughout the specification, this implies Orange County as property Owner and/or an officially appointed County Representative
1.2 PROJECT INFORMATION
A. Project Description: OCCC Campus Floor Box and Sump Pump Upgrades
B. County Project Number: 0960-96
C. Engineer: Hanson Professional Services Inc.
1.3 SCOPE OF WORK
A. Summary of Work:
The Orange County Convention Center (OCCC) desires to repair the Floor Boxes in the West Building, which will include modifications and replacement to the interior domestic water and compressed air piping and electrical/low voltage. There are approximately 1,234 Floor Boxes in the West Building. Also in the West Building, OCCC is upgrading approximately 12 sump pumps to 12 duplex pump assemblies
(each assembly includes two (2) pumps) and approximately 3 sump pumps to 3 simplex sump pumps in the tunnel levels (Bid Additive #2). For the North-South Building, OCCC desires to replace all of the valves for domestic water and compressed air in the approximately 1,042 floor boxes (Bid Additive #1).
OCCC is upgrading approximately 12 simplex sump pumps to 12 duplex pump assemblies (each assembly includes two (2) pumps) in the tunnel level of the North-South Building (Bid Additive #2).
1.4 CONTRACTOR RESPONSIBILITIES
A. The contractor shall have all submittals approved by the Engineer and accepted by the Owner prior to the start of active construction.
B. The contractor shall have all equipment and material onsite prior to the start of active construction.
C. The contractor shall submit to the Owner prior to the project pre-construction meeting the following:
1. Schedule of Values and Phasing Plan
2. Construction Schedule
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 2
3. Submittal Schedule
4. Emergency Telephone List including subcontractors and suppliers.
D. The contractor shall field verify existing conditions of construction prior to start of active construction.
E. The contractor shall coordinate with the Owner on the operation of the existing fire alarm system prior to the start of active construction. There shall be an action plan for the operation of the fire alarm system during construction submitted by the contractor to the Owner for acceptance. This action plan shall be in place prior to the start of active construction. Any false fire alarms that occur during construction and deemed by the Owner to be the fault of the contractor, the contractor shall pay all costs incurred from the local fire department for responding to a false alarm.
F. The contractor is responsible for moving furniture and/or equipment if necessary to perform the work included in the contract. The contractor is responsible for placing the furniture and/or equipment back in its original location. The contractor is responsible for any damages to furniture, equipment, etc., which occur during construction. The contractor shall provide protection for floors, walls, furniture, equipment and any other items that may be subject to damage during the construction periods and will be required to repair or replace to original or better condition.
G. The contractor shall coordinate with the Owner on the operation of the security alarm system prior to the start of active construction. The contractor shall submit an action plan for operation of the security alarm system during construction to the Owner for acceptance prior to start of active construction. This action plan shall be in place prior to the start of active construction. Any false security alarms that occur during construction and deemed by the Owner to be the fault of the contractor, the contractor shall pay all cost incurred from the local police and/or sheriff department for responding to a false alarm.
H. The contractor shall take digital pictures or video of pre-existing conditions of the interior and exterior of the building prior to the start of active construction. Failure to provide digital pictures or video prior to start of construction places the responsibility on the Contractor to complete the necessary replacement, repairs, and/or cleaning as determined by the Owner, at no additional cost to the Owner.
One CD copy of digital pictures or video of the existing site conditions shall be submitted to the Owner.
I. The contractor shall at all times maintain daily cleanup of construction areas. Costs for work areas that are not cleaned by the contractor will be cleaned by the Owner and those costs shall be charged back to the contractor via change order.
J. The contractor shall provide a construction schedule to the Owner’s Project Manager prior to the pre-construction meeting.
K. The contractor shall update the construction schedule weekly and submit it to the Owner’s Project
Manager for review.
L. The contractor shall schedule all work around the Convention Center show schedule, coordinate with
Owner’s Project Manager for schedule.
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 3
1.5 WORK COVERED BY CONTRACT DOCUMENTS
A. Type of Contract:
1. Project will be constructed under a single prime contract.
1.6 WORK UNDER OTHER CONTRACTS
A. Separate contracts may be issued to perform certain construction operations at the site. The contractor of this project will allow reasonable access and coordination to the other contractor/s.
1.7 WORK SEQUENCE
A. The facility shall remain occupied and operational while work is in progress. All work shall be fully coordinated in writing with Orange County Convention Center Project Manager prior to commencement of work. All work shall be performed between the hours of 6:00 pm and 6:00 am, Monday through Friday. Work performed after normal business hours shall be done provided the area where work is done is fully operational and back in original condition prior to beginning of the next business day.
B. The contractor may work on the weekends at his or her discretion with prior written approval from
Orange County Convention Center Project Manager. Weekend work shall not be an additional cost to the Owner. The contractor will coordinate with the Orange County Convention Center Project Manager for access to the building on weekends and after hours work.
1.8 CONTRACTOR USE OF PREMISES
A. General: During the construction period, the Contractor shall have limited use of the Project site for construction operations, as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. The Contractor shall coordinate which areas are acceptable to Orange
County Convention Center Staff for use during the life of the project. The Contractor’s use of the premises is limited only by the Owner’s right to perform construction operations with its own forces or to employ separate contractors on portion of the project.
B. General: Limited use of the Project site to construction activities in areas indicated within the limit of the premises. The Contractor may use any portion(s) of the site for storage or work areas only with prior approval from Orange County Convention Center Project Manager.
1. Confine operations to areas within Contract limits indicated on the Drawings. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.
2. Keep driveways, loading areas, and entrances serving the premises clear and available to the Owner and the Owners’ employees at all times and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
a. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 4
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.
4. Where appropriate, maintain portions of the existing building affected by construction operations in a watertight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building and its occupants during the construction period.
5. Work Restrictions, General: Confine construction operations to the areas permitted by the contract documents and other Owner directives.
a. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
b. All work may be carried out without time restrictions, unless otherwise directed by the
Owner.
c. Unless otherwise directed by the Owner, work shall be scheduled as Night Shift between the hours of 6PM and 6AM each day.
6. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
a. Notify Owner not less than two days in advance of proposed utility interruptions.
b. Obtain Owner's written permission before proceeding with utility interruptions.
7. Provide protection and safekeeping of material and equipment stored on premises.
8. Contractor will move any stored material and equipment, which interfere with operations of the
Owner or other contractors at no additional cost to the Owner.
9. Comply with Owner’s requirements for ingress and egress procedures, prohibitions against firearms, procedures for transportation of workers, safety and fire prevention requirements and all applicable pollution control requirements. Refer to the following reference requirements:
a. Orange County Safety and Health Manual http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHealthManual.asp x#.Wql6OU2oupo
b. Orange County Policy Manual page 96 regarding Firearms http://www.orangecountyfl.net/portals/0/resource%20library/employment%
20%20volunteerism/Policy%20Manual.pdf
10. Require all employees and subcontractors to wear no-objectionable clothing; prohibit revealing clothing and articles of clothing with offensive writing displayed. The contractor shall require offending personnel to leave the premises until such clothing is changed.
11. Contractor employees and subcontractors will not fraternize with County employees or the general public during the entire construction period.
12. Use of sound equipment (such as boom boxes, stereos, radios, etc.) is not allowed.
13. Contractor and their personnel shall abide by the Orange County Tobacco Free policy while on any
Orange County property. This policy shall apply to building, parking lots, parks, break areas and worksites. Tobacco is defined as tobacco products, including but not limited to: Cigars, cigarettes, pipes, chewing tobacco and snuff. Failure to abide by the policy may result in civil penalties levied http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHealthManual.aspx http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHealthManual.aspx http://www.orangecountyfl.net/portals/0/resource%20library/employment%20-%20volunteerism/Policy%20Manual.pdf http://www.orangecountyfl.net/portals/0/resource%20library/employment%20-%20volunteerism/Policy%20Manual.pdf
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 5
under Chapter 386, Florida Statutes and/or Contract enforcement remedies. Refer to the following documents:
a. Orange County Smoking Policy:
http://www.orangecountyfl.net/Portals/0/resource%20library/employment% 20-
%20volunteerism/Employee%20Handbook.pdf
14. Conduct that is disrespectful, abusive or otherwise objectionable to the Owners’ employees or general public will not be allowed at any time during the construction period. Repetitive complaints and violations of the requirements listed above will be cause for dismissal and or permanent removal of offending personnel from the project.
15. Contractor to coordinate with the Owner the site location for storage of equipment, machinery, materials, tools and a construction waste dumpster.
16. Contractor shall at all times keep the premises free of all waste or surplus materials, rubbish and debris, which is caused by contractor employees or subcontractors resulting from their work.
Contractor shall maintain a safe work environment to all building occupants during the construction period.
1.9 SECURITY AND IDENTIFICATION
A. All costs for background investigations will be Contractor’s responsibility. The County shall have the right to request any additional investigative background information including, but limited to, the employment record, Right-To-Know records, E-Verify system records (if the Contractor uses this service as a means to determine employment eligibility, available through www.uscis.gov), training records, payroll records, position for which hired including site location of any personnel assigned to perform the services. The Contractor shall furnish, in writing, such information to the extent allowed by law, prior to commencement of services. The County reserves the right to conduct its own investigation of any employee of the Contractor.
B. A Level 1 (5 years) Background Check for the contractor’s staff must be approved by Orange County’s
Security team prior to working in any County facility. Contractors are responsible for obtaining the necessary forms for background checks for work at the.
1. For security purposes and to maintain privacy when submitting FDLE Background Checks via e-mail the subject line of the email must contain the following **EXEMPT**.
2. The County will inform the contractor of their Background Check results.
3. Upon Background Check approval the contractor’s staff shall arrange an appointment with the
County staff to obtain an Orange County photo ID badge. An affidavit of Identity form (issued by the contractor) and a State of Florida ID or Driver’s License will be required.
C. Contractor’s employees will not be allowed in Orange County facilities without completed and approved background investigations.
1.10 OWNER OCCUPANCY
A. Owner Occupancy: The Owner will be occupying the building during construction. Normal occupancy hours are 7 a.m. to 6 p.m. Monday through Friday, however this may vary with show activity.
http://www.orangecountyfl.net/Portals/0/resource%20library/employment%25 http://www.orangecountyfl.net/Portals/0/resource%20library/employment%20-%20volunteerism/Employee%20Handbook.pdf http://www.orangecountyfl.net/Portals/0/resource%20library/employment%20-%20volunteerism/Employee%20Handbook.pdf
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 6
1. A Certificate of Substantial Completion will be executed for each specific portion of the Work to be occupied prior to Owner occupancy.
2. Obtain a Certificate of Occupancy from local building officials prior to Owner occupancy.
3. Prior to partial Owner occupancy, mechanical and electrical systems shall be fully operational.
Required inspections and tests shall have been successfully completed. Upon occupancy, the Owner will provide operation and maintenance of mechanical and electrical systems in occupied portions of the building.
1.11 DISTRIBUTION OF RELATED DOCUMENTS
A. The Contractor is solely responsible for the distribution of ALL related documents/drawings to ALL appropriate vendors/subcontractors to ensure proper coordination of all aspects of the project and its related parts during bidding and construction.
1.12 CONTRACT DOCUMENT FILE
A. Copies of the Contract Documents, Plans, Specifications, Addenda, Change Orders, Engineers
Supplemental Instructions, approved Shop Drawings, Substitution Acceptances, etc. shall be placed and maintained at the project site by the Contractor throughout the entire contract period. These said documents shall be filed in a manner that allows for ease of retrieval. Documents shall be made available to the Engineer and the County's representatives throughout this same period.
1.13 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all
Sections in the Specifications.
1.14 BUILDING/SITE SECURITY REQUIREMENTS
A. General Contractor will coordinate with Orange County Convention Center for any fire watch security provisions.
Hanson Project #: 24G0030
SUMMARY OF WORK 011100 - 7
PART 2 - PRODUCTS
2.1 ASBESTOS FREE MATERIAL
A. Contractor shall provide a written and notarized statement on company letterhead(s) to certify and warrant that ONLY ASBESTOS FREE MATERIALS AND PRODUCTS were provided AS
REQUIRED BY THE Engineer. Such statement shall be submitted with the final payment request.
Final payment shall not be made until such statement is submitted. Contractor agrees that if materials containing asbestos are subsequently discovered at any future time to have been included in the construction, the Contractor shall be liable for all costs related to the redesign or modification of the construction of the project so that materials containing asbestos are removed from the facility. If construction has begun or has been completed pursuant to a design that includes asbestos containing materials, the Contractor shall also be liable for all costs related to the abatement of such asbestos.
PART 3 - EXECUTION (Not applicable).
END OF SECTION 011100
Hanson Project #: 24G0030
ADDITIVES 012300 - 1
SECTION 012300 - ADDITIVES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for additives.
1.2 DEFINITIONS
A. Additive: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract
Documents.
1. Additives described in this Section are part of the Work only if enumerated in the
Agreement.
2. The cost for each additive is the net addition to the Contract Sum to incorporate additive into the Work. No other adjustments are made to the Contract Sum.
1.3 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the additive into Project.
1. Include, as part of each additive, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of additive.
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each additive. Indicate if additives have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to additives.
C. Execute accepted additives under the same conditions as other Work of the Contract.
D. Schedule: A schedule of additives is included at the end of this Section.
Hanson Project #: 24G0030
ADDITIVES 012300 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ADDITIVES
A. Bid Additive 1: OCCC desires to replace all of the valves for domestic water and compressed air in the 1,042 floor boxes in the North-South Building.
B. Bid Additive 2: OCCC is upgrading 12 simplex sump pumps to 12 duplex pump assemblies (2 pumps per assembly) in the tunnel level of the North-South building and 15 simplex sump pumps to 15 duplex pump assemblies (2 pumps per assembly) in the tunnel level of the West
Building.
END OF SECTION 012300
Hanson Project #: 24G0030
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling request for substitutions made after award of the Contract.
B. The Contractor’s Installation Schedule and the Schedule of Submittals are included under Section
“Submittal Procedures”.
1.3 DEFINITIONS
A. Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.
B. Substitutions: The Contract will be awarded based on the design, methods, materials and/or equipment as addressed in the Contract Drawings and/or described in the Contract Specifications.
Addressing, describing or naming an item is intended to establish the type, function, characteristics and quality required in order to establish a base for bidding.
1. The basis of design shall establish the minimum standard of quality.
2. Substitution requests during bidding are not allowed. Any substitution requested after contract award will be considered at the discretion of the Engineer and Owner.
1.4 SUBMITTALS
A. Substitution Request Submittal: Request for substitution will be considered if received within thirty (30) days after contract award. As long as this time allowance will not impact the construction schedule.
1. Submit three (3) copies of each request for substitution for consideration. Submit requests in the form and in accordance with procedures required for Change Order proposals.
2. Identify the product, or the fabrication or installation method to be replaced in each request.
Include related Specification Section number and Drawing numbers and titles. Provide complete documentation showing compliance with the requirements for substitution, and the following information, as appropriate:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
Hanson Project #: 24G0030
SUBSTITUTION PROCEDURES 012500 - 2
b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Product Data, including Drawings, and descriptions of products, fabrication and installation procedures.
d. Samples, where applicable or requested.
e. A detailed comparison of significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include elements such as size, weight, durability, performance and visual effect.
f. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Owner and separate
Contractors that will become necessary to accommodate the proposed substitution.
g. A statement indicating the substitution’s effect on the Contractor’s construction schedule compared to the schedule without approval of the substitution. Indicate the effect of the proposed substitution on overall Contract Time.
h. Cost information, including a proposal of the net change, if any in the Contract Sum.
i. Certificates and qualification data, where applicable or requested. Certification by the Contractor that the Substitution proposed is equal-to or better in every significant respect to that required by the Contract Documents, and that it will perform adequately in the application indicated. Include the contractor’s waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.
j. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.
k. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
l. Research reports evidencing compliance with building code in effect for Project.
m. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall
Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
n. Cost information, including a proposal of change, if any, in the Contract Sum.
o. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
p. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Engineers Action: Within two weeks of receipt of the request for substitution, the Engineer will request additional information or documentation necessary for evaluation of the request if needed. Within two (2) weeks of receipt of the request, or one week of receipt of the additional information or documentation, whichever is later, the Engineer will notify the Contractor of acceptance or rejection of the proposed substitution. If a decision on use of a proposed substitute cannot be made or obtained within the time allocated, use the project specified by name. Decision on the use of a product substitution or its rejection by the Engineer is considered final. Acceptance will be in the form of a Change Order.
Hanson Project #: 24G0030
SUBSTITUTION PROCEDURES 012500 - 3
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Conditions: The Contractor’s substitution request will be received and considered by the Engineer when one or more of the following conditions are satisfied, as determined by the Engineer;
otherwise, request will be returned without action except to record noncompliance with these requirements.
1. Extensive revisions to Contract Documents are not required.
2. Proposed changes are in keeping with the general intent of Contract Documents.
3. The request is timely, fully documented and properly submitted.
4. The specified product or method of construction cannot be provided within the Contract
Time. The request will not be considered if the product or method cannot be provided as a result of failure to pursue the work promptly or coordinate activities properly.
5. The specified product or method of construction cannot receive necessary approval by a governing authority, and the requested substitution can be approved.
6. A substantial advantage is offered to the Owner, in terms of cost, time, energy conservation or other considerations of merit, after deducting offsetting responsibilities the Owner may be required to bear. Additional responsibilities for the Owner may include additional compensation to the Engineer for redesign and evaluation services, increased cost of other construction by the Owner or separate Contractors, and similar consideration.
7. The specified product or method of construction cannot be provided in a manner that is compatible with other materials, and where the Contractor certifies that the substitution will overcome the incompatibility.
8. The specified product or method of construction cannot be coordinated with other materials, and where the Contractor certifies that the proposed substitution can be coordinated.
9. The specified product or method of construction cannot provide a warranty required by the
Contract Documents and where the Contractor certifies that the proposed substitution provide the required warranty.
B. The Contractor's submittal and Project Manager's acceptance of Shop Drawings, Product Data or
Samples that relate to construction activities not complying with the Contract Documents does not constitute an acceptable or valid request for substitution, nor does it constitute approval.
C. Substitution request constitutes a representation that the Contractor:
1. Has investigated proposed product and determined that it meets or exceeds, in all respects, specified product.
2. Will provide the same warranty for substitution as for specified product.
3. Will coordinate installation and make other changes which may be required for work to be complete in all respects.
Hanson Project #: 24G0030
SUBSTITUTION PROCEDURES 012500 - 4
4. Waives claims for additional costs which may subsequently become apparent. All costs associated with the substitution will be paid by the Contractor regardless of approvals given, and regardless of subsequent difficulties experienced as a result of substitutions.
PART 3 – EXECUTION (Not Used)
END OF SECTION 012500
Hanson Project #: 24G0030
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this section.
1.2 SUMMARY
A. This section specifies administrative and procedural requirements for handling and processing
Contract modifications.
B. Related Sections: The following sections contain requirements that relate to this section:
1. Division 1 Section 01 25 00 Substitution Procedures for administrative procedures for handling requests for substitutions made after award of the Contract.
2. Division 1 Section 01 29 00 Payment Procedures for administrative procedures governing applications for payment.
3. Division 1 Section 01 33 00 Submittals for requirements for the Contractor’s Construction
Schedule.
1.3 MINOR CHANGES IN THE WORK
A. Supplemental instructions authorizing minor changes in the work, not involving an adjustment to the Contract Sum or Contract Time, will be issued by the Project Manager.
B. Engineer will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document
"Architect's Supplemental Instructions."
1.4 CHANGE ORDER PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Engineer will issue a detailed description of proposed changes in the work that will require adjustment to the Contract Sum or Contract Time will be issued by the Project Manager, with a detailed description of the proposed change and supplemental or revised Drawings and Specifications, if necessary.
1. Proposal requests issued by the Engineer are for information only. Do not consider them instruction either to stop work in progress, or to execute the proposed change.
2. Unless otherwise indicated in the proposal request, within 5 days of receipt of the proposal request, submit to the Project Manager from the Owner's review, an estimate of cost necessary to execute the proposed change.
Hanson Project #: 24G0030
CONTRACT MODIFICATION PROCEDURES 012600 - 2
a. Include a list of quantities of products to be purchased and unit costs, along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include a statement indicating the effect the proposed change in the work will have on the Contract Time. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
d. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amount. Include costs of labor and supervision directly attributable to the change.
B. Contractor-Initiated Change Order Proposal Requests: When latent or other unforeseen conditions in mutual accord with the Owner Representative’s findings require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the
Engineer.
1. Include a statement outlining the reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of to be purchased and unit costs along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
Comply with requirements in Section 012500 “Substitution Procedures” - if the proposed change in the work requires that substitution of one product or system for a product or system not specified.
5. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amounts.
6. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the
Contract Time.
C. Proposal Request Form: Project Manager will transfer the information to the appropriate forms for approval. Use AIA Document G 709 for Change Order Proposal Requests.
D. Proposal Request Form: Use forms provided by the Owner for Change Order Proposals.
Hanson Project #: 24G0030
CONTRACT MODIFICATION PROCEDURES 012600 - 3
1.5 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: When the Owner and Contractor are not in total agreement on the terms of a Change Order Proposal Request, the Project Manager may issue a Construction
Change Directive instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. The Construction Change Directive will contain a complete description of the change in the Work and designate the method to be followed to determine change in the Contract
Sum or Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the
Construction Change Directive.
1. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.6 CHANGE ORDER PROCEDURES
A. Upon the Owner's approval of a Change Order Proposal Request, the Project Manager will issue a Change Order for signatures of the Owner and Contractor on County's Change Order form, as provided in the Conditions of the Contract.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 012600
Hanson Project #: 24G0030
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements governing the Contractor’s
Applications for Payment.
B. The Contractor’s Construction Schedule and Submittal Schedule are included in Section 01 33
00 – “SUBMITTAL PROCEDURES”.
1.3 SCHEDULE OF VALUES
A. Coordinate preparation of the Schedule of Values with preparation of Contractor’s Construction
Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment forms with Continuation Sheets, Submittals
Schedule, and Contractor's Construction Schedule.
2. Submit the Schedule of Values to the Owner at the earliest feasible date, but in no case later than Preconstruction Meeting.
3. Sub-Schedules: Where the Work is separated into phases that require separately phased payments, provide sub-schedules showing values correlated with each phase of payment.
B. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Identification: Include the following project identification on the Schedule of Values:
a. Project name and location.
b. Name of the Engineer
c. Engineer’s Project Number
d. Contractor’s name and address
e. Date of submittal
2. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:
a. Generic name
b. Related Specification Section
c. Change Orders (numbers) that have affected value
Hanson Project #: 24G0030
PAYMENT PROCEDURES 012900 - 2
d. Dollar Value
e. Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total
100 percent
3. Submit AIA Document G703 Continuation Sheets
4. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project
Manual table of contents. Break principal subcontract amounts down into several line items:
a. A value will be given for at least every major specification section (subsections can logically be grouped together).
b. A single material subcontractor will not be required to be broken down into labor and material unless it is anticipated the materials will be stored and invoiced prior to installation.
c. All multiple item subcontracts or work items (i.e., mechanical, electrical items, etc.)
will be shown broken down at least in labor and material (all taxes, burden and overhead and profit included).
d. Mobilization (move-on, bond, insurance, temporary office and sanitary service installation) shall not exceed 2 1/2% of contract price.
e. For multi-story work all items broken down per floor.
f. Plumbing: Typically shown per specification section, labor and material, per floor.
g. Electrical: Same as Plumbing.
h. Logical grouping of specification subsections is permitted.
5. Round amounts off the nearest whole dollar, the total shall equal the Contract Sum.
6. For each part of the Work where an Application for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
7. Margins of Cost: Show line items for indirect costs, and margins on actual costs, only to the extent that such items will be listed individually in Applications for Payment. Each item in the Schedule of Values and Applications for Payment shall be complete including its total cost and proportionate share of general overhead and profit margin.
a. At the Contractors’ option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown as separate line items in the
Schedule of Values or distributed as general overhead expense.
8. Schedule Updating: Update and resubmit the Schedule of Values before the next
Applications for Payment when Change Orders or Construction Change Directives result in a change in the contract sum.
1.4 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Owner’s representative and paid for by the Owner.
Hanson Project #: 24G0030
PAYMENT PROCEDURES 012900 - 3
1. The initial Application for Payment, the Application for Payment at time of Substantial
Completion, and the Final Application for Payment involve additional requirements. See items G, I, J and K of this section.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Forms: Use the County’s most updated form as the form for Application for Payment. Form given at the Preconstruction Conference. The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
D. Payment Application Times:…