This document is an Exhibit A Scope of Services for Design Services issued by Orange County, Florida for the West Building Roof Fans Replacement Project at the Orange County Convention Center (OCCC). The project involves replacing the existing roof fans in the West Building, which were original to the building's construction between 1983 and 1996 and have exceeded their useful life. The fans have caused significant roof leaks, necessitating comprehensive replacement to meet current codes. The Design Consultant will be responsible for preparing complete design and construction documents, including plans and specifications, with construction projected to start in February 2023 and estimated for final completion in February 2024. The total project duration is anticipated to be 12 months, with the Design Consultant required to submit all deliverables within 240 calendar days, including two-week review periods by the County.
The project has a specific focus on minimizing disruption to the Convention Center's ongoing events and shows, with an estimated project cost of $780,862.00. The Design Consultant must coordinate closely with the OCCC Sustainability Coordinator and consider the facility's existing certifications, including LEED Gold 2009 O+M, ISO 14001, and APEX/ASTM Certifications. The scope includes comprehensive design services, permitting, bidding assistance, and construction administration, with particular emphasis on sustainability opportunities. The consultant will need to use LEED B+C and O+M guidelines to identify potential improvements in areas such as materials and resources, indoor air quality, energy efficiency, water conservation, and site sustainability, while ensuring economic feasibility of proposed changes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
PART B: SCOPE OF SERVICES
EXHIBIT A
The Design Consultant (Consultant) shall provide Design Services for the OCCC West Building Roof Fans Replacement Project.
BACKGROUND:
The Orange County Convention Center Complex is located on almost 400 acres in Orlando, Florida, North of the intersection of Interstate 4 and State Road 528, consists of two (2) multipurpose buildings, the West Building and the North/South Building, designed for conventions, trade shows, meetings and consumer events. The Center has seven million square feet of space, of which approximately 2.1 million square feet is exhibition space. It contains 23 exhibit halls with over 125 configurations, 74 meeting rooms with over 230 configurations, 8 food courts, a ballroom, a 2,643 seat theater, a 200 seat lecture hall, and over 8,000 parking spaces. It is also accessible by four (4) pedestrian bridges which are connected to adjacent hotels. For additional information about OCCC, demographics, and any other major related facts, proposers should go to the OCCC website at: www.occc.net.
PURPOSE AND JUSTIFICATION:
The OCCC West Building current roof fans are original to its construction between 1983 and 1996 and have exceeded their useful lives. The West Building roof has experienced significant leaks at numerous areas, most considerably, around the curbs of the exhaust fans. The roof fans need to be replaced and brought up to all applicable codes.
Due to the OCCC ongoing show activity all the surrounding infrastructure is required to minimize any activity disruption and provide a safe environment for clients, guests and employees.
PROJECT OVERVIEW – SCOPE OF WORK DESCRIPTION:
The West Bldg. Roof Fans need to be replaced and brought up to code. Roof fans and all ancillary equipment sahall be removed and replaced with new like equipment.
THE FOLLOWING SERVICES SHALL BE PROVIDED BY THE CONSULTANT:
The Consultant shall provide final design and construction plans for the OCCC West Building Roof Fans Replacement Project. The Consultant shall perform those architectural and engineering services required to prepare a complete set of contract documents, (plans and specifications), as described elsewhere herein.
The Consultant’s Engineer-of-Record shall sign and seal a certification on the plans stating that the design has been prepared in accordance with design standards that are most appropriate, including County’s design standards, and any regulatory standards latest edition, in effect at the time of the Notice to Proceed. The Consultant shall utilize best engineering judgment, practices and principles in performing the work. The Consultant shall:
http://www.occc.net/
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
• Provide design documents that meet the additional needs of the OCCC West Building Roof Fans Replacement Project.
• Prepare construction documents to be competitively bid through the County’s Procurement Division. Provide the Owner with assistance in soliciting bids or proposal, and preparing addenda responses.
• Ensure that an acceptance procedure has been identified, established and incorporated in the Bid Documents for the testing/review and acceptance of the new OCCC West Building Roof Fans Replacement Project.
• Prepare all documentation and responses necessary to obtain permits from all agencies having jurisdiction over the project.
• Provide services during bidding, including but not limited to, review of bids, answer RFI’s, addendum assistance.
• Provide services during construction, including but not limited to, construction observation, review submittals and shop drawings, pay applications and answering RFI’s.
The fixed-fee and task-hour requirements shall be presented utilizing forms provided by the County’s Project Manager (Project Manager). The tasks included in this Scope of Services can be generally grouped into the following primary categories:
1. Administration
2. Design and Plans Preparation
3. Permitting
4. Bidding
5. Construction Administration
6. Sustainability
This Scope of Services addresses each task within these elements and serves to further define specific project requirements. The County will bid the Construction Documents developed by the Consultant in accordance with County’s procurement requirements.
The OCCC currently has and or will have contractual commitments to conventions, shows and exhibits, therefore the Consultant shall be required to develop a design of the project to account for schedule and sequence of the work such that minimal to no impact will result to ongoing business functions of the facility or scheduled shows and exhibits.
The Consultant shall submit all required deliverables and provide specific services, with the exception of Construction Administration Services, within 240 calendar days, inclusive of two-week review periods by County for each review of progress submittals, in order to allow sufficient time to solicit and award a construction contract. The awarded Contractor for this project will have a maximum of 12 Months (1 year) to complete the construction. Construction is projected to start in February 2023 and estimated Final Completion in February 2024 and with Construction activity scheduled around show/event schedule to be coordinated with OCCC Project Manager.
The Consultant shall include in its proposal two (2) licenses in order to utilize the County’s adopted e-BuilderTM program for all communications with the A/E Design Team, and other members of Owner Project Team. This shall include but not limited to: changes orders, RFI’s, submittals, daily reports or any other correspondence deemed to be necessary by the county project management
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46) team. The cost of a single license is approximately $2,050 per year. The cost of any additional e- Builders licenses shall be paid by the Consultant.
1. ADMINISTRATION
1.1. Notice to Proceed Meeting. The Consultant shall prepare for and attend a Notice to Proceed (NTP) Meeting with the Project Manager and staff. At this meeting, Orange County staff and key members of the Consulting team shall set the final parameters for the project, formally establish the Project deliverables, review the project criteria, scope and the project approach. The NTP may require an on-site meeting with the User Group.
1.2. Project Meetings. The appropriate members of the Consulting team shall attend project meetings with the Project Manager and staff to discuss project progress and status, technical issues, and upcoming events and activities. The purpose of these meetings is to maintain clear communication between the County and the Project Team. The Consultant shall prepare and distribute meeting minutes, on electronic format, following each of these meetings. Note: The number of project meetings will be determined at contract negotiation.
1.3. Project Management and Supervisions. The Consultant shall include Project
Management and Supervision as a percentage of labor-hours for each primary category except for Administration and Construction Administration Services.
1.4. Final Design Project Schedule. The Consultant shall prepare and submit a detailed project schedule prior to the Notice to Proceed Meeting for completion of final design and plans preparation identifying major tasks, their duration and tasks relationships. All deliverables shall be identified as milestones on the schedule. The Consultant shall submit an updated design project schedule as directed by the Project Manager.
1.5. Design Schedule. The Consultant shall prepare and submit a detailed schedule for design duration.
1.6. Utility Coordination. The Consultant shall coordinate with all utility providers within the project limits by furnishing plans at all design stages to utilities for review, confirmation of utility location, and relocation purposes. The development of the plans shall incorporate and consider the input provided by each utility to ensure that the final design considers all existing and proposed utilities. As part of each progress submittal, the Consultant shall provide a list of all utilities that have been provided copies of the construction plans, and the dates the plans were delivered to each Utility. The Consultant shall also provide a summary of the response received from each Utility. The Consultant shall conduct timely on-going utility coordination efforts to ensure timely receipt of design information from the various utilities. The Consultant shall resolve all utility conflicts prior to submitting final plans. No utilities shall be in conflict with any proposed improvements.
1.7. Quality Assurance/Quality Control. The Consultant shall designate appropriate independent staff to conduct Quality Assurance/Quality Control (QA/QC) reviews of all work products. These reviews shall be performed for all work products prior to their being submitted to the County for review or use. Work effort for QA/QC reviews shall be addressed as part of the work effort for each Pay Task as identified elsewhere herein.
The County will provide a QA/QC form.
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
1.8. Deliverables. Work to be completed under this section by the Consultant shall require the following items to be delivered and accepted by the County:
1.8.1. NTP Meeting Minutes
1.8.2. Project Meeting Minutes
1.8.3. Design Project Schedule
1.8.4. Construction Schedule
1.9. Pay Task. Work to be completed under this section by the Consultant shall be paid for under the following Pay Tasks as listed on the Activity and Fee Summary:
1.9.1. NTP Meeting and Meeting minutes
1.9.2. Project Meetings and Meeting minutes
1.9.3. Design Project Schedule
1.9.4. Construction Schedule
1.9.5. Coordination
1.10. Owner Direct Purchase Program. The County may utilize the Owner Direct Purchase program to the extent reasonable and practical for this Project. Particular emphasis will be placed on the selection, purchase, and delivery of specific equipment and material purchases to facilitate the construction schedule. The Consultant, as a condition of this scope of services, shall submit the necessary technical documentation to support the Project Manager and its other Consultants as required to facilitate the purchase of equipment and material.
2. DESIGN AND PLANS PREPARATION
The Consultant shall prepare documents of sufficient detail and completeness to allow for construction, permitting, and approval from governing authorities; and fully describe all work in order to obtain reliable cost proposal from Contractors. These plans are for the use of the Contractor to bid and construct the project; and for the County to ensure the project is built as designed and to specifications.
The Consultant shall provide the Design Criteria Package, for the County’s review and approval. The Consultant shall then provide construction documents at 60%, 90% and 100% design progress. All text shall be clear and legible on both the full-size and half-size plans. Full-size and half-size plans shall identify the scale of the drawing in both numerical and graphic formats. Each review submittal shall include documentation of the internal Quality Assurance and Quality Control review conducted by the Consultant. The Consultant shall complete designs required for all aspects of the project as specifically described herein.
Final bid Construction Documents shall be submitted in electronic format in accordance with the standards established by the County’s Procurement Division. Consultant shall provide a USB with the final Construction Drawings in the latest version of AutoCAD and PDF formats and the Technical Specifications provided in PDF and Microsoft Word formats.
2.1. Design Development. The Consultant shall complete all design analysis, studies, and investigations as required to complete the design of the project. This effort shall include, but not limited to, the following:
2.1.1. Design Analysis. The Consultant shall conduct a project site visit of the project limits, and field survey of unconcealed conditions, as required, to determine general existing conditions related to the scope of this project. The Consultant shall also review available “as-built” drawings and other documentation available
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46) to the County. Consultant shall determine the physical requirements and functional criteria to satisfy the project needs.
2.1.2. Color Selections (If Applicable). The Consultant shall prepare and submit at least two (2) color boards for presentation to the Project Manager for approval.
Each color board shall have samples of all proposed colors, textures and finishes.
2.1.3. Construction Plans. The Consultant shall prepare final construction plan sheets, notes and details to include, all sheets necessary to convey the intent and scope of the project for the purposes of construction. The plan sheets shall be assembled in a general order as follows, per project basis:
• Cover Sheet
• General Notes
• Standard Drawings and Details
• Summary of Pay (if applicable)
• Typical Sections (if applicable)
• Plan Sheets by discipline (Architectural, Electrical, Mechanical, Structural, etc.)
• Miscellaneous Details
• Utility Adjustment Plans (if applicable)
2.2. Progress Review Submittals. All submittals shall be accompanied by documentation of the Quality Assurance/Quality Control reviews in accordance with Section 1.7 herein. The Consultant shall submit Construction Drawings and Technical Specifications to the County for review at the 60%, 90% and final 100% completion stages. All County comments or questions on previous submittals, and any additional direction received from County must be addressed by the Consultant.
2.3. Technical Specifications. The Consultant shall provide a complete set of Technical
Specifications to be included in the bid documents for the project, in addition to an Index of Technical Specification, Index of Drawings and a list of all submittals. A Schedule of Prices shall be provided, if applicable. Technical Specifications shall be provided at the 60%, 90% and final 100% completion stages, in MS Word format and PDF format, which meets County requirements, as well as in any other electronic format required in accordance with the standards established by the County’s Procurement Division.
Where brand names or manufacturers names are used, at least three (3) shall be listed. Where three (3) names cannot be listed, use the phrase “or acceptable equal.” The Project may require the development of any Special Provisions that shall clearly identify the responsible entity for each permit condition in each regulatory permit, if applicable.
2.4. Construction Drawings. The Consultant shall provide complete set of Construction
Drawings to be included in the bid documents for the project. Bidding Construction Drawings shall be provided at the final 100% completion stage, in AutoCAD format and PDF format, which meets County requirements, as well as in any other electronic format required in accordance with the standards established by the County’s Procurement Division.
2.5. Construction Cost Estimate. The Consultant shall prepare and submit a detailed cost estimate for construction of the project at 60%, 90% and 100% construction document submittals. Required estimate format for Consultant shall be detailed by Construction Specifications Institute (CSI) index.
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
2.6. Bid Process. The Consultant shall provide services during the bidding process of the project as requested by the County as follows:
2.6.1. Pre-Bid Meeting. Attend a pre-bid meeting scheduled by the Project Manager and County’s Procurement Division. Prepare and submit meeting minutes, including a summary of the questions and responses after the pre-bid meeting.
2.6.2. Addenda. Answer questions from the prospective Bidders and prepare addenda as required to interpret, clarify or expand to the technical specifications or the construction drawings. The Consultant shall submit addenda to the Project Manager no later than three (3) days to allow reception of addenda by all bidders.
2.6.3. Bid Evaluation. Evaluate the Contractors bids received by the County by preparing bid tabulation for all bidders, reviewing bids for anomalies and notifying the Project Manager with any comments it may have concerning the bids, and making a recommendation for bid alternate/additive or deductive, as applicable.
Note: If no bids are within +/- 10 % of the Consultant’s estimate, or no bids are received at all, the Consultant will prepare a revised estimate, re-evaluate the construction plans, evaluate the bids and submit a report that summarizes this information. This report will include recommendations for revisions to the construction documents, if needed. The revised documents and the report shall be prepared at no cost to the County.
2.7. Deliverables. Work to be completed under this section by the Consultant shall require the following items to be delivered and accepted by the County:
2.7.1. 60%, 90%, and 100% Construction Plans (Hard copies and digital files).
2.7.2. 60%, 90%, and 100% Construction Technical Specifications (Hard copies and digital PDF and MS word files).
2.7.3. 60%, 90% and 100% Construction Cost Estimate.
2.7.4. Electronic Bid Package.
2.7.5. Schedule of Prices (Draft and Final) (if applicable).
2.7.6. Special Provisions (Draft and Final) (if applicable).
2.7.7. Color Boards (if applicable).
2.7.8. Pre-Bid Meeting Minutes.
2.7.9. Addenda Response Copies.
2.7.10. Bid Tabulation and Recommended Bid Alternates Summary.
2.7.11. Design Review Meeting Minutes.
2.8. Pay Tasks. Work to be completed under this section by the Consultant shall be paid for under the following Pay Tasks as listed on the Activity and Fee Summary:
2.8.1. 60%, 90%, and 100% Construction Documents.
2.8.2. 60%, 90% and 100% Construction Cost Estimates.
2.8.3. Schedule of Prices (If applicable).
2.8.4. Electronic Bid Document Package
2.8.5. Pre-Bid Meeting and meeting minutes
2.8.6. Addenda Responses
2.8.7. Bid Tabulation and Recommended Bid Alternates Summary
3. PERMITTING
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
The Consultant shall submit all applications and other submittals and provide services necessary to obtain all applicable permits that may be necessary for the construction of the proposed improvements.
The County will pay for all permit review fees required to process construction documents and obtain approval from Authority Having Jurisdiction (AHJ) over the project. The fee proposal shall include the estimated permit fees associated with permit reviews, as miscellaneous reimbursable expenses.
The construction plans package shall not be considered complete until all required permits applications approvals have been received by the County.
3.1. Agency Coordination. The Consultant shall notify the County’s Project Manager of all meetings with regulatory agencies to coordinate attendance by County staff. The Consultant is responsible for coordination with agencies early on to confirm the permitting process and the agency’s criteria.
Preliminary meetings with the Building Department, Fire Marshall, and other agencies as required, shall be conducted, prior to submitting document for permit approval for the purposed of incorporating code requirements in the most efficient manner possible. The Consultant shall submit meeting minutes and provide copies of all permit-related correspondence.
3.1.1. Agency Field Review. The Consultant shall conduct and coordinate field investigations as necessary with County’s Project Manager and with the appropriate regulatory agencies. The Consultant shall provide meeting minutes and field notes to the County’s Project Manager.
3.2. Permit Preparation. The Consultant shall prepare and submit all necessary permits.
The Consultant shall submit applications, construction drawings and specifications, and related support documentation to all Authorities Having Jurisdiction (AHJ) over the permitting or approval of the project. Copies of all permit application will be provided to the County for review and signature prior to submittal. It is anticipated that permit preparation shall include one or more Requests for Additional Information (RAI) from the permitting agencies.
3.3. Renewals and Extensions. The County will pay initial permit fees, the Consultant will be responsible for renewals, extensions and resubmittals of expired permits. The Consultant will be responsible for tracking, renewals and extensions of the permits.
Permit fees and extensions, as necessary, shall be paid for under Construction Administration. The Consultant is responsible for cost associated with permit lapse renewal prior to construction
3.4. Deliverables. Work to be completed under this section by the Consultant shall require the following items to be delivered and accepted by the County’s Project Manager (list permits as required):
3.4.1. Orange County Building Permit
3.4.2. Water Management District/ACOE Permit Package (if applicable)
3.4.3. Permit Application
3.4.4. Permit approved set and Final Permit
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
3.5. Pay Tasks. Work to be completed under this section by the Consultant shall be paid for under the following Pay Tasks as listed on the Activity and Fee Summary:
3.5.1. Agency Coordination
3.5.2. Agency Field Review
3.5.3. Permit Preparation
4. CONSTRUCTION ADMINISTRATION
The Consultant shall perform the following Construction Administration services:
4.1. Construction Meeting. Attend a Pre-Construction meeting and answer questions from the Contractors and Sub-contractors; and submit meeting minutes to the County’s Project Manager including a summary of the questions and responses during the pre-construction meeting.
4.2. Construction Progress Meetings. Attend construction progress meetings with the
County’s Project Manager and staff to discuss project progress and status, technical issues, and upcoming events and activities. The purpose of these meetings is to maintain clear communication between the County and the Project Team. The Consultant shall prepare and distribute meeting minutes following each of these meetings. Note: The number of progress meetings will be determined during contract negotiation.
4.3. Construction Observations. Conduct construction site visit observations concerning the installation of the work to observe the progress and quality of the work and to determine, in general, if the work is proceeding in accordance with the intent of the Contract Documents. Each construction observation shall include appropriate Sub consultants, and be documented in a Construction Observation Report that is forwarded to the County’s Project Manager and the Contractor within two (2) working days of the site visit. The Consultant shall route all job correspondence to the Contractor through the County’s Project Manager. Note: The number of site visits will be determined during contract negotiation.
4.4. Contactors Submittals including Shop Drawing reviews. Review and process all
Contractors submittals concerning product data, shop drawing samples and other submissions as required for general conformance with design concept of this Project and the Contract Documents in consultation with the County’s Project Manager. All Consultant‘s approved submittals shall bear the Consultants’ stamp. Contractor shall maintain at all times a Submittal log of all submittals sent to the Consultant. Status of the log shall be reviewed as a part of each Construction Progress Meeting.
4.5. Design Clarification Responses. Review and process all Request for Quotes (RFQ) and Requests for Information (RFI) by providing technical interpretation of the plans/drawings and specifications; evaluating requested deviation from the approved design or specification; reviewing and responding to RFIs. Consultant shall further prepare supplementary sketches as may be necessary for clarification of construction plans and assist in resolving actual field conditions encountered. Consultant shall answer RFIs within five business days unless otherwise directed based on the urgency and critical need for the project. Consultant shall maintain at all times a RFI log of all RFI’s submitted to the Consultant. Status of RFI log shall be reviewed as a part of each Project Progress Meeting.
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
4.6. Modification of Final Construction Plans. Update and modify the final Construction Plans as may be necessary to reflect changes in proposed improvements identified after submittal of the 100% plans. The Consultant shall provide signed and sealed copies of the updated final construction plans.
4.7. Contractor’s Application for Payment. Based on the site visit observations, as set forth above and on the evaluation of the Contractor's invoices requests, the Consultant shall determine an appropriate amount to be paid to the Contractor(s) for the current stage of project, and submit the invoice to the County’s Project Manager with recommendation for payment within five (5) business days of receipt in accordance with FS 218.735, Local Government Prompt Payment Act. Such certificate for payment shall constitute a representation of the Consultant to County that the quantity of the work has been performed in accordance with the Contract Documents. During Project Close-out, Consultant shall assist in negotiating the final payment for the project with justification upon which final settlement and termination of Contract can be based upon.
4.8. Contractor’s Field Order, Change Order Requests and Claims. Provide technical interpretation of the Contract Documents and evaluate requested deviation from the approved design drawings or specifications, and issue Field Orders as necessary.
Review all Contractors Change Order Requests and Claims, and recommend an appropriate cost and course of action within ten (10) calendar days. The Consultant shall maintain at all times a Change Order Request log of all requested change orders sent to the Consultant. Status of the log shall be reviewed as a part of each Construction Progress Meeting.
4.9. Final Close Out. Conduct site visits to the project as necessary to inspect the project in order to determine if the project was completed in general conformance of the construction contract documents. Consultant shall prepare record drawings by transcribing information provided by the Contractor. The Consultant shall revise original design drawings of the project and submit to the County within 30 working days of the final completion date a CD with the drawings in AutoCAD and PDF, and specification in MS-Word and PDF, (latest edition).
4.9.1. Substantial Completion and Final Completion. Attend the Substantial and
Final Completion Inspections. Arrange for all Sub consultants to attend and inspect their respective work. Assist the County’s Project Manager in verifying the completion of the construction contract and develop Substantial and Final Punch Lists. If appropriate, issue a certification of Substantial and Final Completion.
Additionally, Consultant shall provide the signed and sealed necessary partial clearances and certifications of completion to the appropriate regulatory agency.
4.9.2. Operation and Maintenance (O&M) Manual. Distribute to appropriate Sub consultants the Consultant’s operation and maintenance manuals for the facilities equipment and controls as required by the Contract Documents. Review the entire package for conformance with the Contract Document requirements and submit a consolidated package to the County’s Project Manager, (Package shall contain one draft review and one final review of O&M Manual).
4.9.3. Training. Coordinate and provide the necessary training to personnel for the respective project discipline.
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
4.9.4. Warranty Inspection. Attend the 10-month project walk-through warranty inspection. During the inspection, the Consultant shall assist the County’s Project Manager in identifying defective materials and installations by providing meeting minutes that include a written summary of findings that require the Consultants to take corrective action. Consultant shall also conduct a facility operations and performance meeting to test the equipment and receive feedback from County staff on the use of the equipment.
4.10. Deliverables. Work to be completed under this section by the Consultant shall require the following items to be delivered and accepted by the County:
4.10.1. Pre-Construction Meeting Minutes
4.10.2. Construction Progress Meeting Minutes
4.10.3. Construction Observation Visits and Reports
4.10.4. Contractor Submittals, RFIs and Pay Applications.
4.10.5. Substantial Completion and Final Completion Inspections and Punch Lists
4.10.6. Operation and Maintenance (O & M) Manual.
4.10.7. Final Close Out Record Drawings
4.10.8. Warranty Inspection Report.
4.11. Pay Tasks:
4.11.1. Pre-Construction Meeting and Meeting Minutes
4.11.2. Construction Progress Meeting and Meeting Minutes
4.11.3. Construction Observation Visits and Reports
4.11.4. Contractor Submittals, RFIs and Pay Applications.
4.11.5. Substantial Completion and Final Completion Inspections and Punch Lists
4.11.6. Operation and Maintenance (O & M) Manual.
4.11.7. Final Close Out
4.11.8. Coordination of Training.
4.11.9. Warranty Inspection Visit.
5. SUSTAINABILITY
As part of the County’s commitment to sustainability and high performing buildings, the Consultant shall:
5.1. Coordinate with the OCCC Sustainability Coordinator to identify opportunities for integrated design and construction with respect to best energy and environmental practices within the project scope of work. Recognize that the OCCC campus holds a variety of branding certifications which may be impacted by the project. These include LEED Gold 2009 O+M, ISO 14001, and APEX/ASTM Certifications.
5.2. Define expected utility performance outcomes for the building spaces.
5.3. Within the project scope of work, use LEED B+C and O+M to identify specific opportunities to achieve the following: (1) materials and resources, (2) indoor air quality,
(3) energy and atmosphere, (4) water efficiency, (5) sustainable sites, and (6) location and transportation performance credits which are economically feasible regarding project costs and long term operating expenses.
PART B: SCOPE OF SERVICES West Bldg. Roof Fans Replacement (0966-46)
TABLE OF DELIVERABLES
The Consultant shall produce and deliver to the Project Manager the deliverables outlined as follows:
CATEGORIES Copies Paper Copy (Size)
Digital File
Type
1.0 ADMINISTRATION
Design Project Schedule
1 MS
Word &
60%, 90% & 100% Construction Estimates and Construction Duration.
1 MS
Word &
2.0 DESIGN AND PLANS PREPARATION
60%, 90% & 100% Construction Plans.
1 Full Size 1 PDF
60%, 90% & 100% Construction Plans.
1 ½ size 1 PDF
60%, 90% & 100% Technical Specifications 2 8 ½ x 11 1 PDF 60%, 90% & 100% Cost Estimates
2 8 ½ x 11 1 PDF
3.0 PERMITTING
Permit Submittal (includes plans and specifications)
As required by Building Depart.
Permit Set, (Signed and Sealed), for OCCC records
1 Full size 1 PDF
Technical Specifications (Signed and Sealed), for OCCC records.
1 8 ½ x 11 1 PDF
4.0 BIDDING
Bid Construction Plans Submittal 1 Full size 1 PDF
Bid Construction Plans Submittal 1 ½ size 1 PDF
Bid Technical Specification Submittal 1 8 ½ x 11 1 PDF
Conformed Set of final Construction Documents 2 ½ size 1 PDF
5.0 CONSTRUCTION ADMINISTRATION
Meeting Minutes, Logs, Punch Lists, and Reports
1 PDF
As-Builts Drawings and Specifications. 1 PDF/
CAD
End of Exhibit A
PART B: SCOPE OF SERVICES