Concrete Slabs IDIQ Federal contract opportunity
Solicitation number
WV18RFQ021618
Issued by
Department of the Army West Virginia Army National Guard

About this file

additional questions

View the file

Other files for this federal contract opportunity

Other files attached to Concrete Slabs IDIQ, newest first.
File Type Posted
Questions_from_Vendors_Updated_13_March_2018.pdf PDF
Additional_Pictures.docx DOCX document
Questions_from_Vendors_Updated_28_March_2018.pdf PDF
image2_(002).jpeg JPEG file
image1_(002).jpeg JPEG file
SOLICITATION.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions from Vendors:

1. If delivery is done with a flat bed truck, do we unload the slabs, or does the vendor need to unload them.

Answer: We can, would prefer the vendor to unload

2. Can the slabs be stronger than 3000 psi, or do they have to be 3000 psi?

Answer: It can be higher, but no more than 4,000 psi

3. Do you have a schedule of when you would want deliveries for this year? Id school dates

Answer: It can be one shipment/ prefer two....initial (half) and balance in 6 months or upon notification

4. Do you want pricing per slab with delivery feel or a set amount per delivery?

Answer: We want all costs rolled into one, with delivery expenses included.

5. Would there be bi-weekly, quarterly, or just random shipments?

Answer: It can be one shipment/ prefer two....initial (half) and balance in 6 months or upon notification

6. The vendor is stating that the slab would be about a 1/2 less, does this matter, or does it have to be exactly 6 inches thick?

Answer: 1/2" is less is ok

7. Does the hook have to be a steel cable or can it be made out of rebar?

Answer: Steel cable is required

8. Is there a specification for the spacing between the rebar members fro the concrete slabs?

Answer: Yes, a square of rebar 6” from the border is all that is required

9. The specification calls for 6” from the outer edges, but I am not sure if the 6” spacing applies to internal member spacing as well, is there a minimum size steel cable handle desired?

Answer: 3/8” cable is suitable (as long as the cable is rated stronger than the concrete pad weight) The cable loop must be large enough for a fork of a fork truck to lift and use /move the block. Loop should anchor to concrete approximately 8” spacing in the center on a dege, 6” height of loop should be enough to allow the thickness of the fork to pass through the cable loop and pick up the slab.

10. The 8” wide and 6” high lifter to allow fork access is what is wanted to know. I have checked with all of the Precast suppliers and I cannot find a lifter that will meet this. Please know when I say I cannot find a lifter, that means a lifter that has certification. A custom lifter can be made up using cable but it more than likely will not have any certifications with it. If you have a specified lifter that you are wanting please let us know what it is.

Answer: This style is suitable:

TENSION CAPACITY

(4:1 SWL)

1,600 lbs Wire Diameter 1/4” Width 3-15/16” Height 8-1/4”