WV DNR HOLLY RIVER SP TECH SPECS.pdf
PDF 15 MB Posted
- Attached to
- Holly River State Park Water Main Construction
- Solicitation number
- CRFQ 0310 DNR2500000003 3
- Issued by
- Wayne County, West Virginia
About this file
This technical specifications document is prepared by the West Virginia Department of Natural Resources for water system improvements at Holley River State Park in Webster County, West Virginia. The project encompasses construction of approximately 616 linear feet of 6-inch ductile iron pipe (DIP) Class 52, 5,184 linear feet of 4-inch DIP Class 350, 7,720 linear feet of 4-inch polyvinyl chloride (PVC) C900 DR14, and 2,420 linear feet of 2-inch PVC Class 315 pipe, along with one new master meter, one new service connection, twenty-eight service reconnections, gate valves, miscellaneous surface restoration, and associated appurtenances. The specifications detail comprehensive technical requirements across all construction phases including site preparation, piping installation, testing, disinfection, and restoration work to be completed as a complete, in-place, fully operational installation.
The specifications establish detailed performance and material standards including compaction testing requirements (minimum one test per 1,000 linear feet of pipe), pressure testing at 100 psi above normal operating pressure with allowable leakage rates defined by pipe size and diameter, mandatory disinfection per ANSI/AWWA C-651 standards, and complete pipeline cleaning prior to service. Contractor responsibilities include maintaining existing water service to customers throughout construction, providing all erosion and sediment control measures in compliance with West Virginia Department of Environmental Protection standards, restoring all disturbed surfaces within one week or every 400 linear feet of pipe installation, and guaranteeing backfill settlement repairs for one year following completion. The contractor must provide performance and payment bonds, maintain comprehensive insurance coverage, obtain all necessary permits and easements, and submit detailed schedules, shop drawings, and operation and maintenance manuals prior to project closeout and final payment authorization.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEST VIRGINIA DEPARTMENT OF NATURAL RESOURCES
WEBSTER COUNTY, WEST VIRGINIA
WATER SYSTEM IMPROVEMENTS
HOLLEY RIVER STATE PARK
INDEX TO DETAIL SPECIFICATIONS
Section Title
Division 1 General Requirements
01010 ............Summary of Work 01050 .............Measurements and Payment 01200..............Project Meetings 01300..............Submittals 01520..............Existing Utilities 01560..............Temporary Environment Controls 01565..............Erosion and Siltation Control 01570..............Traffic Regulations and Control 01595..............Record Documents 01600..............Temporary Fencing and Site Security 01700 .............Project Closeout
Division 2 Sitework
02195 .............. Pre-Construction Audio/Video Recording 02200 .............Earthwork 02221 .............Trenching and Backfilling 02227 .............Special Fill Material 02229 .............Steel Casing Pipe 02506 .............Stone Surfacing Material 02580 .............Pavement Driveway and Sidewalk Restoration 02585 .............Property Utility Maintenance and Restoration 02600 .............Piping-General Provisions 02616 .............Ductile Iron Water Pipe 02618 .............Ductile Iron Fittings and Joint Restrainers 02623..............Polyvinyl Chloride (PVC) Water Pipe 02630..............Utility Line Marking Tape 02641 .............Valves and Valve Boxes 02645..............Miscellaneous Water Piping Materials 02650..............Asphalt Paving
02655..............Connections to Existing Water Main 02665 .............Horizontal Directional Drilling 02676 .............Disinfecting Pipelines 02677 .............Cleaning Pipelines 02678..............Pressure and Leakage Tests 02715 ……….Project Sign 02721..............Dumped Rock Gutter and Rip Rap 02931..............Seeding and Mulching
Division 3 Concrete
03301 .............. Cast-In-Place Concrete 03302 .............Precast Concrete
SECTION 01010-1
SECTION 01010
SUMMARY OF WORK
1.0 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The Contractor shall furnish all materials, incidentals, supplies, tools, equipment, labor and other services necessary to execute, complete, place into service and deliver the Project required by the Contract Documents, complete in every detail.
Holley River State Park – Water System Improvements
This project includes the construction of approximately 616 LF of 6” DIP CL 52, 5,184 LF of 4” DIP CL 350, 7720 LF of 4” PVC C900 DR14, and 2,420 LF of 2” PVC CL 315, one (1) new master meter, one (1) new service connections, twenty-eight (28) service reconnections, gate valves, miscellaneous surface restoration, and all other necessary appurtenances for a complete and in-place installation. It is anticipated that once the construction of the new water line is complete, the existing water storage tanks and existing water treatment plant will be decommissioned and removed from park property.
1.2 PARTIAL OWNER OCCUPANCY
Prior to substantial completion, the Owner, with the concurrence of the Contractor, may connect to and use completed or substantially completed portions of the work. This provision shall not be construed as relieving the Contractor of the sole responsibility for the care and protection of the work, or the restoration of any damaged work except as may be caused by agents or employees of the Owner. The Contractor on his own may not start connecting users as construction progresses without the written consent of the Engineer and Owner.
1.3 CONTRACTOR'S USE OF PREMISES
The Owner has clearly detailed the zone of construction for this project. The Contractor shall confine his equipment, the storage of materials and equipment and the operations of his workmen to this area. The Contractor shall provide, at his own expense and without liability to the Owner, access to the work site if other than along the line of construction and any additional land and access thereto that the Contractor may desire for temporary construction facilities, or the storage of materials. The Contractor shall obtain at his own expense and provide to the Owner signed agreements with each property owner where such additional easements are secured.
SECTION 01010-2
If the Contractor after commencement of the project deems it necessary to secure additional rights-of-ways or easements for his convenience; the Contractor shall furnish the Owner copies of all such agreements.
1.4 PUBLIC CONVENIENCE
The Contractor shall at all times conduct his work so as to insure the least possible obstruction to traffic and inconvenience to the general public and the residents of the area, and to insure the protection of persons and property.
The Contractor shall be responsible to maintain all barricades, flagmen, warning devices and other measures as may be necessary to comply with the Department of Transportation's standards and to insure proper traffic control through the work area.
The Contractor shall schedule and layout his work in such a manner that traffic flow through an area is not totally disrupted. In the event it is necessary to shut off traffic flow to an area, the Contractor shall establish an emergency evacuation plan and provide 24 hours notice to the residents. This plan must be approved by local fire, police and ambulance authorities prior to implementation.
1.5 RESTORATION AND CLEAN-UP
The Contractor shall remove all excess materials, shipping and packing materials scrap trash, garbage, etc. on a daily basis. This shall include all grading, plantings, and temporary sidewalk, driveway and road restoration. Failure to comply with these requirements will result in the stopping of all pipe laying activities until work is caught up. The Owner reserves the right to withhold all payments until these requirements are met.
2.0 MAINTENANCE AND OPERATION OF EXISTING SYSTEM
A. All existing water lines, as well as pumping stations, that are to be renovated, upgraded or replaced must remain fully operational throughout the project.
B. The Owner must operate and maintain the existing facility. The Contractor must provide full access to all areas of construction at all times. Existing Customers of the Owner shall have service maintained without interruption throughout the duration of this project.
END OF DOCUMENT
SECTION 01050-1
SECTION 01050
MEASUREMENT AND PAYMENT
1.0 GENERAL
1.1 DESCRIPTION
This item describes the methods for measurement and payment of project-related work called for in the Form of Proposal.
2.0 UNIT PRICE BID ITEMS
Unit price bid items are defined as items of work that are listed in units of Linear Foot, Each, Square Yard, or other items of similar definition.
2.1 MEASUREMENT
Measurement for the items defined will made as a complete unit per unit price basis for each item of work defined in the Form of Proposal and shall include all materials, labor, and equipment necessary, including all other items considered incidental to construction, for a completed in place and fully functioning item, in accordance to these Contract Documents.
2.2 PAYMENT
Payment for work performed under these items shall be under the individual unit price bid items shown of the Form of Proposal, which price and payment shall be full compensation herein described in a workmanlike manner, including all, but not limited to, labor, tools, bonds, equipment, supplies, and incidentals necessary to complete the work.
3.0 LUMP SUM BID ITEMS
Lump sum bid items are defined as items of work that are listed as Lump Sum only and are to be defined as items that are to be paid the specified amount for a complete in place and functioning item.
3.1 MEASUREMENT
Measurement for the items defined will be as a complete unit on a lump sum basis for each item of work and shall include all excavation, setting, materials, labor, tools, sheeting, shoring, bailing, and other incidentals or items of work described on the plans or as detailed in the specifications, which will be necessary for a complete and working item, in accordance with these Contract Documents.
SECTION 01050-2
3.2 PAYMENT
Payment for work performed under these items shall be under the lump sum items shown of the Form of Proposal, which price and payment shall be full compensation herein described in a workmanlike manner, including all, but limited to, labor, tools, bonds, equipment, supplies, and incidentals necessary to complete the work.
4.0 GENERAL ITEMS OF WORK
4.1 DESCRIPTION
Following is a description of work included under each item in the Form of Proposal.
See appropriate sections of the Detail Specifications for actual material and installation of the items bid.
PVC or DIP Water Lines (per LF):
Payment will be made at the contract unit price per linear foot for the size, type and class pipe to be installed, complete in place. The Contractor shall be solely responsible for the means, methods, techniques, sequences and procedures necessary for the construction of the pipeline(s).
The installation of each separate pipe item shall include, if applicable, per linear foot unit price, the installation of the following; trenching, bedding material/backfill material, compaction, cleaning/pigging, pressure testing, disinfection, bacteriologic sampling, and any other operation necessary for a finished installation, complete and in-place.
Materials and the installation of which is to be included in the unit price are, but not limited to, as follows: water pipe, fittings, restraints, anchors, rodding, friction clamps, joint restraint gaskets, fasteners, polyethylene encasement, tracer wire, marking tape, and any other incidental to be included for a complete and in-place installation
No separate payment will be made for rock excavation, aggregate bedding and backfill, for seeding and mulching, or shoulder stone.
This pay item includes the removal, hauling and legal disposal of all excavated material.
Compaction testing on WVDOH right-of-way shall be the responsibility of the
CONTRACTOR.
No separate payment for maintaining water service to existing customers.
Since the timely and proper cleanup and restoration of property is considered a part of the unit price for each bid item, the Engineer may withhold up to 25 percent of the unit
SECTION 01050-3
price if the Contractor does not perform cleanup and restoration in a timely and proper manner.
The above description is applicable to all pipe items that will be paid on a linear foot basis.
Stream/Creek Crossing/Restrained Joint Water Line (per LF):
Various sizes of stream or creek crossing water lines installed across or along creeks and waterways complete in place. This bid item includes but not limited to all excavation, backfilling, bedding, and all fittings, restraints, and thrust blocking. Installation by horizontal directional drilling is also included in this item, if as shown on the Drawings.
Contractor must install these lines under provisions granted in accordance with all permits or licenses obtained, and with the Contract Documents.
Water Service Line (per LF):
Water service lines installed complete in place. This bid item includes but not limited to all excavation, backfilling, bedding, all necessary fittings, and all surface restorations including gravel road surfacing, seeding and mulching and landscaping. Contractor shall restore the surface of the excavation to its former or better condition including but not limited to all existing fences, driveways, sidewalks etc.
Water Service Line Road Crossing (per LF):
Water service lines installed complete in place, bored or punch underneath of existing roadways, includes all of the above discussed items in addition to the equipment and material necessary to perform the roadway crossing.
Steel Casing, Bore & Jack (per LF):
Steel casings of various diameters, installed by the bore and jacked method, complete in place as detailed in the Construction Drawings, and as specified elsewhere in the specifications. This unit bid price shall include the price for the carrier pipe, spacers and end seals and all other incidentals necessary for the item.
Steel Casing, Open Cut (per LF):
Steel casings of various diameters, installed by the open trenching method, complete in place as detailed in the Construction Drawings, and as specified elsewhere in the specifications. This unit bid price shall include the price for the carrier pipe, spacers and end seals and all other incidentals necessary for the item and described in these Contract Documents.
SECTION 01050-4
Gate Valves (per EA):
Install gate valves on new water lines, where shown. This unit bid price shall include all necessary fittings, restrainers and thrust blocking as detailed on the Drawings, valve boxes, valve markers, and all surface restorations including paved or gravel road surfacing, seeding and mulching and landscaping. Contractor shall restore the surface of the excavation to its former or better condition including but not limited to all existing fences, driveways, sidewalks etc. Gate valves shown on Connection Details will be paid for under this item; however, gate valves associated with tapping sleeves will be paid for under the appropriate Connection Detail item.
New Service Connections (per EA):
Unit price bid for this item shall include installing the new service line from the saddle on the main (to be included in this item) and to the proposed meter location. The new meter setting as detailed in the Drawings will be installed and left with 5 lf of service line on the customer side of the meter. Locations of proposed waterline may vary from the actual situation in the field. Unit price bid for this item shall also include installing up to 10 lf of new service line on the Owner side of the meter. Contractor shall restore the surface of the excavation to its former or better condition including but not limited to all existing fences, driveways, sidewalks etc.
Hydrant Assembly with valve (per EA):
Unit price bid for this item shall include the installation of a Fire Hydrant, shut off valve, up to 5 lf of 6” PVC or DIP waterline and all other fittings, thrust blocks and restrainers necessary to connect the assembly to the main waterline. Contractor shall restore the surface of the excavation to its former or better condition including but not limited to all existing fences, driveways, sidewalks etc.
Air/Vacuum Relief Valves (per EA):
This bid item includes the cost of installing an Air/Vacuum Relief Valves inside of a pre-cast concrete vault with frame and cover as detailed on the Drawings. The unit price shall include all costs of excavation, backfilling, installation of the valve complete and in place, including all surface restoration to its former or better condition. This includes but is not limited to all existing fences, driveways, sidewalks etc.
Connection Details (LS):
This bid item is for connecting newly installed waterlines to existing waterlines that are to be left in service. The lump sum bid for this item shall include cutting the existing waterline and connecting the new waterline to it including all necessary fittings, restrainers, and thrust blocking. This connection may also be a hot tap. Contractor shall restore the surface of the excavation to its former or better condition including but not
SECTION 01050-5
limited to all existing fences, driveways, sidewalks etc. Each connection to existing lines will be detailed on the Drawings. Gate valves as shown in the Connection Details shall be paid for separately under that pay item.
Pressure Reducing Valve (LS):
The lump sum bid for this item shall include all materials as detailed on the Drawings, including all necessary fittings, restrainers, and thrust blocking and any other miscellaneous materials for a complete in-place installation. Contractor shall restore the surface of the excavation to its former or better condition including but not limited to all existing fences, driveways, sidewalks etc.
Concrete Drive Restoration (per LF):
Unit price bid for this item shall include installing concrete driveway or sidewalk at designated areas as shown in the drawings and as specified in the specifications. The unit price bid shall include all costs of all excavation (including but not limited to the existing sidewalk), expansion joints, gravel bedding, backfilling, steel reinforcing, forming and curing the sidewalk and connecting the same to the existing curbs and sidewalks.
Gravel Drive Restoration (per LF):
Unit price bid for this item shall include installing gravel driveway at designated areas as shown in the drawings and as specified in the specifications. The unit price bid shall include all costs of all excavation, surface preparation, backfilling, and any and all incidentals in order to match the elevations of the existing driveway.
Type ‘A’ Trench Repair (per LF):
Unit price bid for this item shall include labor, equipment and materials for the installation of Type ‘A’ Trench Repair as detailed in the Construction Drawings and in accordance with WV DOH Standards and Specifications, including all saw cutting of existing surfaces, asphalt and matching the grade of the existing adjacent pavement.
This Bid Item will be paid per Linear Foot, and the width necessary to restore all disturbed surfaces.
Type ‘B’ Trench Repair (per LF):
Unit price bid for this item shall include labor, equipment and materials for the installation of Type ‘B’ Trench Repair as detailed in the Construction Drawings and in accordance with WV DOH Standards and Specifications, including all saw cutting of existing surfaces, asphalt and matching the grade of the existing adjacent pavement.
This Bid Item will be paid per Linear Foot, and the width necessary to restore all disturbed surfaces.
SECTION 01050-6
Type ‘C’ Trench Repair (per LF):
Unit price bid for this item shall include labor, equipment and materials for the installation of Type ‘C’ Trench Repair as detailed in the Construction Drawings and in accordance with WV DOH Standards and Specifications. This Bid Item will be paid per Linear Foot, and the width necessary to restore all disturbed surfaces.
Pre-Construction Audio/Video Recording (per LS):
Lump sum price bid for this item shall include three (3) complete sets of the Pre- Construction Recording as detailed in Section 02195. The recording must be accepted and approved by the Owner/Engineer prior to any construction initiating.
Mobilization (per LS):
Lump sum price bid for this item shall be limited to no more than 3% of the total Base Bid Amount. If this amount exceeds 3% of that amount, the Bid shall be considered unresponsive. This lump sum amount may be paid on the first pay request and will cover the Bidder’s cost for mobilization/demobilization of materials and equipment to the project site, bonds, insurance, project sign, etc.
5.0 GENERAL ITEMS OF WORK
5.1 DESCRIPTION
All other items of work (such as, but not limited to attending project meetings, preparing submittals, Temporary Environmental Controls, Erosion and Siltation Controls, field office, record documents, temporary fencing and site utility, project closeout, video taping, utility marking tapes, testing of sewer systems, and project sign), which are not specifically mentioned in the above Lump Sum and Unit price bid items, but are necessary for a complete and operating system, are considered Incidentals and will not be measured or paid separately. The cost of all such items shall be included in the various items of work defined in the Form of Proposal. Failure to do so will not be cause for extra payment or compensation.
END OF SECTION
SECTION 01200 - 1
SECTION 01200
PROJECT MEETINGS
1.0 DESCRIPTION
A. Work included under this section includes attending the contract signing, pre-construction conference and progress meetings.
2.0 APPLICATION
A. Contract Signing
Within ten (10) days after the issuance of the Notice of Award, the Contractor shall be required to appear at the office of the Engineer or the Owner so that he may sign the contract.
The Contractor shall be represented at the meeting by two top ranking officers of the company; if a corporation, the president and secretary; if a partnership, both partners.
The Contractor shall bring the following items:
1. Six (6) copies of the performance bond.
2. Six (6) copies of the payment bond.
3. Six (6) copies of the insurance documents, including the power of attorney.
4. Six (6) copies of the Workers' Compensation certificate.
5. The corporate seal.
B. Pre-Construction Conference
As soon as possible after the contract signing, the pre-construction conference will be held at the office of the Engineer or the Owner.
The Contractor shall be represented at the conference by one top ranking officer of the company and the project superintendent.
The agenda for the conference will generally include the discussion of the following topics:
1. Responsibilities of Consulting Engineer
2. Responsibilities of Owner
3. Responsibilities of Contractor
SECTION 01200 - 2
4. Responsibilities of Funding Agency
5. Coordination of utility relocation work
6. Procedures of processing periodic estimates
7. Discussion of Contractor's schedule
8. Review of subcontractors
9. Procedures for change orders
10. Safety of project
11. Labor and equal employment requirements
12. Project inspection
13. Rights-of-way and easements
14. Project sign
15. Coordination between contractors
16. General contract requirements
17. Project closeout and final acceptance
C. Progress Meetings
Progress meetings shall be held on a monthly basis corresponding to the submittal of the periodic estimate.
The meeting shall be held at or near the project site.
The Contractor shall be represented by the project superintendent at all meetings and by a ranking officer, if so requested by the Owner.
The Contractor further agrees to attend any and all meetings outside the scope described above if they are deemed necessary by the Owner or Engineer in insure the timely and successful completion of the project.
SECTION 01300 - 1
SECTION 01300
SUBMITTALS
1.0 SCOPE
A. This Section covers items and information to be submitted to the Owner for approval throughout the project duration.
B. Work Included:
1. Scope
2. Sequence of Construction
3. Schedule of Quantities and Costs
4. Schedule of Payments
5. Construction Progress Schedule
6. Product Data
7. Shop Drawings and Samples
8. Subcontractors
9. Payrolls
10. Daily Log
11. Test Results
12. Operation and Maintenance Manuals
13. Record Documents
C. Work Specified Elsewhere:
1. Refer to General Conditions for additional coverage of these submittals.
2. Refer to 01595 - Record Documents.
2.0 SCHEDULE OF QUANTITIES AND COSTS
A. Submit to the Owner such schedule of quantities and costs as may be determined by the Owner to be necessary and in sufficient detail to establish the value of work completed for partial payments
B. Such schedule shall be submitted prior to the start of any work.
C. The Contractor shall submit ten (10) copies to the Engineer’s office ten working days prior to the District’s monthly meeting. The Contractor must review the estimate with the Field representative and secure his signature prior to submission to the Engineer’s office. It is the Contractor’s responsibility to coordinate, copy, secure signatures, and deliver to the Engineer the appropriate number of copies.
The Owner will act upon the payment request at his normal monthly meeting and issue payment within thirty days after his approval.
SECTION 01300 - 2
3.0 SCHEDULE OF PAYMENTS
A. Submit a schedule of payments anticipated to be earned during the course of the work.
B. Such schedule shall be submitted prior to the start of any work.
C. Substantial deviation from the original schedule may result in a delay of payment.
D. Contractor must submit a revised and updated schedule of payments throughout the duration of the project detailing the progress of payment draw downs, but this does not relieve him of the requirements of paragraph C above.
4.0 CONSTRUCTION PROGRESS SCHEDULE
A. Submit a construction progress schedule showing the order in which the work will be performed and completed, including dates at which time various parts of the work will commence and be completed.
B. Such schedule shall be submitted fourteen (14) days after the notice to proceed is given, and shall be updated monthly showing actual progress against the initial schedule.
5.0 PRODUCT DATA
A. Furnish product data for all materials which are proposed to be incorporated.
B. Data to include installation instructions when applicable.
6.0 SHOP DRAWINGS AND SAMPLES
A. Provide six (6) sets each of shop drawings and samples as may be necessary for the prosecution of the work and Owner's selection of materials.
B. Shop drawings and samples shall bear the Contractor's certification that he has reviewed, checked and approved the submittal, and that they are in conformance with the requirements of the Contract Documents.
C. No materials and/or equipment are to be ordered until the shop drawings are approved by the Engineer and/or Owner.
D. The shop drawing submittals shall be made in a three-ring binder with an index of the contents and numbered tabs identifying each item by specification section and bid item in the submittal. The Contractor shall consolidate his submittals to minimize the number of binders. The binders shall be black with a clear pocket on
SECTION 01300 - 3
the front. A title page shall be inserted into this cover. The page shall list the project, type of equipment/material, contractor, date and submittal number.
Major equipment items may require separate binders and submitted separate from other items. The Contractor is to consolidate the submittals into divisions of work into one binder such as Architectural, Mechanical, Electrical, etc. All binders shall be the same color and style.
E. No shop drawings will be reviewed unless all components are included in the submittal.
7.0 SUBCONTRACTORS
Submit the name, qualifications and type of work to be performed by each subcontractor prior to beginning any work. The Contractor will not be paid for work performed by a subcontractor whose name and qualifications have not been submitted and approved by the Owner prior to work beginning. Nothing in these documents shall be interpreted to imply that there is an agreement between any subcontractors secured by the Contractor and the Owner. Any and all claims made by the subcontractor for extra costs, work, or materials will be dealt with exclusively by the Contractor. The Contractor shall indemnify and hold harmless the Owner for any such claims and provide an insurance policy to that effect.
8.0 PAYROLLS
A. Submit weekly a copy of all payrolls to Owner.
B. The payroll record shall be accompanied by a signed statement indicating that the payrolls are correct and complete, that the wage rates are not less than those required, and that the classifications conform to the work performed.
9.0 DAILY LOG
A. The Contractor shall keep in a bound book a daily log of men and equipment on the job, work performed, work conditions encountered, and any problems encountered. All entries shall be kept in ink.
B. Submit copies of daily logs no less than weekly.
10.0 TEST RESULTS
Submit the results of all tests required by these Contract Documents or as may be necessary to determine the suitability of the work performed or materials used.
11.0 OPERATION AND MAINTENANCE MANUALS
SECTION 01300 - 4
A. Submit operation and maintenance manuals for all equipment prior to the 50% project completion point. Failure of the Contractor to submit the O & M manuals, as stated herein, will result in the withholding of all payments to the Contractor by the Owner.
B. Manual shall include, when applicable, operation and maintenance instruction, listing of parts and recommended spare parts inventory, wiring diagram, model number, type, size, serial or identification number of each piece, and figures and narrative which describe the equipment and its function.
C. Failure to supply these manuals by the specified project completion point will result in an immediate suspension of payments.
12.0 RECORD DOCUMENTS
A. Maintain throughout the duration of the work, a complete record of the work and submit these documents based upon the following schedule:
For unit price contracts:
1. Monthly with payment requests.
B. Submittal shall have transmittal letter, in duplicate, containing date, project title and number, Contractor's name and address, title and number of each record document, certification that each document as submitted is complete and accurate, and signature of the Contractor or his authorized representative.
C. Failure to comply with these requirements will result in the immediate increase in the retained amount held on progress payments.
SECTION 01520 - 1
SECTION 01520
EXISTING UTILITIES
1.0 GENERAL
1.1 UNDERGROUND UTILITIES
A. Utilities and other existing underground structures indicated on plans are shown for the purpose of indicating the existence of such utilities or structures, and no guarantee is given of their exact location or the completeness of the information shown.
UTILITIES ENCOUNTERED - Call West Virginia 811 by dialing 811 or 1-800-245-4848 at least 48 hours prior to commencing any construction activities or stakeouts. The Contractor shall provide all affected utilities a schedule of his activities specifically noting where he will be in close proximity to their facilities.
B. The Contractor shall protect and preserve all under-ground utility service lines, wastewater disposal systems and drains along the route of construction. The Contractor shall promptly repair or replace any damaged facilities.
C. The Contractor shall thoroughly review the Plans to become aware of the involvement with utilities. Existing service is not to be interrupted unless so noted on the Plans. If differing conditions exist and prevent the Contractor from completing the work as proposed, a change in scope will be negotiated provided the Contractor has, prior to undertaking the work on a section of line, clearly and accurately located all existing utilities to determine the work cannot be constructed as designed. Failure to do so will relieve the Owner of the responsibility for payment of the section laid prior to the problem area. A change in scope will be negotiated accordingly.
D. The Contractor may not vary from the approved Plan to avoid working adjacent to utilities for his convenience without prior written approval of the Engineer.
The Contractor shall bear any and all costs associated with such changes, including but not limited to, engineering fees, rights-of-ways, etc.
SECTION 01560 - 1
SECTION 01560
TEMPORARY ENVIRONMENTAL CONTROLS
1.0 GENERAL
1.1 DESCRIPTION
A. This Section covers temporary environmental controls during the life of this contract.
2.0 APPLICATION
A. General
1. In order to prevent and to provide for abatement and control of any environmental pollution arising from their construction activities, the Contractor shall comply with all applicable federal, state and local laws and regulations concerning environmental pollution control and abatements, as well as all specific requirements stated elsewhere in the contract specifications.
2. The Owner will notify the Contractor in writing of a non-compliance with the foregoing provisions and the action required, and upon notice, the Contractor shall immediately take corrective action. Such notice, when delivered to the Contractor or his authorized representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Owner may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor unless it was later determined that the Contractor was in compliance.
3. The Contractor shall obliterate all signs of temporary construction facilities such as work areas, structures, foundations or temporary structures, stockpiles of excess or waste materials, or any other vestiges of construction as directed. Restoration to original contours is required unless specific variances are granted by the affected property owner in writing. In addition, all spoil above grade around the crown of trees and shrubs shall be removed. The disturbed areas shall be graded and filled as required and seeded as specified herein.
4. During the life of this contract, the Contractor shall maintain all facilities constructed for pollution control under this contract as long as the operations creating the particular pollutants are being carried out or until
SECTION 01560 - 2
the material concerned has become stabilized to the extent that pollution is no longer being created. During the Construction period, the Contractor should conduct frequent training courses for his maintenance personnel.
The curricula should include methods of detection of pollution, familiarity with pollution standards, and installation and care of vegetation covers, plants and other facilities to prevent and correct environmental pollution.
B. Land Resources Protection
1. It is intended that the land resources within the project boundaries and outside the limits of the permanent work performed under this contract be preserved in their present condition after completion of construction that will appear to be natural and not detract from the appearance of the project. The Contractor shall confine his construction activities to areas defined by the Plans and/or Specifications unless he has obtained variances in writing from the affected property owners.
C. Noise Control
1. Contractor shall comply with all federal, state or local laws and regulations concerning noise control.
2. The Contractor shall be required to execute the work under this contract between the hours of 7:00 A.M. and 7:00 P.M., L.P.T., unless written permission for night work is obtained from the Owner.
D. Dust Control
1. The Contractor will be required to maintain all work sites, excavations, embankments, stock-piles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which would cause a hazard or nuisance to others. Approved temporary methods of stabilization consisting of sprinkling, chemical treatment, light bituminous treatment or similar methods will be permitted to control dust.
2. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor shall have sufficient competent equipment on the job to accomplish this.
Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.
3. Calcium chloride, ASTM D98, shall be the only approved chemical treatment.
SECTION 01560 - 3
E. Debris Control
1. The Contractor shall keep all work areas involved in the project free from all trash and debris, including excess or unusable materials.
2. All areas shall be cleaned up and made orderly on a weekly basis. However, should the project representative determine that the health or safety of the public is threatened due to an unkempt work area, he may order the project or part of the project shut down as per Paragraph A-2 of this section until such time as the area in question is cleaned up.
F. Water Pollution Control
1. The Contractor shall not pollute any rivers or streams with fuels, oils, bitumens, calcium chloride, acids or harmful materials. It is the responsibility of the Contractor to investigate and comply with all applicable federal, state, county and municipal laws concerning pollution of rivers and streams. All work under this contract shall be performed in such a manner that objectionable conditions will not be created.
2. At all times of the year, special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, waste washings, herbicides and cement drainage from entering public waters.
3. Disposal of any materials, wastes, effluents, trash, garbage, oil, grease, chemicals, etc., in areas adjacent to streams will not be allowed. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the condition of the adjacent undisturbed area. If necessary, contaminated ground shall be excavated;
disposed of as directed; and replaced with suitable fill material, compacted and finished with topsoil all at the expense of the Contractor.
4. The Contractor shall at all times perform all work and take such steps required to minimize the severity and duration of any interferences or disturbances to fish and wildlife. The Contractor will not be permitted to disturb native habitat adjacent to the project area, which, in the opinion of the Owner, are critical to fish, and wildlife.
Fouling or polluting of water will not be permitted. Wash waters and wastes shall be processed, filtered, ponded, or otherwise treated prior to their release into the streams.
G. Erosion Control
Reference Section 01565 for Erosion and Siltation Control.
SECTION 01560 - 4
H. Burning the Materials
1. Burning of any excess materials or debris will not be permitted unless written permission is obtained from the Owner and the office of the State Fire Marshal and Office of Air Quality Control.
I. Air Pollution
1. The Contractor shall exercise every reasonable precaution throughout the life of the project to keep air pollution to a minimum. The Contractor shall also comply with the applicable regulations of the West Virginia Air Pollution Control Commission. During times of limited dispersion, construction operations may be suspended.
2. Time lost due to a suspension of work under this item shall be added on to the contract completion time.
J. Protection of Archaeological and Historical Findings
1. Should the Contractor's excavation operations encounter remains of prehistoric people's dwelling sites or artifacts of historical or archaeological significance, the operation in that locality shall be temporarily discontinued.
The Engineer will contact appropriate authorities to determine the disposition thereof.
2. When directed by the Engineer, the Contractor shall excavate the site in such a manner as to preserve the artifacts encountered and shall remove them for delivery to the custody of the proper state authorities. Such excavation will be considered as an extra amount of work, and shall be paid for with a Change Order.
3. The time lost due to a temporary work stoppage shall be added on to the contract completion time.
SECTION 01565 - 1
SECTION 01565
EROSION AND SILTATION CONTROL
1.0 GENERAL
1.1 DESCRIPTION
A. The Owner has obtained registration under their WV NPDES General Permit prior to construction, if applicable to this project. All work described in the Contract Documents shall be performed in accordance to the “Erosion and Sediment Control Best Management Practice Manual,” the latest revision, as published by the West Virginia Department of Environmental Protection.
B. The Contractor shall be responsible for implementation and maintenance of all Best Management Practices (BMP) necessary to protect against the transfer of water borne sediment. Any violation or fines associated in the performance of this work shall be the sole responsibility of the Contractor.
C. The Contractor shall review the following: Section 02221 “Trench Excavation and Backfill”, Section 02721 “Dump Rock Gutter and Rip Rap”, and Section 02931 “Seeding and Mulching”, closely with this section.
D. In general, the work to be done includes measures necessary to provide erosion and sediment control within the construction area to the acceptance of the WV Division of Natural Resources, WV Department of Environmental Protection, Division of Water and Waste Management, and the U.S. Army Corps of Engineers. The Contractor is responsible for the implementation of the erosion and sediment control plan, as initially set forth. Erosion and Sediment Control Standard Details have been provided in this specification.
E. A meeting shall be arranged by the Engineer between the Contractor and the Department of Environmental Protection prior to construction to assure a proper and smooth implementation of the Erosion and Sediment Control Plan and compliance with the Owner’s General Permit registration, if applicable.
F. Related Work:
1. Trench, Excavation and Backfill Section 02221
2. Dump Rock Gutter and Rip Rap Section 02721
3. Seeding and Mulching Section 02931
SECTION 01565 - 2
2.0 DEVICES
A. The following list of devices available to be utilized by the Contractor is not all inclusive, nor is it intended to be. Other devices as described in the WV DEP BMP Manual may be utilized if they are more applicable to the specific site.
2.1 SILT FENCES
A. Definition
1. A temporary barrier with a life expectancy of six months or less, installed below small disturbed areas or at the toe of a slope or as shown on the plans.
B. Purpose
1. The purpose of a silt fence is to intercept and detain sediment from small unprotected areas.
C. Conditions Where Practice Applies
1. A regular silt fence may be used where:
a. No other practice is feasible or economical.
b. There is no concentration of water in a channel or other drainage-way above the barrier.
c. Erosion will occur in the form of sheet and rill erosion.
d. Protection of a property line or limits of grading is required.
e. 100 feet of silt fence will collect the runoff from an area of ¼ acre or less, and the maximum gradient is 2:1 or less.
2. A super silt fence may be used where:
a. Sensitive areas (wetlands, woods, streams, etc.) are adjacent to the project location.
b. Structures, such as residential homes or commercial buildings, are down slope and in close proximity to the disturbed areas.
c. The project location is prone to heavy winds and drifting snow.
d. The disturbance is anticipated on lasting for a long duration, over one year.
SECTION 01565 - 3
e. Sediment traps cannot be built due to land availability.
f. Indicated by the Engineer or regulatory agency.
D. Materials
1. Regular Silt Fence
a. Silt Fence Cloth: Filter X, Poly-filter X, Mirafi 100X, Laurel Erosion Control Cloth, Bidim, or approved equal, which is resistant to the sun’s rays.
b. Fence Posts: The length shall be a minimum of 48” long. Wood posts will be of sound quality hardwood with a minimum diameter of 2-inches, or as approved. Steel posts will be standard T or U section weighing not less than 1.33 pounds per linear foot.
3. Super Silt Fence
a. The chain link fence fabric shall be 42 inches and the pole length shall be 72 inches.
b. The poles do not need to be set in concrete.
c. The chain link fence fabric and the first layer of filter fabric shall be imbedded in the ground a minimum of 8 inches.
d. Silt Fence Cloth: Filter X, Poly-filter X, Mirafi 100X, Laurel Erosion Control Cloth, Bidim, or approved equal, which is resistant to the sun’s rays.
e. The filter fabric shall be secure to the chain link fence fabric with ties spaced at 24 inches centers along the top and mid section.
f. Once sedimentation has reached half of the Super Silt Fence height, all accumulated sediment shall be removed and disposed of as directed by the Engineer.
E. Construction Specifications
1. The fence posts shall be spaced a maximum distance of 10 feet center to center.
2. The filter cloth shall be embedded in the soil a minimum of 4 inches, and have compact soil to hold it in place.
SECTION 01565 - 4
3. The inspection shall be in accordance with Paragraph 3.4 of this Section or more frequently as required, and the filter cloth shall be replaced promptly as needed if it is torn or damaged. Sediment shall also be removed to insure capacity when sediment reaches one-half of height of barrier.
4. See Erosion and Sediment Control detail sheets.
2.2 TEMPORARY DITCH STONE CHECK DAMS
A. Definition
1. A “temporary” barrier with a life expectancy of the project, installed across a ditch or swale.
B. Purpose
1. The purpose of a temporary ditch stone check dam is to detain small amounts of sediment and to slow the water flow to prevent erosion before vegetation or grass has taken root.
C. Construction Specifications.
1. The ditch stone check dams shall consist of rock, fieldstone, or quarry stone 3” to 6” size.
2. The ditch stone check dams shall be 6” minimum and 2’ maximum in depth and 4’0” minimum in length, dumped into bottom of ditch line.
3. An inspection shall be in accordance with Paragraph 3.4 of this Section and sediment should also be removed to insure capacity when sediment reaches one-half height of barrier.
4. The ditch stone check dams will be spaced as follows:
(Calculate by formula) L = Length in feet S = Rise over run – multiply by 100 L = 160/S (maximum 150’)
5. The ditch stone check dams shall not be removed completely but shall be used in the construction of rock-lined ditch. The rock shall supplement the rock required to install the rock-lined ditch.
6. See Construction Drawings for detail sheets.
SECTION 01565 - 5
2.3 TEMPORARY SEDIMENT TRAPS
A. Definition
1. A temporary basin formed by excavation and/or embankment to intercept sediment-laden runoff to trap or retain sediment prior to re-entering the waterway.
B. Purpose
1. To intercept sediment runoff and trap the sediment in order to protect drainage ways, properties and rights-of-ways from sedimentation.
C. Construction Specifications.
1. Size of temporary sedimentation basin must be by calculation and submittal by the Owner to the Department of Environmental Protection.
2. Area under embankment shall be cleared, grubbed, and stripped of any vegetation and root mat. The pool area shall be cleared.
3. The fill material for the embankment shall be free of roots or other woody vegetation as well as oversized stones, rocks, organic material or other objectionable material. The embankment shall be compacted by traversing with equipment while it is being constructed.
4. Sediment shall be removed and trap restored to its original dimensions when the sediment has accumulated to ½ wet volume of the trap.
Removed sediment shall be deposited in a suitable area and in such a manner that it will not erode.
5. The structure shall be inspected at least once every seven (7) calendar days and within 24 hours of any storm event of 0.5 inches or greater of rain per 24-hour period. See attached example inspection form.
6. Construction operations shall be carried out in such a manner that erosion and water pollution are minimized.
7. The structure shall be removed and area stabilized when the remaining drainage area has been properly stabilized.
8. All cut and fill slopes shall be 2:1 or flatter.
9. All pipe joints shall be watertight.
SECTION 01565 - 6
10. Fill material around the pipe spillway shall be hand compacted in 4-inch layers. A minimum of two feet of hand compacted backfill shall be placed over the pipe spillway before crossing it with construction equipment.
11. Outlet crest elevation shall be, at least, below the top of the embankment, except for pipe or stone outlets. This shall be at least 1.5 feet for pipe outlets and 1 ft. for stone outlets.
12. The crushed stone used in the outlet shall meet AASHTO designation M43, Size No. 2 or 24, or it’s equivalent. Gravel meeting the above gradation may be used if crushed stone is not available. Crusher run is not acceptable.
13. Sediment traps and basins must be capable of safely passing the peak discharge from a 25 year, 24-hour storm event with one foot of freeboard after settling.
2.4 PIPE LAYING ALONG STREAM
A. Special precautions against soil erosion must be taken when laying pipelines along stream. These are listed below:
1. Where the stream bank has been disturbed and is not to be protected with rock fill, a nylon blanket netting as manufactured by North American Green, Inc., P-300 or equal, shall be installed from the bottom of the stream to the high water mark to hold the mulch in place.
2. Mulch and netting shall be installed within twenty-four (24) hours of completion of the pipe installation on that section of the stream.
3. All grading should be limited to the minimum necessary to install the crossing.
4. Grading of the approaches shall be done by backblading or other similar methods so as to keep both soil and equipment out of the stream.
5. Cofferdam or other approved diversionary technique included in the construction drawings or specifications should be used wherever possible to divert flow to one part of the stream while construction work is being performed on another part.
6. All sediment-laden water pumped from ditch lines and cofferdams should be filtered and discharged to a stable area.
7. Equipment shall not enter a stream unnecessarily. Most work can be done from the bank or inside the cofferdam area.
SECTION 01565 - 7
8. Spoil shall be stored and/or disposed of outside the limits of normal high water and in such a way that it will not re-enter the stream.
9. Green concrete is toxic to aquatic life and should be kept out of contact with the flowing stream for seventy-two (72) hours. Cofferdams must be used if green concrete is to be placed in the stream.
10. Surface water runoff should be diverted away from approaches.
11. Approaches shall be reshaped, fertilized, limed, seeded and mulched immediately upon completion of construction activities and/or otherwise adequately stabilized.
12. Material for backfilling the ditch in the stream shall be able to withstand normal stream flows without excessive erosion.
13. Where the Contractor intends to continuously cross a steam, creek, or river with equipment and vehicular traffic, the streambed shall be protected as required by the WV Department of Environmental Protection. The Contractor shall submit to the Owner a plan for temporary stream crossing, which would be subject to WV DEP approval.
2.5 COFFERDAMS
A. Cofferdams are structures to enclose and divert flow around a portion of a stream so the enclosed area can be dewatered. Their primary functions are to make in stream construction work easier while minimizing pollution from the construction work. They can be constructed with sand bags, concrete traffic barriers, or other non-erodible materials.