WPSP_Specifications.pdf

PDF 86 KB Posted

Attached to
Warriors Path S. P. Lift Station(s) Renovations-UPDATED
Solicitation number
Event 32701-13751
Issued by
Sullivan County, Knoxville City, Tennessee

About this file

This is a Request for Bids from the State of Tennessee, Department of Environment and Conservation, Facilities Management for lift station renovations at Warriors Path State Park in Kingsport, Tennessee. The project involves the complete renovation of 12 sewer lift stations that are 30 years old and experiencing frequent operational failures. Work includes removal of interior components from seven single-2HP sewer lift stations and three duplex-3HP sewer lift stations, followed by installation of new Zoeller 3HP reversible grinder pumps, control panels, rails, fittings, connections, 2-inch schedule 80 PVC piping, wire, conduit, and floats in these ten stations. For two duplex-5HP sewer lift stations, the existing pumps will remain in service, but all deteriorated interior components including rails, fittings, connections, pipe, floats, control panels, wire, and conduit will be replaced as needed. All valve and connection fittings must be stainless steel or brass. The work must be completed within 60 days of contract execution unless a written exception is granted by the Facilities Management Regional Manager. On-site work shall be conducted during normal business hours of Monday through Friday, 8:00 a.m. to 4:30 p.m., unless an alternate schedule receives Facilities Management approval. A pre-construction conference and final inspection are required before work begins and final payment is released.

Bidders must possess active CMC-A and CE licenses prior to bid submission, with all licenses verified through the Tennessee Commerce and Insurance database before project award. All subcontractors must hold active Tennessee Building Contractor licenses and be identified in a Declaration of Intended Use of Subcontractors form submitted with the bid. The contractor is responsible for all permits and associated fees and must comply with State-approved versions of the International Building Code, applicable standards, regulations, and manufacturer recommendations. The contractor must maintain a Certificate of Insurance on file and be registered with the Tennessee Department of Revenue for sales and use tax collection before contract execution. Workmanship is warranted for not less than one year from the final inspection date, while materials are warranted per manufacturer specifications. All materials must be new, in good condition, and UL listed when applicable. Invoice submission is permitted only after project completion and final acceptance but no later than 10 days following acceptance. The State reserves the right to terminate the contract for convenience with 30 days' written notice and may immediately terminate if the contractor fails to properly perform obligations or materially violates contract terms. Regional management contacts are Regional Manager Chad Young at 865-606-1551 and Project Manager Doug Stephens at 865-221-2633.

View the file

Other files

File Type Posted
Lift_Stations_Addendum.pdf PDF
Terms_Conditions.pdf PDF
PreBid_Memo.pdf PDF
Warriors_Path_S.P._Lift_Station(s)_Renovations.pdf PDF
Terms_Conditions.pdf PDF
Warriors_Path_S.P._Lift_Station(s)_Renovations.pdf PDF
PreBid_Memo.pdf PDF
WPSP_Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIFT STATIONS RENOVATIONS

WARRIORS PATH STATE PARK

490 HEMLOCK ROAD

KINGSPORT, TN

This request for bids is for a Contract to furnish all material, equipment, supplies, and labor necessary to completely renovate 12-sewer lift stations that are 30-years old and are constantly having problems.

General Conditions

1) On-Site work shall be performed between receipt of signed Contract or Purchase Order and 60-days unless a written exception is granted by the Facilities Management Regional Manager.

2) For this project, the Contractor and applicable subcontractors shall possess an active CMC-A and CE license prior to submitting a bid. Failure of the Contractor and applicable subcontractors to provide copies of their appropriate license shall result in the disqualification of the bid. All licenses shall be verified via Tennessee Commerce and Insurance database before project award.

3) The Contractor shall not assign this Contract or enter into a subcontract for this project without prior written approval of Facilities Management. The Contractor’s bid shall include a Declaration of Intended Use of Subcontractor(s) form that clearly states the intent to use a subcontractor, along with their name and license number. Facilities Management reserves the right to reject a bid in whole or a subcontractor, based upon failure to possess an appropriate active TN builder’s license. After project award, any proposed substitution or addition of a subcontractor shall require written Facilities Management acceptance and approval before being allowed on-site or perform any work under this Contract. All subcontractors are required to have an active TN Building Contractor license for the applicable work to be performed before and throughout the project. Any proposed subcontractor failing to meet these requirements are not allowed to perform work on any portion of this project.

4) All work shall comply with State-approved versions of the IBC, standards, regulations, other applicable codes, manufacturer’s recommendation, and best practices. The Contractor is responsible for all permits and associated fees.

5) Only the Facilities Management Project Manager or Facilities Management Regional Manager can approve any alterations, modifications, and substitutions of the specifications or requirements of the project. No additional work shall be authorized unless pre-approved by either the Project Manager or Regional Manager in writing.

Park/Hospitality management and staff are not authorized to make any changes, deletions, or additions to the project or accept any portion of the work. This Contract shall be modified only by a written agreement signed by all parties. Any work performed outside of the written scope with any written change orders will be the responsibility of the Contractor or others and not Facilities Management. All questions, directives, and acceptance shall come only from either the Facilities Management Regional Manager and/or Project Manager.

6) The Contractor shall keep the jobsite clean and safe and leave in a neat and tidy manner.

7) All color selections shall be provided to the Contractor by the Facilities Management Project Manager.

8) All material substitutions must be pre-approved prior to bid acceptance.

9) All materials shall be installed per manufacturer’s recommendation, industry best practice, and applicable code.

10) All dimensions listed are approximate. The Contractor is solely responsible for verifying actual dimensions prior to ordering any materials or bidding. No allowances shall be made due to a bidder neglecting to visit the site and verifying dimensions and conditions.

11) All work performance under this Contract shall be under the full-time direction of the Contractor. The Contractor shall be responsible for work and performance, and damages of any subcontractors and/or independent contractors or laborers hired in connection with the work under this Contract.

General Scope of Work

Description of Demolition or Associated Work

All debris shall be removed from the park property and disposed of in accordance with all applicable regulations, unless specifically noted.

1) The Contractor shall remove all interior components from the, seven, single- 2HP sewer lift stations and the three, duplex-3HP sewer lift stations, including the control panels.

2) The Contractor shall remove any deteriorated components from the two, duplex-5HP sewer lift stations after pumping, cleaning and inspection.

New Work

1) SEVEN-2HP GRINDER PUMP-SINGLE MOTOR-SEWER LIFT STATIONS

A. The Contractor shall pump all the sewage out of the lift stations. The Contractor shall clean and inspect the lift stations. The Contractor shall repair any damaged areas of the interior walls of the lift stations as applicable.

B. The Contractor shall install new (Zoeller) 3HP, reversible, grinder pumps in all seven lift stations including, new grinder pump rails, new fittings, connections, PVC pipe, new control panels (Zoeller brand with all necessary components), wire, conduit and floats.

C. The PVC pipe shall be 2-inch schedule 80.

D. Any necessary fittings other than PVC shall be brass or stainless steel. All valves shall be stainless or brass.

E. The Contractor shall change any existing outlet pipe that is not 2-inch to 2-inch and shall be schedule 80 PVC. This includes outside the lift station.

2) THREE-3HP GRINDER PUMP-DUPLEX-SEWER LIFT STATIONS

A. The Contractor shall pump all the sewage out of the lift stations. The Contractor shall clean and inspect the lift stations. The Contractor shall repair any damaged areas of the interior walls of the lift stations as applicable.

B. The Contractor shall install new (Zoeller) 3HP, reversible, grinder pumps in all three lift stations including, new grinder pump rails, new fittings, connections, PVC pipe, new control panels (Zoeller brand with all necessary components), wire, conduit and floats.

C. The PVC pipe shall be 2-inch schedule 80.

D. Any necessary fittings other than PVC shall be brass or stainless steel. All valves shall be stainless or brass.

3) TWO-5HP GRINDER PUMP-DUPLEX-SEWER LIFT STATIONS

A. The Contractor shall pump all the sewage out of the lift stations. The Contractor shall clean and inspect the lift stations. The Contractor shall repair any damaged areas of the interior walls of the lift stations as applicable.

B. The Contractor shall not change out the existing 5HP grinder pumps.

C. The Contractor, after inspecting all interior components in the lift station, shall make any necessary repairs or replacements to grinder pump rails, fittings, connections, pipe, floats, control panels, wire and conduit.

D. The Contractor shall change any valves or connections that are not stainless steel or brass.

Additional Terms and Conditions

1) All aspects of this job shall be left in a finished condition: All finish work, interior and exterior walls and trim, finish painting, caulking and final cleanup are included in this Contract.

2) The Contractor shall be responsible for determining where all utilities are on the job site and care should be taken to protect the utilities from any damage caused by the demolition/construction. This shall include any underground utilities around the job site area. If damage occurs, it shall be repaired within a 24-hour period from the time damage occurs.

3) The Contractor shall perform work on regular time and shall invoice work time and material not to exceed the quoted price. Any variance in quote shall be addressed only with a representative of the Facilities Management Regional Office before any additional work is undertaken or materials ordered.

4) Work shall be scheduled to avoid any interference with normal operation of the park as much as possible. During the construction period, coordinate construction schedules and operations with the Park Manager. Work shall be conducted during the normal business hours of Monday through Friday, 8:00 a.m. to 4:30 p.m., unless an alternate schedule is approved by Facilities Management.

5) The successful Contractor shall schedule and attend a pre-construction conference where a pre-construction form shall be signed by Facilities Management, Contractor and Park Manager or park representative before work can begin. The Contractor shall also schedule and attend a final inspection where a final inspection form shall be signed by Facilities Management, Contractor and Park Manager or park representative before final invoice shall be paid.

6) The Contractor shall protect areas adjacent to his work and shall be required to repair any damage they may cause. The Contractor shall protect work of other trades. The Contractor shall correct any painting related damage by cleaning, repairing, or replacing, and refinishing as directed by Facilities Management. The Contractor shall leave residences and other buildings in a habitable manner after hours by securing unfinished openings.

7) Workmanship shall be warrantied for not less than one year from date of final inspection. Materials shall be warrantied as per manufacturer’s warranty.

8) Unless otherwise indicated, all materials, equipment, and supplies shall be new and in good condition, UL listed when applicable, and all work accomplished in a manner acceptable to Facilities Management.

9) Clean up of the project site shall be the responsibility of the Contractor. The Contractor shall assure that job site is clean of nails, debris, etc., at end of each day to ensure safety. The Contractor shall clean up and haul away all scrap when work is completed to an approved location off state property.

10) The Contractor, employees, and sub-contractors shall be licensed, certified, or registered as required. They shall be registered in the State of Tennessee Edison purchasing system.

11) The State of Tennessee shall not be held liable for any damage, loss of property, or injury of personnel resulting from actions of the Contractor and/or his/her sub-contractors or employees.

12) At all times, the Contractor shall have a copy of project specifications, permits, and Certificate of Insurance on-site.

13) Facilities Management may terminate this Contract for convenience without cause and for any reason. Facilities Management shall give the Contractor at least thirty (30) days written notice before the termination date. The Contractor shall be entitled to compensation for all conforming goods delivered and accepted by the Facilities Management or for satisfactory, authorized services completed as of the termination date. In no event shall the State be liable to the Contractor for compensation for any goods neither requested nor accepted by the Facilities Management or for any services neither requested by Facilities Management nor satisfactorily performed by the Contractor. In no event shall the State's exercise of its right to terminate this Contract for convenience relieve the Contractor of any liability to the State for any damages or claims arising under this Contract.

14) If the Contractor fails to properly perform its obligations under this Contract in a timely or proper manner, or if the Contractor materially violates any terms of this Contract, the State shall have the right to immediately terminate the Contract and withhold payments in excess of compensation for completed services or provided goods.

Notwithstanding the above, the Contractor shall not be relieved of liability to the State for damages sustained by virtue of any Breach Condition and the State may seek other remedies allowed at law or in equity for breach of this Contract.

15) Notwithstanding any use of the approved subcontractors, the Contractor shall be the prime contractor and responsible for compliance with all terms and conditions. The State reserves the right to request additional information or impose additional terms and conditions before approving an assignment of this Contract in whole or in part or the use of subcontractors in fulfilling the Contractor's obligations under this Contract.

16) The Contractors and all subcontractors are not authorized to day laborers or temporary labor on this project without the express written permission of Facilities Management.

17) The Contractor shall have a Certificate of Insurance on file with Facilities Management and in compliance with state regulations. The Contractor shall have insurance as shall protect the Contractor from claims which may arise out of or result from the

Contractor’s operations under the Contract and for which the Contractor may be held legally liable, whether such operations be by the Contractor or by sub-contractor or by anyone directly or indirectly employed by any of them, or anyone associated with them for whose acts they may be liable. Sub-contractors shall also be registered in the State of Tennessee Edison purchasing system, be listed on the bid application, submit copy of applicable license, and shall show proof of insurance and have workers compensation.

18) Note: Before the Contract resulting from this Invitation to Bid is signed, the apparent successful proposer shall be registered with the Department of Revenue for the collection of Tennessee sales and use tax. The State shall not approve a Contract unless the proposer provides proof of such registration. The foregoing is a mandatory requirement of an award of a Contract pursuant to this solicitation.

19) Invoice shall be submitted for payment not before project completion and final project acceptance but also no later than 10 days after project completion and acceptance. A copy of the invoice shall be submitted to: Deborah Quist, 160 State Circle, Rocky Top, TN 37769, 865-606-0785, deborah.g.smith@tn.gov.

20) Facilities Management Regional Contacts for this project are:

Regional Manager: Chad Young, 865-606-1551, chad.young@tn.gov

Project Manager: Doug Stephens, 865-221-2633, doug.stephens@tn.gov

Nothing follows mailto:deborah.g.smith@tn.gov mailto:chad.young@tn.gov

LIFT STATIONS RENOVATIONS
General Conditions
General Scope of Work
Description of Demolition or Associated Work
All debris shall be removed from the park property and disposed of in accordance with all applicable regulations, unless specifically noted.
New Work
Additional Terms and Conditions

File details come from the government source that posted it. Updated .