WIS Boiler Replacements Bid Walk-thru Questions 11.21.25.pdf
PDF 151 KB Posted
- Solicitation number
- BD-26-1446-BR625-BR001-122415
- Issued by
- Bristol County, Boston City, Massachusetts
About this file
This document is a bid walk-through questions and answers file from the Bridgewater-Raynham Regional School District regarding boiler replacements at Williams Intermediate School in Bridgewater, Massachusetts. The project involves the replacement of two existing inoperable HB Smith boilers with two new HB Smith BRTS/28HE-8 cast-iron, knock-down hot-water boilers or approved equivalents, along with associated concrete pad preparation, hydronic piping modifications, electrical and venting system connections, and safety control installations. A mandatory walkthrough was scheduled for November 19, 2025, at 10:00 AM, with bid proposals required by December 1, 2025, at 10:00 AM at the Central Office located at 166 Mt. Prospect Street, Bridgewater. The bid award is scheduled for December 5, 2025, and the project completion deadline is December 31, 2025. The project specifications require equipment with approximately 850,000 BTU/hr output per unit and minimum 80 percent combustion efficiency. All four boilers must operate in sequence through the district's Johnson Controls Building Management System upon completion.
Contractor qualifications include a minimum of ten years of verifiable experience installing commercial hydronic boiler systems, completion of at least three comparable K-12 or municipal projects within the past five years, employment of Massachusetts-licensed professionals, DCAMM Certification in HVAC, and OSHA 10-hour certification for all on-site personnel. The estimated construction cost ranges between $150,000 and $225,000. A bid bond of 5 percent of the total bid amount and performance and payment bonds at 100 percent are required. Prevailing wage regulations under M.G.L. Chapter 149, Sections 26-27 apply to the project. The awarded contractor must provide a one-year warranty including twenty-four-hour service. Equipment substitutions are permitted only if submitted at least four business days prior to bid opening with detailed technical documentation demonstrating full equivalence. Both existing boilers can be demolished and replaced simultaneously without operational constraints.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The mission of the Bridgewater-Raynham Regional School District is to provide excellence in education for all students in a safe learning environment.
The Bridgewater-Raynham Regional School District does not discriminate on the basis of race, color, sex (including pregnancy and gender identity), sexual orientation, religion, national origin, homelessness or handicap in its educational activities or employment practices.
Telephone: 508-279-2140 www.bridge-rayn.org Fax: 508-697-7012
WIS Boiler Replacements Bid Walk-thru Questions/Answers
Below are questions that were sent via email from a vendor on 11/21/25.
Questions/Answers:
1. Is there a certain time for the bid drop off on 12/1/25? Yes, the bid opening will be at 10:00am on December 1st, 2025 at our Central Office which is located at 166 Mt.
Prospect Street, in Bridgewater. The award will be on December 5th, 2025.
2. During the walkthrough, it appeared that Boiler 3 is currently operational while Boiler 4 is inactive. Can both boilers be demolished and replaced simultaneously, or is one required to remain online until the new unit is installed and operational? Please advise on any required sequencing or operational constraints? Yes, both boilers can be demolished simultaneously. When work is completed all four boilers should operate in sequence with each other through our BMS control system (Johnson Controls).