This document is a draft Request for Proposal (RFP) Volume 3, Part 2 containing detailed infrastructure mapping and site plans for the Southern Oregon Rehabilitation Center and Clinics (SORCC) in White City, Oregon. The technical drawings, prepared by Southerland Page, Inc. and SS&A Design Collective, comprehensively document existing infrastructure including site layout, water systems, sanitary sewer systems, stormwater systems, and gas and electrical infrastructure for the VA facility.

The site plans detail developable areas, construction parking and laydown zones, contractor access points, and critical requirements such as maintaining pedestrian and vehicular access throughout construction. Key infrastructure elements include existing water lines (8" and 10"), sanitary sewer lines (8", 10", and 12"), stormwater systems with a lift station, multiple transformers, electrical switches, and a gas line. The documents specify that contractors must restore all surfaces to new condition, maintain utility services to existing buildings, and obtain government approval for work outside designated developable areas, with a specific focus on protecting pedestrian and vehicle safety during the construction process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N

W phone: (541) 890-1131 email: John@ParianiLS.com

Pariani Land Surveying

361W Section 17 Tax Lot 800

Existing Conditions Utility Structure Inverts

T-1

2024-873 March 17, 2025

MNB

CJP/JRH

JRP

S.O Rehab Center & Clinic 8495 Highway 62

White City, OR 97503

REGISTERED

PROFESSIONAL

LAND SURVEYOR

July 13, 1999

JOHN R. PARIANI

#51382

Renews: December 31, 2026

OREGON

B – SUPPORTING SITE PLAN AND INFRASTRUCTURE INFORMATION

B300 DEVELOPABLE AREA

B301 DEVELOPABLE AREA

CONSTRUCTION

PARKING AND

LAYDOWN AREA

ADDITIONAL CONSTRUCTION LAYDOWN AREA

CONTRACTOR

ENTRANCE TO VA

CAMPUS

B222

B223

PEDESTRIAN AND VEHICULAR ACCESS

TO B201 & B20A MUST BE MAINTAINED

THROUGHOUT THE DURATION OF

CONSTRUCTION.

AVENUE N

ANDRIES W

AY

AVENUE J

KELLY RD

VETERANS MEMORIAL DR

96TH AVE

MESS HALL RD

WHITE ROAD

RICKER ROAD

STORMWATER

LIFT STATION

RAISED PLANTERS

EXISTING STORMWATER

POND

TEMPORARY MRI TRAILER. PEDESTRIAN ACCESS

FROM B201 AND B201A MUST BE MAINTAINED

THROUGHOUT CONSTRUCTION.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved Project Director:

VA FORM 08 - 6231

A

FULLY SPRINKLEREDU.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseTEAM

321 4 5 6 7 8 9 10

20 MAR 2025 CDB BDS

Revisions: Date:

Key Plan

Page Southerland Page, Inc.

pagethink.com

TEL

ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING

Austin / Dallas / Denver / Houston / Mexico City / Phoenix / San Francisco / Washington DC / International Affiliate Offices

1800 Main Street Suite 123 Dallas, TX 75201 214 522 3900

214 522 4380

32GO24019VA WHITE CITY

Project Abbreviation:

WHITE CITY, OREGON

US ARMY CORPS OF ENGINEERS

STAMP

SORCC WC VA

3047 Carter Hill Road Montgomery, AL 36111

SS&A Design Collective ssainc.com

TEL

FAX

334 263 6481

ARCHITECT:

DESIGNER:

SSA | PSP

221A

203A

204A

205A

206A

207A

208A

209A

225A

220A

218A

217A

215A

216A

201A

211A

23420

B300B300 & B301

B1

EXISTING INFRASTRUCTURE, SITE AND

STRUCTURES DRAFT RFP

SCALE: 1"=80'

60' 100' 160'

DEVELOPABLE AREA

KEY

GENERAL NOTES

1. WORK OUTSIDE OF DEVELOPABLE AREA MUST BE

APPROVED BY THE GOVERNMENT, AND ALL SURFACES

MUST BE RESTORED TO NEW CONDITION UPON

COMPLETION OF WORK.

2. DB CONTRACTOR SHALL ADDRESS PROTECTION OF

PEDESTRIANS AND VEHICLES IN AN ACCIDENT PREVENTION

PLAN REQUIRED BY SPECIFICATION SECTION 01 35 26.00 25

GOVERNMENT SAFETY REQUIREMENTS.

3. EXISTING SITE FEATURES WITHIN THE DEVELOPABLE

AREAS MAY BE DEMOLISHED BY THE DB CONTRACTOR.

4. ALL SURFACES AND SITE FEATURES OUTSIDE OF THE

DEVELOPABLE AREAS WHICH ARE DAMAGED BY

CONSTRUCTION MUST BE RESTORED TO NEW CONDITION.

BLDG. TO BE DEMOLISHED BY

DB CONTRACTOR

CONCRETE

PAVEMENT/SIDEWALK

ASPHALT PAVEMENT

PLAN NORTH

SD

x

SD x

SD x

SD

x

SD

x

B300 DEVELOPABLE AREA

B301 DEVELOPABLE AREA

CONSTRUCTION

PARKING AND

LAYDOWN AREA

ADDITIONAL CONSTRUCTION LAYDOWN AREA

CONTRACTOR

ENTRANCE TO VA

CAMPUS

B222

B223

PEDESTRIAN AND VEHICULAR ACCESS

TO B201 & B20A MUST BE MAINTAINED

THROUGHOUT THE DURATION OF

CONSTRUCTION.

AVENUE N

ANDRIES W

AY

AVENUE J

KELLY RD

VETERANS MEMORIAL DR

96TH AVE

MESS HALL RD

WHITE ROAD

RICKER ROAD

STORMWATER

LIFT STATION

RAISED PLANTERS

W/ IRRIGATION

EXISTING STORMWATER

POND

EXIST. FIRE HYDRANT

B201A BACKFLOW PREVENTER

EXIST. 8" WATER LINE

EXIST. WATER MAIN IN

EXIST. WATER MAIN IN

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANTEXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

EXIST. 8" WATER LINE

EXIST. FIRE HYDRANT

EXIST. FIRE HYDRANT

PLAN NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved Project Director:

VA FORM 08 - 6231

A

FULLY SPRINKLEREDU.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseTEAM

321 4 5 6 7 8 9 10

20 MAR 2025 CDB BDS

Revisions: Date:

Key Plan

Page Southerland Page, Inc.

pagethink.com

TEL

ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING

Austin / Dallas / Denver / Houston / Mexico City / Phoenix / San Francisco / Washington DC / International Affiliate Offices

1800 Main Street Suite 123 Dallas, TX 75201 214 522 3900

214 522 4380

32GO24019VA WHITE CITY

Project Abbreviation:

WHITE CITY, OREGON

US ARMY CORPS OF ENGINEERS

STAMP

SORCC WC VA

3047 Carter Hill Road Montgomery, AL 36111

SS&A Design Collective ssainc.com

TEL

FAX

334 263 6481

ARCHITECT:

DESIGNER:

SSA | PSP

221A

203A

204A

205A

206A

207A

208A

209A

225A

220A

218A

217A

215A

216A

201A

211A

23420

B300B300 & B301

B2

EXISTING INFRASTRUCTURE, DOMESTIC AND

FIRE WATER SYSTEMS DRAFT RFP

SCALE: 1"=80'

60' 100' 160'

DEVELOPABLE AREA

KEY

GENERAL NOTES

1. WORK OUTSIDE OF DEVELOPABLE AREA MUST BE

APPROVED BY THE GOVERNMENT, AND ALL SURFACES

MUST BE RESTORED TO NEW CONDITION UPON

COMPLETION OF WORK.

2. DB CONTRACTOR SHALL ADDRESS PROTECTION OF

PEDESTRIANS AND VEHICLES IN AN ACCIDENT PREVENTION

PLAN REQUIRED BY SPECIFICATION SECTION 01 35 26.00 25

GOVERNMENT SAFETY REQUIREMENTS.

3. EXISTING SITE FEATURES WITHIN THE DEVELOPABLE

AREAS MAY BE DEMOLISHED BY THE DB CONTRACTOR.

4. ALL SURFACES AND SITE FEATURES OUTSIDE OF THE

DEVELOPABLE AREAS WHICH ARE DAMAGED BY

CONSTRUCTION MUST BE RESTORED TO NEW CONDITION.

5. THE CONTRACTOR IS TO MAINTAIN UTILITY SERVICE TO

EXISTING BUILDINGS ON CAMPUS. AT NO POINT SHALL THE

CONTRACTOR SHUT OFF UTILITIES TO EXISTING BUILDINGS

WITHOUT HAVING A NEW UTILITY IN PLACE TO FEED THAT

BUILDING.

BLDG. TO BE DEMOLISHED BY

DB CONTRACTOR

CONCRETE

PAVEMENT/SIDEWALK

ASPHALT PAVEMENT

WATER LINE (W/ SIZE)

SD x

SD x

SD

x

SD

x

B300 DEVELOPABLE AREA

B301 DEVELOPABLE AREA

CONSTRUCTION

PARKING AND

LAYDOWN AREA

ADDITIONAL CONSTRUCTION LAYDOWN AREA

CONTRACTOR

ENTRANCE TO VA

CAMPUS

B222

B223

PEDESTRIAN AND VEHICULAR ACCESS

TO B201 & B20A MUST BE MAINTAINED

THROUGHOUT THE DURATION OF

CONSTRUCTION.

AVENUE N

ANDRIES W

AY

AVENUE J

KELLY RD

VETERANS MEMORIAL DR

96TH AVE

MESS HALL RD

WHITE ROAD

RICKER ROAD

STORMWATER

LIFT STATION

RAISED PLANTERS

EXISTING STORMWATER

POND

8" SANITARY SEWER

10" SANITARY SEWER

12" SANITARY SEWERSANITARY SEWER MAIN OUT

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved Project Director:

VA FORM 08 - 6231

A

FULLY SPRINKLEREDU.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseTEAM

321 4 5 6 7 8 9 10

20 MAR 2025 CDB BDS

Revisions: Date:

Key Plan

Page Southerland Page, Inc.

pagethink.com

TEL

ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING

Austin / Dallas / Denver / Houston / Mexico City / Phoenix / San Francisco / Washington DC / International Affiliate Offices

1800 Main Street Suite 123 Dallas, TX 75201 214 522 3900

214 522 4380

32GO24019VA WHITE CITY

Project Abbreviation:

WHITE CITY, OREGON

US ARMY CORPS OF ENGINEERS

STAMP

SORCC WC VA

3047 Carter Hill Road Montgomery, AL 36111

SS&A Design Collective ssainc.com

TEL

FAX

334 263 6481

ARCHITECT:

DESIGNER:

SSA | PSP

221A

203A

204A

205A

206A

207A

208A

209A

225A

220A

218A

217A

215A

216A

201A

211A

23420

B300B300 & B301

B3

EXISTING INFRASTRUCTURE, SANITARY

SEWER SYSTEM DRAFT RFP

SCALE: 1"=80'

60' 100' 160'

DEVELOPABLE AREA

KEY

GENERAL NOTES

1. WORK OUTSIDE OF DEVELOPABLE AREA MUST BE

APPROVED BY THE GOVERNMENT, AND ALL SURFACES

MUST BE RESTORED TO NEW CONDITION UPON

COMPLETION OF WORK.

2. DB CONTRACTOR SHALL ADDRESS PROTECTION OF

PEDESTRIANS AND VEHICLES IN AN ACCIDENT PREVENTION

PLAN REQUIRED BY SPECIFICATION SECTION 01 35 26.00 25

GOVERNMENT SAFETY REQUIREMENTS.

3. EXISTING SITE FEATURES WITHIN THE DEVELOPABLE

AREAS MAY BE DEMOLISHED BY THE DB CONTRACTOR.

4. ALL SURFACES AND SITE FEATURES OUTSIDE OF THE

DEVELOPABLE AREAS WHICH ARE DAMAGED BY

CONSTRUCTION MUST BE RESTORED TO NEW CONDITION.

5. THE CONTRACTOR IS TO MAINTAIN UTILITY SERVICE TO

EXISTING BUILDINGS ON CAMPUS. AT NO POINT SHALL THE

CONTRACTOR SHUT OFF UTILITIES TO EXISTING BUILDINGS

WITHOUT HAVING A NEW UTILITY IN PLACE TO FEED THAT

BUILDING.

BLDG. TO BE DEMOLISHED BY

DB CONTRACTOR

CONCRETE

PAVEMENT/SIDEWALK

ASPHALT PAVEMENT

PLAN NORTH

SANITARY SEWER LINE

(W/SIZE)

SD x

SD x

SD

x

SD

x

B300 DEVELOPABLE AREA

B301 DEVELOPABLE AREA

CONSTRUCTION

PARKING AND

LAYDOWN AREA

ADDITIONAL CONSTRUCTION LAYDOWN AREA

CONTRACTOR

ENTRANCE TO VA

CAMPUS

B222

B223

PEDESTRIAN AND VEHICULAR ACCESS

TO B201 & B20A MUST BE MAINTAINED

THROUGHOUT THE DURATION OF

CONSTRUCTION.

AVENUE N

ANDRIES W

AY

AVENUE J

KELLY RD

VETERANS MEMORIAL DR

96TH AVE

MESS HALL RD

WHITE ROAD

RICKER ROAD

STORMWATER

LIFT STATION

EXISTING STORMWATER

POND

12" STORMWATER

FORCE MAIN

36" DISCHARGE PIPE

TO POND

STORMWATER

LIFT STATION SERVING

B201A

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved Project Director:

VA FORM 08 - 6231

A

FULLY SPRINKLEREDU.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseTEAM

321 4 5 6 7 8 9 10

20 MAR 2025 CDB BDS

Revisions: Date:

Key Plan

Page Southerland Page, Inc.

pagethink.com

TEL

ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING

Austin / Dallas / Denver / Houston / Mexico City / Phoenix / San Francisco / Washington DC / International Affiliate Offices

1800 Main Street Suite 123 Dallas, TX 75201 214 522 3900

214 522 4380

32GO24019VA WHITE CITY

Project Abbreviation:

WHITE CITY, OREGON

US ARMY CORPS OF ENGINEERS

STAMP

SORCC WC VA

3047 Carter Hill Road Montgomery, AL 36111

SS&A Design Collective ssainc.com

TEL

FAX

334 263 6481

ARCHITECT:

DESIGNER:

SSA | PSP

221A

203A

204A

205A

206A

207A

208A

209A

225A

220A

218A

217A

215A

216A

201A

211A

23420

B300B300 & B301

B4

EXISTING INFRASTRUCTURE, STORMWATER

SYSTEM DRAFT RFP

SCALE: 1"=80'

60' 100' 160'

DEVELOPABLE AREA

KEY

GENERAL NOTES

1. WORK OUTSIDE OF DEVELOPABLE AREA MUST BE

APPROVED BY THE GOVERNMENT, AND ALL SURFACES

MUST BE RESTORED TO NEW CONDITION UPON

COMPLETION OF WORK.

2. DB CONTRACTOR SHALL ADDRESS PROTECTION OF

PEDESTRIANS AND VEHICLES IN AN ACCIDENT PREVENTION

PLAN REQUIRED BY SPECIFICATION SECTION 01 35 26.00 25

GOVERNMENT SAFETY REQUIREMENTS.

3. EXISTING SITE FEATURES WITHIN THE DEVELOPABLE

AREAS MAY BE DEMOLISHED BY THE DB CONTRACTOR.

4. ALL SURFACES AND SITE FEATURES OUTSIDE OF THE

DEVELOPABLE AREAS WHICH ARE DAMAGED BY

CONSTRUCTION MUST BE RESTORED TO NEW CONDITION.

5. THE CONTRACTOR IS TO MAINTAIN UTILITY SERVICE TO

EXISTING BUILDINGS ON CAMPUS. AT NO POINT SHALL THE

CONTRACTOR SHUT OFF UTILITIES TO EXISTING BUILDINGS

WITHOUT HAVING A NEW UTILITY IN PLACE TO FEED THAT

BUILDING.

BLDG. TO BE DEMOLISHED BY

DB CONTRACTOR

CONCRETE

PAVEMENT/SIDEWALK

ASPHALT PAVEMENT

PLAN NORTH

STORM DRAIN (W/ SIZE)

STORMWATER FORCE MAIN

SD x

SD x

SD

x

SD

x

B300 DEVELOPABLE AREA

B301 DEVELOPABLE AREA

CONSTRUCTION

PARKING AND

LAYDOWN AREA

ADDITIONAL CONSTRUCTION LAYDOWN AREA

CONTRACTOR

ENTRANCE TO VA

CAMPUS

B222

B223

PEDESTRIAN AND VEHICULAR ACCESS

TO B201 & B20A MUST BE MAINTAINED

THROUGHOUT THE DURATION OF

CONSTRUCTION.

AVENUE N

ANDRIES W

AY

AVENUE J

KELLY RD

VETERANS MEMORIAL DR

96TH AVE

MESS HALL RD

WHITE ROAD

RICKER ROAD

STORMWATER

LIFT STATION

EXISTING STORMWATER

POND

TRANSFORMER E

AND PANEL MPD

SWITCH T SWITCH V

TRANSFORMER A

SWITCH B

TRANSFORMER

B

TRANSFORMER HSWITCH S

TRANSFORMER ITRANSFORMER J

TRANSFORMER K

SWITCH R

TRANSFORMER L

TRANSFORMER M

TRANSFORMER O

TRANSFORMER R

TRANSFORMER U

TRANSFORMER P

SWITCH Q

TRANSFORMER F

SWITCH U

TRANSFORMER T

EXISTING GAS LINE

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved Project Director:

VA FORM 08 - 6231

A

FULLY SPRINKLEREDU.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseTEAM

321 4 5 6 7 8 9 10

20 MAR 2025 CDB BDS

Revisions: Date:

Key Plan

Page Southerland Page, Inc.

pagethink.com

TEL

ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING

Austin / Dallas / Denver / Houston / Mexico City / Phoenix / San Francisco / Washington DC / International Affiliate Offices

1800 Main Street Suite 123 Dallas, TX 75201 214 522 3900

214 522 4380

32GO24019VA WHITE CITY

Project Abbreviation:

WHITE CITY, OREGON

US ARMY CORPS OF ENGINEERS

STAMP

SORCC WC VA

3047 Carter Hill Road Montgomery, AL 36111

SS&A Design Collective ssainc.com

TEL

FAX

334 263 6481

ARCHITECT:

DESIGNER:

SSA | PSP

221A

203A

204A

205A

206A

207A

208A

209A

225A

220A

218A

217A

215A

216A

201A

211A

23420

B300B300 & B301

B5

EXISTING INFRASTRUCTURE, GAS,

ELECTRICAL, AND STEAM SYSTEMS DRAFT RFP

SCALE: 1"=80'

60' 100' 160'

DEVELOPABLE AREA

KEY

GENERAL NOTES

1. WORK OUTSIDE OF DEVELOPABLE AREA MUST BE

APPROVED BY THE GOVERNMENT, AND ALL SURFACES

MUST BE RESTORED TO NEW CONDITION UPON

COMPLETION OF WORK.

2. DB CONTRACTOR SHALL ADDRESS PROTECTION OF

PEDESTRIANS AND VEHICLES IN AN ACCIDENT PREVENTION

PLAN REQUIRED BY SPECIFICATION SECTION 01 35 26.00 25

GOVERNMENT SAFETY REQUIREMENTS.

3. EXISTING SITE FEATURES WITHIN THE DEVELOPABLE

AREAS MAY BE DEMOLISHED BY THE DB CONTRACTOR.

4. ALL SURFACES AND SITE FEATURES OUTSIDE OF THE

DEVELOPABLE AREAS WHICH ARE DAMAGED BY

CONSTRUCTION MUST BE RESTORED TO NEW CONDITION.

5. THE CONTRACTOR IS TO MAINTAIN UTILITY SERVICE TO

EXISTING BUILDINGS ON CAMPUS. AT NO POINT SHALL THE

CONTRACTOR SHUT OFF UTILITIES TO EXISTING BUILDINGS

WITHOUT HAVING A NEW UTILITY IN PLACE TO FEED THAT

BUILDING.

BLDG. TO BE DEMOLISHED BY

DB CONTRACTOR

CONCRETE

PAVEMENT/SIDEWALK

ASPHALT PAVEMENT

PLAN NORTH

NATURAL GAS LINE

UNDERGROUND POWER

STEAM LINES

VOL 03 H Geotechnical