WFLHD Construction Contract Administration_FY 23 V2.pdf

PDF 162 KB Posted

Attached to
OR FLAP DOT CRGNSA 100(7), Historic Columbia River Highway State Trail, Mitchell Point Dr. to Ruthton Trailhead
Solicitation number
69056726B000009
Issued by

About this file

This document is a Federal Highway Administration (FHWA) compliance filing that provides required data on construction contract change order administration procedures under FAR 36.211. The document states that FHWA currently has no agency-specific additional policies and procedures beyond federal requirements for definitizing equitable adjustments for change orders, which are defined as modifications to contract work per FAR 52.243-4.

The document presents a three-year performance data table (FY 2021-2023) tracking the time required to definitize equitable adjustments for change order proposals under construction contracts. Key findings show that definitization timeframes varied significantly across the period: in FY 2021, nine total proposals were processed with processing times ranging from 0-30 days (1 proposal) to 366+ days (2 proposals); in FY 2022, two total proposals were definitized, with most completed within 91-180 days; and in FY 2023, thirteen total proposals were definitized with a more distributed timeline across all categories except the fastest (0-30 days), with notable numbers in the 31-60 day (3), 61-90 day (3), 91-180 day (4), and 181-365 day (3) ranges. No undefinitized equitable adjustments carried over to contract completion in any fiscal year.

View the file

Other files

File Type Posted
QA_10.14.2026.pdf PDF
Amendment A001.pdf PDF
QA_10.8.2026.pdf PDF
ora-dot-crgnsa100-7_plans.pdf PDF
IFB_69056726B000009_OR FLAP DOT CRGNSA 100(7).pdf PDF
Physical Data.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WFLHD Construction Contract Administration

FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.

Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.

There are no agency-specific additional policies and procedures that exist at this time.

The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).

Time to definitize after receipt of an adequate change order definitization proposal under construction contracts

Number of change order proposals definitized under construction contracts

FY 2021 FY 2022 FY 2023

0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance

0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4

File details come from the government source that posted it. Updated .