WFLHD Construction Contract Administration_FY 23 V2.pdf
PDF 162 KB Posted
- Solicitation number
- 69056726B000009
About this file
This document is a Federal Highway Administration (FHWA) compliance filing that provides required data on construction contract change order administration procedures under FAR 36.211. The document states that FHWA currently has no agency-specific additional policies and procedures beyond federal requirements for definitizing equitable adjustments for change orders, which are defined as modifications to contract work per FAR 52.243-4.
The document presents a three-year performance data table (FY 2021-2023) tracking the time required to definitize equitable adjustments for change order proposals under construction contracts. Key findings show that definitization timeframes varied significantly across the period: in FY 2021, nine total proposals were processed with processing times ranging from 0-30 days (1 proposal) to 366+ days (2 proposals); in FY 2022, two total proposals were definitized, with most completed within 91-180 days; and in FY 2023, thirteen total proposals were definitized with a more distributed timeline across all categories except the fastest (0-30 days), with notable numbers in the 31-60 day (3), 61-90 day (3), 91-180 day (4), and 181-365 day (3) ranges. No undefinitized equitable adjustments carried over to contract completion in any fiscal year.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_10.14.2026.pdf | ||
| Amendment A001.pdf | ||
| QA_10.8.2026.pdf | ||
| ora-dot-crgnsa100-7_plans.pdf | ||
| IFB_69056726B000009_OR FLAP DOT CRGNSA 100(7).pdf | ||
| Physical Data.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2021 FY 2022 FY 2023
0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4