Western Hills Neighborhood Revitalization Project - Special Provisions

This document comprises the Special Provisions for the Western Hills Neighborhood Revitalization Project, a joint undertaking by the City of Tucson Department of Transportation and Mobility in partnership with the Arizona Department of Transportation (ADOT). The project involves comprehensive neighborhood improvements including roadway milling and repaving, ADA upgrades with concrete curb access ramps and sidewalks, enhanced bus stops with shelters along E 36th Street, speed humps and speed table installations, asphaltic shared-use path construction within James Thomas Park, utility adjustments, and drainage improvements through roadway reprofiling. The project encompasses the Western Hills and Las Vistas neighborhoods bounded by E 36th Street to the north, Jason Vista to the south, S Campbell Avenue to the west, and S Country Club Road to the east. The contractor shall have 360 consecutive calendar days from the Notice to Proceed to complete all work. A pre-construction meeting must be scheduled within 14 calendar days of notice of award and held within 30 days, at which point the Notice to Proceed will be issued. The contractor must submit a critical path construction schedule meeting or reducing the allotted contract days.

The project imposes substantial requirements regarding quality control, traffic management, environmental compliance, and stakeholder coordination. The contractor bears full responsibility for quality control testing in accordance with Table 106-1 specifications and must designate a Quality Control Manager. Payment adjustments apply for deficiencies in asphaltic concrete mixture properties and compaction per Tables 110-2 and 110-5. Traffic control must maintain at least one open lane unless alternative approaches are approved, with emergency vehicle and mail delivery access continuously maintained. The contractor must coordinate with utilities, manage invasive species eradication including buffelgrass treatment, implement a Stormwater Pollution Prevention Plan, and provide GPS documentation of utilities accurate to within 0.5 feet. Specific restrictions apply during identified community events including the Gem and Mineral Show, Pima County Fair, and school sessions. Record drawings must be submitted within 60 days of project acceptance, with final retention withheld until acceptance is granted.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Provisions City of Tucson Plan No. U-2025-010 Western Hills Neighborhood Federal Project No. TUC-0(275)D Revitalization Project ADOT TRACS No. T0466 01C

SP-1

WESTERN HILLS NEIGHBORHOOD

REVITALIZATION PROJECT

SPECIAL PROVISIONS

COT Job No. 181820-06

COT Plan No. U-2025-010

Federal Project No. TUC-0(275)D

ADOT TRACS No. T0466 01C

PCRWRD No. UPC-2024-160

February 2026

SP-2

CONTRACT SPECIAL PROVISIONS FOR:

WESTERN HILLS NEIGHBORHOOD

REVITALIZATION PROJECT

COT JOB NO. 181820-06, COT PLAN NO. U-2025-010

FEDERAL PROJECT NO. TUC-0(275)D, ADOT TRACS NO. T0466 01C

PROFESSIONAL SEALS

These specifications were prepared under the direction of the following individuals:

Daniel Bacon, P.E. (Civil), Kimley-Horn

Their seals, affixed above, attest that those portions of these specifications which relate to the plan sheet numbers appearing next to the seal were prepared under their direction.

d

Date Signe

.C

ATE NO

CIFITRE

A

ANOZIR

, U A..S.

s

R seforPderetsige ional Engineer (Civi)l

69335

DANIEL E.

BACON

02 02 26

SP-3

TABLE OF CONTENTS

TABLE OF CONTENTS

SPECIFICATIONS AND DETAILS

PROJECT LOCATION AND SCOPE OF WORK

GENERAL PROVISIONS

SECTION 101 - ABBREVIATIONS AND TERMS

SECTION 102 - BIDDING REQUIREMENTS AND CONDITIONS

SECTION 104 - SCOPE OF WORK

SECTION 105 - CONTROL OF WORK

SECTION 106 - CONTROL OF MATERIAL

SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC

SECTION 108 - PROSECUTION AND PROGRESS

SECTION 109 - MEASUREMENT AND PAYMENT

SECTION 110 – CORRECTIVE REQUIREMENTS FOR DEFICIENCES

SECTION 201 - CLEARING & GRUBBING

SECTION 202 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

ITEM 2020061 RELOCATE MAILBOX

SECTION 206 - FURNISH WATER SUPPLY

SECTION 404 - BITUMINOUS TREATMENTS

SECTION 406 - ASPHALTIC CONCRETE

SECTION 515 - UTILITY IMPACTS

ITEM 5150005 - UTILITY POTHOLING, DEPTH LESS THAN TWELVE FEET

(12’)

SECTION 607 - SIGN SUPPORTS

ITEM 6070010 - SIGN POST (PERFORATED) (SINGLE)

ITEM 6070110 - FOUNDATION FOR SIGN POST (PERFORATED)

SECTION 608 - SIGN PANELS

SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC

SECTION 704 - THERMOPLASTIC STRIPES AND MARKINGS

SECTION 706 - RAISED PAVEMENT MARKERS

SECTION 708 - PAINTED PAVEMENT MARKINGS

SP-4

SECTION 730 - GENERAL REQUIREMENTS FOR TRAFFIC SIGNAL AND

STREET LIGHTING SYSTEMS

SECTION 732 - ELECTRICAL MATERIAL AND SERVICE

SECTION 803 - LANDSCAPE BORROW AND PLATING MATERIAL

ITEM 8061700 - LANDSCAPE PRUNING

ITEM 8080111 - MISCELLANEOUS LANDSCAPE WORK ALLOWANCE

SECTION 810 - EROSION CONTROL AND POLLUTION PREVENTION

SECTION 908 - CONCRETE CURBS, GUTTERS, SIDEWALKS AND

DRIVEWAYS

SECTION 909 - SURVEY MONUMENTS

SECTION 924 - CONTRACTOR QUALITY CONTROL

ITEM 9240170 - CONTRACTOR QUALITY CONTROL

SECTION 930 - INCIDENTAL ITEMS

ITEM 9300109 - MISCELLANEOUS WORK (MINOR ALTERATIONS IN

DETAILS OF CONSTRUCTION)

SECTION 1005 - BITUMINOUS MATERIALS FOR SURFACING

SECTION 1007 - RETROREFLECTIVE SHEETING

SP-5

LIST OF APPENDICES

APPENDIX A - SPEED HUMP AND SPEED TABLE DETAILS

APPENDIX B – CURB ACCESS RAMP DETAILS

APPENDIX C - BUS STOP PAD, SHELTER & PULLOUT DETAILS

APPENDIX D - SURVEY MONUMENT DETAILS

APPENDIX E – WESTERN BURROWING OWL AWARENESS

APPENDIX F – NON-VIBRATORY ROLLING PATTERN PROCEDURE

SP-6

SPECIFICATIONS AND DETAILS

The work embraced herein shall be performed in accordance with the requirements of the following documents:

Specifications

Pima Association of Governments (PAG), Standard Specifications for Public Improvements, 2015 Edition, Volume 1 (typically referenced as “Standard Specifications” unless otherwise specified).

http://apps.pagnet.org/standardspecifications/

Arizona Department of Transportation (ADOT), Highways Division, Standard Specifications for Road and Bridge Construction, 2021 Edition.

https://azdot.gov/sites/default/files/media/2021/04/2021_Standard_Specifications_for_Road_and _Bridge_Construction_PC.pdf

Details

PAG, Standard Details for Public Improvements, 2015 Edition, Volume 2, except as modified on the plans.

http://apps.pagnet.org/standardspecifications/

City of Tucson DTM, Speed Hump and Table Detail, 2024. See Appendix A of these Special Provisions (Sheets 1 through 4).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/speed-hump-table-detail_oct2024.pdf

City of Tucson Department of Transportation and Mobility (DTM), Curb Access Ramp Detail, 2025. See Appendix B of these Special Provisions (Sheets 1 through 15).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/curb_access_ramp_sep2025.pdf

City of Tucson DTM, Bus Stop Pad, Shelter & Pullout Detail, 2025. See Appendix C of these Special Provisions (Sheets 1 through 13).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/bus_stop_pad_shelter_pullout_detail_jan2025__update.pdf

City of Tucson DTM, Survey Monument Detail, 2024. See Appendix D of these Special Provisions (Sheets 1 through 5).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/survey-monument-detail.pdf

SP-7

ADOT, Traffic Safety for School Areas Guidelines, 2006.

https://azdot.gov/sites/default/files/2019/07/adot-traffic-safety-for-school-area-guidelines.pdf

ADOT, Engineering And Construction, Construction Standard Drawings, (C-Drawings), May 2012 and current revisions.

https://azdot.gov/business/engineering-and-construction/roadway-engineering/roadway-design/construction-standard

ADOT, Engineering And Construction, Signing and Marking Standard Drawings, June 2014 and current revisions.

https://azdot.gov/business/engineering-and-construction/traffic/signing-and-marking-standard-sms-drawings

ADOT, Engineering And Construction, Signals and Lighting Standard Drawings, current revisions.

https://azdot.gov/business/engineering-and-construction/traffic/signing-and-marking-standard-sms-drawings

Manuals

U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform Traffic Control Devices for Streets and Highways, 11th Edition, December 2023.

https://mutcd.fhwa.dot.gov/pdfs/11th_Edition/mutcd11theditionhl.pdf

Pima County/City of Tucson, Signing and Pavement Marking Manual, 2020, First Edition.

https://content.civicplus.com/api/assets/c8d13f95-b46c-446e-97fe-8e5127201983

Pima County Department of Transportation, Street Lighting and ITS Conduit Design Manual, June 2011 and current revisions.

https://content.civicplus.com/api/assets/b5f6d60f-1c64-4e50-80f3-1c2f04ac07a9

SP-8

Other Specifications and Details

Tucson Water, Standard Specifications and Details Manual, 2017 Edition:

https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/tucson-water/documents/tucson_water_standard_specifications_and_details_manual_complete_dec_201 7_v1.pdf

Pima County Regional Wastewater Reclamation Department, Standard Specifications and Details for Construction, 2022 Edition.

https://content.civicplus.com/api/assets/82db6816-17b9-4383-8c2e-591b24dd23f4

These Special Provisions, Bid Schedule, and the Project Plans.

SP-9

PROJECT LOCATION AND SCOPE OF WORK

The proposed work is located within Section 29 of Township 14 South, Range 14 East, Gila and Salt River Meridian, City of Tucson, Pima County, Arizona.

This project consists of furnishing all labor, materials, and equipment necessary to perform pavement rehabilitation and ADA upgrades within the Western Hills and Las Vistas neighborhood. The project limits include E 36th Street to the north, Jason Vista to the south, S Campbell Avenue to the west, and S Country Club Road to the east.

The work includes, but is not limited to, the following construction activities and other related incidental work:

• Milling, pavement preparation, and paving of residential streets for the locations shown on the City of Tucson Plan No. U-2025-010.

• ADA upgrades and installations for concrete curb access ramps, concrete sidewalk, and concrete driveway aprons as shown on the City of Tucson Plan No. U-2025-010.

o Ramp and Sidewalk Notes:

The City expects that the Contractor will have some flexibility in the layout of the ramps using City ramp details, provided that federal ADA standards are met.

Sidewalks are to be constructed to PROWAG Standards; City or PAG standard details may be used, as applicable.

No changes or modifications shall be made by the contractor without approval of a City representative.

The removal of sidewalk and curb ramps is included in Item 2020007 Removal of Miscellaneous Concrete. The City of Tucson Plan No. U- 2025-010 shows select locations of sidewalk and curb ramp removals but not all locations. Field adjustments are anticipated.

• Enhanced bus stops along E 36th Street as shown on the City of Tucson Plan No. stated above.

• Speed hump and speed table installations as shown on the City of Tucson Plan No. U- 2025-010.

o Speed Hump and Speed Table Notes:

Surface treatment shall include the speed humps and tables with new striping and raised pavement markings per Detail 220 (included in Appendix E). Speed tables and speed humps shall receive the PAG 2-LV, as a non-RAP mixture with PG70-10 binder.

• Asphaltic shared use path, post-and-cable fencing, and parking lot resurfacing within the James Thomas Park as shown on the City of Tucson Plan No. U-2025-010.

• Utility adjustments as a result of conflicts between existing features and the construction activities stated within these special provisions.

• Reprofiling of roadway segments to enhance drainage flow and mitigate ponding issues.

SP-10

GENERAL PROVISIONS

For these Special Provisions, the terms Agency, Department, City, City of Tucson, and Engineer are synonymous.

1. Project Objectives

The objective of this contract is to complete construction as quickly as possible while minimizing the impact to the Stakeholders. The Stakeholders are, but not limited to, the adjacent businesses, schools, commuters, buses, emergency services, pedestrians, bicyclists, and adjoining neighborhoods. As such, this work will be accomplished in an orderly manner as defined herein.

Driver and pedestrian/access shall be maintained during the construction of improvements.

Temporary paved access shall always be provided by the contractor to meet the Americans with Disabilities Act (ADA) requirements. The contractor shall maintain access to all side streets, access roads, driveways, alleys, parking lots, and adjacent businesses during their hours of operations. The contractor is advised that an approved construction sequencing scheme meeting the intent of the project objectives will need to be followed. Once approved, the contractor shall follow the phasing plan unless modified by the Engineer in writing.

Access to neighborhoods, businesses, and schools shall be maintained at all times.

2. Project Limits and Restrictions

The contractor shall perform all work within the public right-of-way, legally obtained easements including temporary construction easements (TCEs), legally obtained rights-of-entry (ROE), drainage easements, and legally acquired property by the City of Tucson. The contractor shall assume all responsibility and liability for any encroachment upon private property. The use of private property for construction yards will be allowed only if zoning requirements allows its use for this purpose – see Section 106-9 of the Standard Specifications for further details regarding temporary construction yards. The cost of the construction yard is considered incidental to the project. Under no circumstances shall any equipment, vehicles or other construction items, not specifically required or needed for the immediate construction at hand, be stored or left on private property without the express written permission of the property owner.

The contractor shall field verify all existing conditions shown on plans and specified herein prior to beginning construction. Any significant deviations to the conditions that may affect the timely construction of improvements shall be brought to the attention of the Engineer within 24 hours of discovery. Prior to delivery of any equipment, materials or supplies to the site of any work, or the beginning of any construction work, it is strongly recommended that the contractor take pre-construction photos or videos as deemed appropriate for establishing the conditions existing in all the areas that may be affected by the construction.

SP-11

3. Prebid Meeting

A pre-bid meeting is a part of the bid process and will be held at the location determined in the Invitation for Bids solicitation.

Before undertaking work, at any location covered by this project, the contractor shall obtain all applicable permits, from the City of Tucson, as needed.

4. Contract Time

Once the contract has been awarded and signed, the contractor shall be issued a Notice to Proceed (NTP). This will begin Phase 1 of the project, the construction phase, and the contractor shall have 360 consecutive calendar days to complete this work as shown on the project plans and as specified herein.

If the Final Inspection should reveal work that is not completed or is unacceptable to the Engineer for any reason, a "punch list" of these items shall be generated and provided to the contractor. Substantial completion (for the purpose of stopping the contract time) will be granted in accordance with Section 105-21 of the Standard Specifications.

Once substantial completion is granted, the contractor shall actively work to achieve final acceptance of the construction phase of the contract within 15-calendar days from the substantial completion date of that phase. Failure to prosecute the remaining work within this time period will result in the resumption of time charges and the application of liquidated damages from the date scheduled for final acceptance.

When the work on this list has been satisfactorily completed, final acceptance of the phase(s) shall be given for all items of work.

The Contractor shall schedule a pre-construction meeting within 14 calendar days of notice of award and hold the meeting within 30 days of notice of award.

DTM will issue a notice to proceed at the pre-construction meeting.

At the pre-construction meeting, the Contractor shall submit a critical path construction schedule for all project elements that meets or decreases the allotted Calendar Contract Days.

5. Construction Scheduling

Various activities within the community must be considered in the project scheduling to provide the most effective and least impacting effort. The following dates are provided for information and shall be referred to when planning work and lane restrictions:

SP-12

Christmas Retail Season .......................................................................... Nov. 1st to Jan. 2nd Gem and Mineral Show ........................................................................ Jan. 27th to Feb. 11th Pima County Fair .............................................................................. April 18th to April 28th Tucson Water Department Restrictions ............................................... April 1st to Sept. 30th SWG Construction Restrictions .................................................... October 1st to March 30th TEP Construction Restrictions ........................................................... May 1st to August 30th School Session ..................................................................................... July 17th to May 24th

The contractor shall factor these events into his construction schedule. The contractor may do incidental work during these restrictions to complete areas that are not specifically described herein if no additional impacts to commuters, businesses, and residents are imposed and the work is previously approved by the Engineer.

Work requiring lane restrictions beyond the minimum stated herein shall be done at night unless approved by the Engineer.

All work shall be done during the day.

The intent of this project is to complete the work as quickly as possible to minimize any inconvenience to the traveling public, or adjacent stakeholders. To that end, the contractor is strongly encouraged to consider working weekends, double shifts, or as often as necessary to complete the work by the specific milestones. Lost time due to little or no work being performed shall not be considered when applying for a contract time extension.

6. Maintenance & Protection of Traffic

The contractor shall be responsible for all construction zone traffic control and shall provide a traffic control plan in accordance with Section 701 of the Standard Specifications, these Special Provisions and shall be approved by the Engineer prior to construction.

The traffic control plans shall meet the conditions and requirements described in Subsection 104- 5 of these Special Provisions.

The contractor shall not allow any work to commence unless the conditions and requirements of Subsection 104-5 Maintenance of Traffic are adhered to. If the contractor fails to abide by the conditions and requirements of this specification section, it shall be considered sufficient grounds for the City to suspend the contractor’s work.

7. Construction Sequencing

The Contractor shall be issued a Notice to Proceed at the Pre-Construction meeting. The Contractor shall field verify all existing conditions shown on plans and specified herein prior to beginning construction. Any significant deviations to the conditions that may affect the timely

SP-13

construction of improvements shall be brought to the attention of the Engineer within 24 hours of discovery.

Prior to the delivery of any equipment, materials or supplies to the site of any work, or the beginning of any construction work, it is strongly recommended that the Contractor take pre-construction photos or videos for the purpose of establishing the conditions existing in all the areas to be affected by the construction.

The Contractor shall follow the sequencing and/or steps as described under Treatment A. Paving schedules shall be coordinated closely with any weather. Pavement data is provided in the project plans. If the paving operation is not started directly behind the milling, grading and compaction steps and weather-related issues arise, the contractor will be held responsible for any issues that may arise.

Treatment A – Mill and Infill, and Pavement Reprofiling

ID TREATMENT A - MILL AND INFILL

1 Data Collection:

-Contractor shall identify and document existing roadway features including pavement markings, utility facilities, survey monumentation, and speed humps.

-The City’s surveyor will cross-section the roadway prior to the treatment in order to provide pavement grades.

2 Pavement Preparation:

-Contractor shall adjust utility facilities (as required) prior to and after work efforts. No utility holes will be left overnight without trench plates.

-Contractor shall remove obstructions and eradicate any vegetation within or adjacent to the roadway necessary to execute the contract.

3 ADA Ramps:

-Contractor shall remove and replace ADA ramps per the table information provided in project plans. New ramps are only to be installed where there is existing or new sidewalk.

-Contractor shall complete replacement of any and all landscape materials (brick, gravel, etc.) removed or relocated during the curb ramp/sidewalk installation in an attempt to return these materials to state of pre-ramp installation.

-Contractor shall complete any other miscellaneous work necessary to deliver the final product, complete in place, of the completed curb ramp installation.

4 Milling and Reprofiling:

-Contractor shall mill/plane the existing asphalt per the depth identified in the Project Plans.

5 Subgrade Preparation:

-When the existing asphalt remaining is thin and not suitable for overlay operations, Contractor shall run a sheepsfoot roller on the remaining asphalt and prepare the subgrade for pavement.

-Contractor shall prepare subgrade for paving per PAG Standard Specifications for Public Improvements, 2015 Edition, Section 205. Expected preparation shall include but is not limited to grading and shaping of subgrade to allow positive drainage away from road or across drainage areas such as washes, compacting subgrade to a point that is acceptable for pavement placement, hydration of subgrade material to promote desired compaction and any other work consistent with prior to paving operations.

6 Paving:

- When there is existing asphalt remaining, Contractor shall sweep existing milled roadway where required and tack with

Certified Boot Truck using CSS1 50/50 dilute at a maximum application rate of .08 gallons/SY and tack all vertical surfaces.

Note: When the bid schedule quantities for the pavement milling and the roadway grading items are similar, the existing asphalt surface to remain is not anticipated for the project.

-Contractor shall pave new asphalt per the depth identified in the Project Treatment List.

7 Finish Work:

-Contractor shall replace all survey monumentation disturbed during work efforts in kind.

-Contractor shall replace all traffic marking/striping (paint, symbols, legends, thermoplastic, raised pavement markers) and match to standard using Pima County and City of Tucson Department of Transportation Signing and Pavement Manual, December 2020, First Edition.

SP-14

-Contractor shall replace signage impacted as part of this project.

-Contractor shall complete any other miscellaneous work necessary to deliver final paved roadway, complete and in place.

-If speed humps or speed tables are present on any roadway on the project list, contractor shall replace speed humps or speed tables that were removed during the milling process.

ID CONTRACTOR REQUIREMENTS

1 Contractor shall not leave any areas milled over a weekend and/or holiday period for any reason if not previously approved by Field Engineering.

2 Contractor shall shore up edge of pavement at all driveways, mailboxes and areas not level with new pavement within one week of completion of paving roadway/street.

3 Contractor to match improved driveways with asphalt (i.e., brick, concrete, or asphalt).

4 Contractor shall have all utility adjustments, including water, sewer, and survey, completed within 30 days of completion of paving for roadway, street or subdivision unless prior approval from Field Engineering has been obtained.

5 Contractor shall re-install speed humps or speed tables, when removed for paving operations, within 45 days of completion of paving for roadway, street or subdivision unless prior approval from Field Engineering has been obtained.

6 Contractor is not allowed to place millings on shoulder unless prior approval from Field Engineering has been obtained.

7 Chip Seal tabs shall be placed upon final asphalt placement and removed prior to thermoplastic stripe installation. Contractor is to lay out temporary striping and give the City 3 working days to review prior to installation. Temporary striping shall be installed within 7 days of final asphalt placement and must include all striping, i.e., shoulder, stop bars, pavement marking legends. Temporary stripe application rate and bead quantity shall be approved by Field Engineering.

8 Final Thermoplastic Striping shall be completed 21-30 calendar days after temporary stripe placement for roadway, street, or subdivision unless prior approval from Field Engineering. Application rate and bead quantity shall be approved by Field

Engineering.

9 Cleanup shall be completed within 10 calendar days of all utility adjustments for roadway, street, or subdivision unless prior approval from the Engineer.

8. Disposal of Material

All construction debris, rubble, excess, surplus and unsuitable materials structures and obstructions, except as hereafter specified, shall be removed from the job site and disposed of by the contractor at a site previously secured by the contractor, and done in a manner approved by the Engineer.

Disposal shall be the responsibility of the contractor. However, the contractor shall, with each and every disposal site arranged for (other than commercial waste sites), provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware of what the material consists. The contractor shall also provide a letter to the Engineer from the City or County (whichever has jurisdiction), giving site approval for materials disposal at each site to be used. The approval letter shall be received and approved by the Engineer prior to the disposal of any materials at any site.

Costs associated with the disposal of these materials shall be incidental to the related items of work. Fees associated with the disposal of these materials shall be paid by the contractor.

All material removals shall be transported and legally disposed of from the project site the same day they are removed. Stockpiling of removed materials within the public rights-of-way shall not be allowed unless previously approved and directed by the Engineer. The location of the disposal

SP-15

site shall be the responsibility of the contractor and the contractor shall identify in writing the quantity of materials removed and disposed of to that location.

Upon removal, existing material, including existing guardrail, anchors, breakaway cable terminals, posts, and hardware, shall become the property of the contractor unless otherwise specified in the project plans, or in these Special Provisions, or by the Engineer.

Upon removal, disposal of the existing asphaltic concrete shall be the responsibility of the contractor. When approved by the Engineer, the contractor may stockpile and use it as recycled asphaltic concrete or dispose of it at an approved site. No measurement or direct payment will be made for disposal. The cost of disposing the removed AC pavement shall be incidental and considered as included in the cost of contract items.

If in good condition as determined and approved by the Engineer, removal of existing fence and gate material along the project limits may be salvaged and used for reconstruction of fence and gates at necessary locations.

9. Permits

Before undertaking any of this contract work at any location covered by this project, the contractor shall obtain all applicable business licenses and permits, including but not limited to:

water quality permits, air quality permits, traffic control and street closure permits, excavation/construction in the public rights-of-way permits, storm water pollution prevention plan, and any other permits required by ordinance and/or state and federal law.

The contractor shall be pay for all necessary fees, taxes and other costs associated with obtaining and securing all permits, including plan review. The costs associated with obtaining permits shall be considered incidental and inclusive with the associated items of work. No additional compensation will be provided.

Excavation permits for excavation/construction in the public rights-of-way will not be required when the work is administered by the Agency.

No separate payment shall be made for preparation of the traffic control plans, and the costs shall be included in the overall cost of the project. The overall cost shall also include applicable plan review and permit fees.

Prior to any ground disturbing activity, the contractor shall obtain an Activity Permit from the Pima County Department of Environmental Quality. The contractor shall implement the standard specifications for dust suppression.

SP-16

10. Material Sources

No Agency designated materials source has of yet been identified for use on this project.

Contractor material sources shall be as specified in Section 1001 of the Standard Specifications.

11. Public Relations

It shall be the Contractor's responsibility to contact adjacent property owners one week prior to construction.

The Contractor shall:

1. With City guidance, prepare and distribute notification letter to affected residents and businesses. The letter shall provide information on the date and time when the work will commence, parking restrictions when conducting the work, contractor contact numbers for any additional information, and other relevant information on the project and scope of the work.

2. Message Boards shall also be utilized to notify the traveling public.

3. Post No-Parking signs (as necessary) stating actual dates & times work is to commence and restricting access to private properties.

4. Maintain access to all side streets, access roads, business, residences, driveways, alleys, and parking lots except for the period when the paving operation, sidewalk construction, or driveway construction is being conducted with required curing time.

5. Post No Lane Marking signs prior to striping activities.

Cost shall be considered incidental to project activities.

12. Construction Survey and Layout, and GPS Documentation

The Contractor shall provide GPS documentation of utilities within the pavement. The survey GPS data shall be in the most recent State Plane Coordinates (NAD 1983 State Plane Arizona, Central) and will be gathered using survey quality equipment, and accurate to within 0.5-feet.

This data will be provided to the City of Tucson. The basis of coordinates will be included. This data will be categorized by street segment and labeled with street names and supplied in either raw data in text or an Excel workbook format. The format will include coordinates in northings and eastings and each point shall contain a description of the utility appurtenance: all water & gas valves, monitor wells, sewer manholes & clean outs, communication manholes, and so forth.

These structures shall be documented by GPS methods before they are lowered. The surveying/GPS documentation of the utility appurtenances shall be considered incidental and included in the respective pre-lowering utility item. This work shall be considered incidental to the other items of construction and shall not be measured or paid separately.

The City’s surveyor will be required to cross-section the roadway prior to the treatment in order to be able to provide the contractor information to grade to.

DTM forces will perform survey for monument and project layout.

SP-17

13. Record Drawings

The contractor is responsible for keeping a set of record project plans on site for the annotation of changes in detail, location, and depth of all items constructed which vary from the contract documents that are made during the construction. LOCATION OF UTILITY POTHOLES (BID ITEMS 5150005 & 5150007) SHALL BE IDENTIFIED ON THE RECORD DRAWINGS. The record project plans shall include any revised or added plan sheets. The cost of furnishing record drawings shall be considered as included in the overall cost of the project.

Upon completion of the work, the contractor shall transfer the annotated information to a clean set of the project plans. The dimensions and notations provided on the record project plans shall be complete, clear, and legible. No later than 60 calendar days after acceptance of the project or as directed by the Engineer, the contractor shall submit the dated record set of project plans along with a transmittal letter to the Engineer for review and acceptance. Final retention shall not be released until the record project plans are accepted by the Engineer. The contractor’s failure to furnish this item may delay the contract close-out.

14. Saw Cutting

The contractor’s work shall consist of saw cutting and/or wheel cutting the existing pavement where new asphaltic concrete (AC) and Portland cement concrete pavement (PCCP) is to match existing pavement surfaces. The contractor’s work shall also include saw cutting and/or wheel cutting existing Portland cement driveways, sidewalks, and curbs where new construction shall match the grade of these existing surfaces. Saw cuts shall be made to a minimum depth of 1½ inches and in all cases, deep enough to ensure a neat vertical joint. Portland cement concrete that is damaged by the contractor’s saw cutting shall be replaced in kind at the contractor’s expense.

No measurement or direct payment will be made for saw cutting and/or wheel cutting, the cost being considered as included in the price of other contract items.

15. Existing Vegetation

Clearing limits must be approved in advance by the Engineer. Grading and construction near and around vegetation that is to be preserved-in-place may be required. The Engineer may require that specific vegetation remain within the construction limits in addition to what is shown in the project plans. The contractor and the Engineer shall tour the project site prior to any construction beginning and together verify what specific vegetation shall be preserved in place.

The contractor shall preserve in place some existing plant material in the Right-of-Way as shown on the project plans. The contractor shall prune exiting trees to remain in place and provide fencing as described in Sections 201 and 806 of these Special Provisions or as directed by the City Landscape Architect.

The contractor’s work to remove, salvage, or protect vegetation shall be in accordance with the project plans. Existing project vegetation on this project shall not be disturbed by the contractor

SP-18

beyond those limits actually needed for the contractor’s construction purposes. Those items unnecessarily damaged by the contractor shall be repaired or replaced at the contractor’s expense.

16. Contractor’s Environmental Requirements and Mitigation Measures

To prevent the introduction of invasive species seeds, all earthmoving and hauling equipment shall be washed prior to entering the construction site and the contractor shall inspect all construction equipment and remove all attached debris, including plant parts, soil, and mud, prior to the equipment entering the construction site.

To prevent invasive species seeds from leaving the site, the contractor shall inspect all construction and hauling equipment and remove all debris, including plant parts, soil, and mud, prior to leaving the construction site.

Prior to the start of construction and before ground disturbing or earthmoving activities occur, the contractor shall treat noxious and invasive vegetation, particularly buffelgrass, in accordance with Section 201-3.04. Invasive species eradication shall continue throughout the entire project from clearing and grubbing through final project acceptance.

In compliance with Executive Order 13112 regarding invasive species, all disturbed soils that will not be landscaped or otherwise permanently stabilized by construction will be seeded using species native to the project vicinity.

In compliance with Executive Order 13112 regarding invasive species, all earth-moving and hauling equipment shall be washed prior to leaving the construction site to prevent invasive species seeds from leaving the site

The Department of Transportation and Mobility Planning Administrator (520.279.5545) will provide special provisions for the control of noxious and invasive plant species during construction that may require treatment and control within the project limits.

The project mitigation measures are not subject to change without written approval from ADOT Environmental Planning. The Contractor shall follow all the requirements of the permits specified herein and comply with the project special provisions as well as the PAG Standard Specifications for Public Improvements, as well as all applicable local environmental requirements.

City of Tucson Responsibilities:

• If any active bird nests cannot be avoided by vegetation clearing or construction activities, the Engineer will contact the Department of Transportation and Mobility Planning Administrator (520.279.5545) to evaluate the situation.

SP-19

• The Department of Transportation and Mobility Planning Administrator (520.279.5545) will provide special provisions for the control of noxious and invasive plant species during construction that may require treatment and control within the project limits.

Contractor Responsibilities:

• If vegetation clearing will occur during the migratory bird breeding season (March 1– August 31), the contractor shall avoid any active bird nests. If the active nests cannot be avoided, the contractor shall notify the Engineer to evaluate the situation. During the non-breeding season (September 1–February 28) vegetation removal is not subject to this restriction.

• Prior to construction, all personnel who will be on-site, including, but not limited to, contractors, Contractors’ employees, supervisors, inspectors, and subcontractors shall review the attached Arizona Department of Transportation Environmental Planning “Western Burrowing Owl Awareness” flyer (See Appendix E).

• If any burrowing owls or active burrows are identified the contractor shall notify the Engineer immediately. No construction activities shall take place within 100 feet of any active burrow.

• If the Engineer in cooperation with the Environmental Planning Biologist determines that burrowing owls cannot be avoided, the contractor shall employ a qualified biologist holding a permit from the US Fish & Wildlife Service to relocate burrowing owls from the project area, as appropriate.

• The contractor shall develop a Noxious and Invasive Plant Species Treatment and Control Plan in accordance with the requirements in the contract documents. Plants to be controlled shall include those listed in the state and federal noxious weed and the state invasive species lists in accordance with state and federal laws and executive orders. The plan and associated treatments shall include all areas within the project right-of-way and easements as shown on the project plans. The treatment and control plan shall be submitted to the Engineer for the Department of Transportation and Mobility Professional Landscape Architect for review and approval prior to implementation by the contractor.

• Prior to the start of ground-disturbing activities and throughout the duration of construction and any landscape establishment period, the contractor shall arrange for and perform the control of noxious and invasive species in the project area.

• For milling activities, the roadway surface preceding the milling machine shall be kept sufficiently wet so as to prevent the generation of any visible fugitive dust particles, but not so wet as to cause excess runoff from the roadway surface onto the roadway shoulder.

• The contractor shall not utilize any abrasive tools or methods for the removal of the light poles that would disturb the lead-based paint. This includes, but is not limited to, sawing, grinding, sanding, or heating. Woven straps or other non-abrasive items (not linked chains) may be used to lift the light poles from their base.

SP-20

17. Archeological Features

If human remains, including human skeletal remains, cremations, and/or ceremonial objects and funerary objects are found during excavation or any activity related to construction in any part of the project area, ground disturbing activities must cease in the immediate vicinity of the discovery. Should artifacts or human remains be uncovered, the area will be taped off and the City of Tucson Engineer notified. The City of Tucson Engineer will immediately contact the City of Tucson Historic Preservation Department (520-837-6968) and arrange for the proper treatment of those resources. State laws ARS 41-865 and ARS 41-844 require that the Arizona State Museum (520-621-4795) be notified of the discovery by the contractor so that cultural groups who claim cultural or religious affinity to them can make appropriate arrangements for the repatriation and reburial of the remains. The human remains will be removed from the site by a professional archaeologist pending consultation and review by the Arizona State Museum and the concerned cultural groups.

The work is subject to delay in that location pursuant to ARS 41-844 while an examination takes place.

18. Hazardous Materials

If suspected hazardous materials are encountered during construction, work shall cease at the location and the Engineer shall be notified immediately to arrange for proper assessment, treatment, or disposal of those materials. The area will be taped off, and further investigation and clean up by the City of Tucson will follow. No adjustments will made due to work shut down. If potentially hazardous or contaminated materials are encountered, the contractor shall stop work and remove all workers within the contaminated area. For life threatening situations, follow the procedures in the Safety Plan, as specified in Subsection 107-7.02.

19. Utilities

Utility relocation work both shown and not shown on the project plans or noted in these Special Provisions will be the responsibility of the appropriate utility. All efforts have been made to avoid utility conflicts and assure as much of the utility work as possible was completed prior to the start of this project. If any relocation work is necessary due to additional conflicts, the utility companies will perform the relocation work during the project construction phases unless otherwise noted on the project plans. The contractor is hereby notified that the utility companies, in conjunction with the contract work, will perform their own utility relocation work. The contractor shall make every effort to cooperate fully with each utility company and acknowledges and agrees that delays to his operations may necessarily occur. Due to these delays that are anticipated by the utility companies, the Engineer will consider requests by the contractor for contract time extensions if necessary. The contractor will also acknowledge and agree that no monetary compensation will be given to the contractor by the Agency as a result of the impacts on the construction operations that are caused by the utility companies due to their

SP-21

anticipated work or delay. The contractor is also referred to Section 105-6 of the Standard Specifications, Cooperation With Utility Companies.

The contractor shall consider the extent of utility work in preparing the contract bid and project schedule. It will be the contractor’s responsibility, prior to bidding, to contact the appropriate utilities to obtain additional information such as relocation record drawings and/or as-builts, relocation sequencing, utility windows, construction time frames, and identification of areas requiring subgrade preparation by the contractor prior to the start of utility work.

At least two (2) working days prior to commencing excavation, the contractor shall call the Arrizon 811, between the hours of 6:00 a.m. and 5:00 p.m., Monday through Friday for information relative to the location of buried utilities. The number to call is: Tucson and Pima County 1-800-STAKE-IT.

It shall be the responsibility of the contractor to contact the utility companies in order for them to determine if there is a need for any overhead protection, bracing or shoring necessary during the construction of this project. If overhead protection, bracing or shoring is necessary, the contractor shall conduct this work to the satisfaction of the utility. No measurement or direct payment will be made for overhead protection, bracing or shoring, the cost being considered as incidental.

It shall be the responsibility of the contractor to verify and locate all existing overhead and underground utilities whether shown on the plans or not. The contractor is advised that the placement of a utility on the project plans is in no way meant to indicate its exact location.

Utility locations shown on the plans are approximate, and all utilities located within the project limits may not necessarily be shown. The absence of a utility from the plans does not necessarily indicate that it is not present.

The possibility of conflicts with existing utilities-in-service always exists. If conflicting utilities interfere with the normal progress of the contractor towards completion of this project, the Engineer may, with the prior written approval of the owner of the utility to be relocated, authorize the contractor to relocate said conflicting utilities by Force Account (see Section 515 of these Special Provisions).

The contractor shall take full responsibility of costs incurred due to damage to utilities as a result of construction, grading or excavation operations. If any utilities are damaged, the contractor shall repair or replace the damaged utility at his sole expense.

The contractor shall coordinate with affected utilities, so the utilities can notify affected customers of service interruptions. All utility relocations that were deemed necessary and were already known to have been in conflict with the project improvements have been completed. The contractor is also referred to Section 107-21 of these special provisions for more specific details.

SP-22

All discarded matter (including but not limited to trash, garbage, oil drums, fuel, ashes, equipment, concrete, and chemicals) that is generated by contractor construction activities shall be removed or disposed on a daily basis according to state and federal regulations. Contractor’s construction areas shall be maintained in a sanitary condition at all times.

Storage areas for petroleum products and other chemicals used by the contractor shall be located or protected in such a manner that any spills will not enter stream channels or impact groundwater.

20. Coordination of Residential Garbage and Recycling Services

Before undertaking work at any location covered by this project, the Contractor shall coordinate with City of Tucson Environmental Services (ES) to coordinate continuous weekly residential garbage and recycling services for the duration of construction. Damage to the pavement caused by Brush and Bulky equipment activity due to improper scheduling on the part of the contractor shall be repaired in a manner acceptable to the City at no cost to the contract.

In addition, the Contractor shall address the City of Tucson Environmental Services Brush and Bulky Material Collection in the project schedule and sequence all work, at any location covered by this project, to be complete at least one month in advance of the next bi-annual Brush and Bulky Material Collection. The Brush and Bulky Material Collection schedule is available at the following website: https://www.tucsonaz.gov/es/brush-and-bulky

21. Storm Water/Ground Water Management

It shall be the responsibility of the contractor to allow for any subsurface groundwater and storm water runoff during the time of project construction. The contractor shall not divert or impound water in such a manner as to flood adjacent homes, facilities, or roadways. No additional compensation shall be provided for dewatering or diversion structures required for constructing or protecting the work, the cost being considered incidental to the project.

Dewatering may be done by the contractor by permit only. No measurement or direct payment will be made for dewatering groundwater or channelizing surface water required during the course of construction, including all permits. A contractor’s licensed well driller is required for conducting any dewatering operation, and all costs for dewatering shall be considered incidental to the contract unit cost of the bid items requiring dewatering. The contractor shall apply to the Arizona Department of Water Resources for the Dewatering Permit in a timely manner. The contractor shall note that up to approximately 90 days may be required for the approval of the Dewatering Permit.

The contractor’s attention is also directed to Section 810 of these Special Provisions regarding the requirements for temporary and permanent erosion control.

SP-23

22. Shoring and Bracing

All contractor construction shall be conducted in conformance with the details shown on the project plans and these Special Provisions, with appropriate soil stabilization and bracing measures as previously approved by the Engineer. No measurement or direct payment will be made for shoring and/or bracing, unless shown as a line item(s) in the bidding schedule.

Contractor shoring and/or bracing is considered incidental to the cost of the other bid items.

Appropriate soil stabilization and bracing measures as previously approved by the Engineer for the protection of utilities and private facilities shall be implemented by the contractor. No measurement or direct payment will be made for contractor soil stabilization and bracing measures, it will be considered incidental to the cost of the project.

23. Contractor’s Staging or Storage Yard

No contractor’s staging area or storage yard has been identified for this project. It is the contractor’s responsibility to locate a staging area(s) and obtain approval of said area(s) from the Engineer. The contractor shall include their staging area in their SWPPP and include the staging area acreage of disturbance on their NOI. Refer to Section 106 for offsite staging outside of the right-of-way.

Identification of equipment, materials storage/stockpiling and contractor/sub-contractor parking shall be the responsibility of the contractor. The contractor shall provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware and agreeable to said equipment, materials storage/stockpiling and contractor/sub-contractor parking. This written approval is to be provided to the Engineer prior to commencement of the work.

No work shall be allowed to commence unless the conditions and requirements of this specification section is ahered to. Failure of the contractor to abide by this specification section shall be sufficient grounds for the City of Tucson to suspend work.

The contractor’s cost of the construction yard is considered incidental to the project. Appropriate locations for field offices, equipment yards, batch plants, and other construction related activities shall be the responsibility of the contractor as coordinated with and approved by the Engineer.

The contractor shall provide and maintain temporary fencing around the equipment yard and field office for the duration of the contract; the cost being incidental and considered as included in the cost of contract items.

All discarded matter (including but not limited to trash, garbage, oil drums,…