This is a Stormwater Pollution Prevention Plan (SWPPP) template document prepared for the Two Trout Creek Culvert Replacement project (WA FLAP JEFFER 134309(2)) located in Forks, Washington. The SWPPP was prepared by the Western Federal Lands Highway Division with an estimated project duration from March 2, 2026, to November 27, 2026. The project involves replacing two existing 48-inch parallel corrugated metal pipe culverts with a new box culvert at the original pre-1999 alignment on Oil City Road, along with installation of engineered log jams downstream for fish habitat protection. The site encompasses approximately 640 acres with approximately 1.0 acre of total disturbance and a maximum of 1 acre disturbed at any one time.
The SWPPP addresses compliance with the EPA's 2022 Construction General Permit (CGP, as modified in 2025) and includes comprehensive erosion and sediment control measures, pollution prevention controls, inspection and maintenance procedures, and dewatering practices. Key control measures include silt fence and fiber roll installation prior to clearing and grubbing, stabilization through turf establishment and native vegetation seeding with willow and cottonwood pole cuttings, dust control as needed, equipment fueling and maintenance at least 200 feet from wetlands, and dewatering through temporary diversion berms. The project qualifies for buffer disturbance exemptions under a CWA Section 404 permit (NWS-2025-182) due to in-water work requirements and is subject to Endangered Species Act consultation documented through USFWS Biological Opinion FWS/R1/2023-0092871. Historic property screening determined no historic properties will be affected, with concurrence from the Hoh Tribe THPO and Washington State Department of Archaeology and Historic Preservation. The document serves as a compliance template rather than a finalized operational plan, with specific contractor implementation details to be provided through detailed design specifications and supplementary contractor-submitted plans.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stormwater Pollution Prevention Plan
SWPPP
For:
Federal Highway Administration Western Federal Lands Highway Division
Tab 1
Stormwater Pollution Prevention Plan (SWPPP) Two Trout Creek Culvert Replacement i
Construction Stormwater Pollution Prevention Plan Template
To be covered under the U.S. Environmental Protection Agency�s (EPA) Construction General Permit (CGP), all construction operators are required to develop a �Stormwater Pollution Prevention Plan� (or �SWPPP�) prior to submitting a Notice of Intent (NOI) for permit coverage.
EPA created this SWPPP Template to help you develop a SWPPP that is compliant with the minimum requirements of Part 7 of EPA�s 2022 Construction General Permit (�2022 CGP�), and is customizable to your specific project and site.
Note: Permit was modified in 2025 to include coverage for Lands of Exclusive Federal Jurisdiction � Permit is found at 2022 Construction General Permit (CGP) | US EPA (Modified 2022 CGP).
Any reference in the SWPPP to the 2022 CGP, is referencing the Modified 2022 CGP.
Instructions for Using the SWPPP Template
Each section of the SWPPP Template includes instructions and space for your project and site information. Read the instructions for each section before you complete that section. Specific instructions on what information to include is indicated in each text field in blue text. Click on the blue text and the instructions will disappear once you start typing. The SWPPP Template is an editable document file so that you can easily add tables and additional text and delete unneeded or non-applicable fields. Note that some sections may require only a brief description while others may require several pages of explanation.
The following tips for using this template will help ensure that you meet the minimum permit requirements:
Read the 2022 CGP (as modified) thoroughly before you begin preparation of your SWPPP to ensure that you have a working understanding of the permit�s underlying requirements. You will also need to consult Part 9 of the permit to determine if your State or Tribe has included additional requirements that affect you.
Complete the SWPPP prior to submitting your NOI for permit coverage. This is required in Parts 1.4 and 7.1.
If you prepared a SWPPP under a previous version of EPA�s CGP, you must update your SWPPP to ensure that the 2022 CGP requirements are addressed prior to submitting your
NOI.
If there is more than one construction operator for your project, consider coordinating development of your SWPPP with the other operators.
Once EPA has provided your site with coverage under the CGP, include your NOI, your authorization email, and a copy of the CGP as attachments to the SWPPP. See Appendices B and C of the SWPPP Template.
While EPA has made every effort to ensure the accuracy of all instructions contained in the SWPPP Template, it is the permit, not the template, that determines the actual obligations of regulated construction stormwater discharges. In the event of a conflict between the SWPPP Template and any corresponding provision of the 2022 CGP, you must abide by the requirements in the permit. EPA welcomes comments on the SWPPP Template at any time and will consider those comments in any future revision of this document. You may contact EPA for CGP-related inquiries at cgp@epa.gov.
ii
For Construction Activities At:
WA FLAP JEFFER 134309(2)
Two Trout Creek Culvert Replacement
Forks, WA 98331 Insert Project/Site Telephone Number
SWPPP Prepared For:
610 E. 5th Street
Vancouver, WA 98661 Phone: 360-619-7811
Fax: 360-619-7846
SWPPP Prepared By:
610 E. 5th Street
Vancouver, WA 98661 Phone: 360-619-7811
Fax: 360-619-7846
SWPPP Preparation Date:
07/15/2025
Estimated Project Dates:
Project Start Date: 03/02/2026
Project Completion Date: 11/27/2026 iii
Contents
SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES
1.1 Operator(s) / Subcontractor(s)
1.2 Stormwater Team
SECTION 2: SITE EVALUATION, ASSESSMENT, AND PLANNING
2.1 Project/Site Information
2.2 Discharge Information
2.3 Nature of the Construction Activities
2.4 Sequence and Estimated Dates of Construction Activities
2.5 Authorized Non-Stormwater Discharges
2.6 Site Maps
SECTION 3: DOCUMENTATION OF COMPLIANCE WITH OTHER FEDERAL
REQUIREMENTS
3.1 Endangered Species Protection
3.2 Historic Property Screening Process
3.3 Safe Drinking Water Act Underground Injection Control Requirements ...18
SECTION 4: EROSION AND SEDIMENT CONTROLS AND DEWATERING PRACTICES ...19
4.1 Natural Buffers or Equivalent Sediment Controls
4.2 Perimeter Controls
4.3 Sediment Track-Out
4.4 Stockpiles or Land Clearing Debris Piles Comprised of Sediment or Soil ...24
4.5 Minimize Dust
4.6 Minimize Steep Slope Disturbances
4.7 Topsoil
4.8 Soil Compaction
4.9 Storm Drain Inlets
4.10 Constructed Site Drainage Feature
4.11 Sediment Basins or Similar Impoundments
4.12 Chemical Treatment
4.13 Dewatering Practices
4.14 Other Stormwater Controls
4.15 Site Stabilization
SECTION 5: POLLUTION PREVENTION CONTROLS
5.1 Potential Sources of Pollution
5.2 Spill Prevention and Response
5.3 Fueling and Maintenance of Equipment or Vehicles
5.4 Washing of Equipment and Vehicles
5.5 Storage, Handling, and Disposal of Building Products, Materials, and Wastes 36
5.6 Washing of Applicators and Containers used for Stucco, Paint, Concrete, Form Release Oils, Cutting Compounds, or Other Materials
5.7 Application of Fertilizers
5.8 Other Pollution Prevention Practices
iv
SECTION 6: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION
6.1 Inspection Personnel and Procedures
6.2 Corrective Action
6.3 Delegation of Authority
SECTION 7: TURBIDITY BENCHMARK MONITORING FOR DEWATERING DISCHARGES
SECTION 8: CERTIFICATION AND NOTIFICATION
SWPPP APPENDICES
SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES
1.1 Operator(s) / Subcontractor(s)
Operator(s):
Insert Company or Organization Name Insert Name Insert Address Insert City, State, Zip Code Insert Telephone Number Insert Fax/Email Insert area of control (if more than one operator at site)
[Repeat as necessary.]
Subcontractor(s):
Insert Company or Organization Name Insert Name Insert Address Insert City, State, Zip Code Insert Telephone Number Insert Fax/Email Insert area of control (if more than one operator at site)
[Repeat as necessary.]
Emergency 24-Hour Contact:
Insert Company or Organization Name Insert Name Insert Telephone Number
Instructions (see definition of �operator� at CGP Part 1.1.1):
Identify all site operators who will be engaged in construction activities at the site and the areas of the site over which each operator has control (Part 7.2.1). Indicate respective responsibilities, where appropriate. Also include the 24-hour emergency contact.
List subcontractors expected to work on-site. Notify subcontractors of stormwater requirements applicable to their work.
1.2 Stormwater Team
Instructions (see CGP Parts 6 and 7.2.2):
Identify the individuals (by name and position) that you have made part of the project�s stormwater team pursuant to CGP Part 6.1, their individual responsibilities, and which members are responsible for inspections. At a minimum the stormwater team is comprised of individuals who are responsible for the design, installation, maintenance, and/or repair of stormwater controls; the application and storage of treatment chemicals (if applicable); conducting inspections as required in CGP Part 4.1; and taking corrective actions as required in Part 5.
Each member of the stormwater team must have ready access to either an electronic or paper copy of applicable portions of the 2022 CGP and the SWPPP.
Each member of the stormwater team must understand the requirements of the 2022 CGP and their specific responsibilities with respect to those requirements, including the information in Part 6.2.
For projects that receive coverage under the 2022 CGP on or after February 17, 2023, to be considered a qualified person under Part 4.1 to conduct inspections under Part 4, you must, at a minimum, either:
Have completed the EPA construction inspection course developed for this permit and have passed the exam; or
Hold a current valid construction inspection certification or license from a program that, at a minimum, covers the following:
o Principles and practices of erosion and sediment control and pollution prevention practices at construction sites;
o Proper installation, and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites; and o Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4.
Note that if one of the following topics (e.g., installation and maintenance of pollution prevention practices) is not covered by the non-EPA training program, you may consider supplementing the training with the analogous module of the EPA course (e.g., Module 4) that covers the missing topic.
Provide copies of training certificates in Tab 12. Training/Certification Log is found in Tab 12 of the SWPPP
For projects that receive coverage under the 2022 CGP prior to February 17, 2023, any personnel conducting site inspections pursuant to Part 4 on your site must, at a minimum:
Be knowledgeable in the principles and practice of erosion and sediment controls and pollution prevention, Possess the appropriate skills and training in conditions at the construction site that could impact stormwater quality, and
Possess the appropriate skills and training in the effectiveness of any stormwater controls selected and installed to meet the requirements of this permit.
Stormwater Team Name and/or Position, and Contact Responsibilities I Have Completed
Training Required by CGP Part 6.2
I Have Read the CGP and Understand the
Applicable Requirements Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email
Insert Responsibility Yes No
Yes Date: Click here to enter a date.
Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email a date.
Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email a date.
[Insert or delete rows as necessary.]
Stormwater Team Members Who Conduct Inspections Pursuant to CGP Part 4 Name and/or Position and Contact Training(s) Received
Date Training(s)
Completed
If Training is a Non-EPA Training, Confirm that it Satisfies the Minimum
Elements of CGP Part 6.3.b Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email
Insert Title of Training Received
Date: Click here to enter a date.
Principles and practices of erosion and sediment control and pollution prevention practices at construction sites
Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites
Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4
Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email
Insert Title of Training Received
Date: Click here to enter a date.
Principles and practices of erosion and sediment control and pollution prevention practices at construction sites
Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites
Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4
Insert Name of Responsible Person Insert Position Insert Telephone Number Insert Email
Insert Title of Training Received
Date: Click here to enter a date.
Principles and practices of erosion and sediment control and pollution prevention practices at construction sites
Proper installation and maintenance of erosion and sediment controls and pollution prevention practices used at construction sites
Performance of inspections, including the proper completion of required reports and documentation, consistent with the requirements of Part 4
[Insert or delete rows as necessary.]
SECTION 2: SITE EVALUATION, ASSESSMENT, AND PLANNING
2.1 Project/Site Information
Project Name and Address
Project/Site Name: Two Trout Creek Culvert Replacement
Street/Location: Oil City Road @ MP 0.52
City: Forks
State: Washington
ZIP Code: 98331
County or Similar Government Division: Jefferson County
Project Latitude/Longitude
Latitude: 47.80364722º N
(decimal degrees)
Longitude: -124.26243333 º W (decimal degrees)
Latitude/longitude data source: Map GPS Other (please specify):
________Google Earth_______
Horizontal Reference Datum: NAD 27 NAD 83 WGS 84
Additional Site Information
Is your site located on Indian country lands, or on a property of religious or cultural significance to an Indian Tribe? Yes No
If yes, provide the name of the Indian Tribe associated with the area of Indian country (including the name of Indian reservation if applicable), or if not in Indian country, provide the name of the Indian Tribe associated with the property: Insert Text Here
Instructions (see �Project/Site Information,� Section IV of Appendix H � NOI Form and Instructions):
In this section, compile basic site information that will be helpful when you file your NOI.
2.2 Discharge Information
Does your project/site discharge stormwater into a Municipal Separate Storm Sewer System (MS4)?
Are there any waters of the U.S. within 50 feet of your project�s earth disturbances?
Yes No
Yes No
Instructions (see �Discharge Information,� Section V of Appendix H � NOI Form and Instructions):
In this section, include information relating to your site�s discharge. This information corresponds to the �Discharge Information� section of the NOI form.
List all of the stormwater points of discharge from your site. Identify each point of discharge with a unique 3-digit ID (e.g., 001, 002).
For each unique point of discharge you list, specify the name of the first receiving water that receives stormwater directly from the point of discharge and/or from the MS4 that the point of discharge discharges to. You may have multiple points of discharge that discharge to the same receiving water.
Next, specify whether any waters of the U.S. that you discharge to are listed as �impaired� as defined in Appendix A, and the pollutants causing the impairment.
Identify any Total Maximum Daily Loads (TMDL) that have been completed for any of the waters of the U.S. that you discharge to and the pollutants for which there is a TMDL.
For more information on impaired waters and TMDLs, including a list of TMDL contacts and links by State, visit https://www.epa.gov/tmdl.
Finally, indicate whether any receiving water that you discharge to is designated as a Tier 2, Tier 2.5, or Tier 3 water and if so, what the designation is (2, 2.5, or 3). A list of Tier 2, 2.5, and 3 waters located in the areas eligible for coverage under this permit can be found at https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates.
For each point of discharge, provide a point of discharge ID (a unique 3-digit ID, e.g., 001, 002), the name of the first receiving water that receives stormwater directly from the point of discharge and/or from the MS4 that the point of discharge discharges to, and the following receiving water information, if applicable:
Point of Discharge
ID
Name of receiving water that receives stormwater discharge:
Is the receiving water impaired (on the CWA 303(d) list)?
If yes, list the pollutants that are causing the impairment:
Has a TMDL been completed for this receiving waterbody?
If yes, list TMDL Name and ID:
Pollutant(s) for which there is a
TMDL:
Is this receiving water designated as a Tier 2, Tier 2.5, or Tier 3 water?
If yes, specify which Tier (2, 2.5, or 3)?
[001] Two Trout Creek
Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[002] Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[003] Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[004] Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[005] Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[006] Yes No Yes No Yes No [INSERT "Tier 2", "Tier 2.5", or "Tier 3"]
[Include additional rows or delete as necessary.]
2.3 Nature of the Construction Activities
General Description of Project Provide a general description of the nature of your construction activities, including the age or dates of past renovations for structures that are undergoing demolition:
Oil City Road is a rural, two-lane road located south of Forks, Washington in Jefferson County providing access to the Oil City Trailhead in Olympic National Park, industrial timberland and private residences. In 1999 a winter storm event, in conjunction with the existing roadway undercut by Two Trout Creek caused a culvert washout and road failure. Jefferson County installed two 48-inch parallel corrugated metal pipe (CMP) culverts and constructed a new roadway upstream of the original alignment to act as a temporary repair.
The proposed project will serve as a permanent repair and involves installing a new box culvert at the original pre-1999 alignment and then removing of the culverts and restoring the site. The project also involves installing engineered log jams downstream of the box culvert to assist in providing fish habitat and preventing further headcutting up Two Trout Creek by the Hoh River.
If you are conducting earth-disturbing activities in response to a public emergency, document the cause of the public emergency (e.g., mud slides, earthquake, extreme flooding conditions, widespread disruption in essential public services), information substantiating its occurrence (e.g., State disaster declaration or similar State or local declaration), and a description of the construction necessary to reestablish affected public services:
Insert Text Here
Business days and hours for the project: Insert Text Here
Instructions (see CGP Parts 1.2.1.c and 7.2.3):
Provide a general description of the nature of the construction activities at your site.
Describe the size of the property (in acres or length in miles if a linear construction site), the total area expected to be disturbed by the construction activities (to the nearest quarter acre or quarter mile if a linear construction site), and the maximum area expected to be disturbed at any one time.
A description of any on-site and off-site construction support activity areas covered by this permit;
Indicate the type of construction site, whether there will be certain demolition activities, and whether the predevelopment land use was for agriculture.
Provide a list and description of all pollutant-generating activities (e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations) and indicate for each activity the associated pollutants or pollutant constituents (e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels) which could be discharged in stormwater from your construction site.
Describe the construction support activities covered by this permit (see Part 1.2.1.c of the permit).
Size of Construction Site
Size of Property 640 acress
Total Area Expected to be Disturbed by Construction Activities
1.0 Acres
Maximum Area Expected to be Disturbed at Any One Time, Including On-site and Off-site Construction Support Areas
1 acre
[Repeat as necessary for individual project phases.]
Type of Construction Site (check all that apply):
Single-Family Residential Multi-Family Residential Commercial Industrial
Institutional Highway or Road Utility Other ____________________________
Will you be discharging dewatering water from your site? Yes No
If yes, will you be discharging dewatering water from a current or former Federal or State remediation site? Yes No
Pollutant-Generating Activities
List and describe all pollutant-generating activities and indicate for each activity the associated pollutants or pollutant constituents that could be discharged in stormwater from your construction site. Take into account where potential spills and leaks could occur that contribute pollutants to stormwater discharges, and any known hazardous or toxic substances, such as PCBs and asbestos, that will be disturbed during construction.
Pollutant-Generating Activity
(e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations)
Pollutants or Pollutant Constituents
(e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels)
Clearing and Grubbing Sediment
Excavation and Grading Sediment
Vehicles, equipment, fueling, storage, maintenance
Oil, grease, fuel, trash, debris, solid waste
[Include additional rows or delete as necessary.]
Construction Support Activities (only provide if applicable)
Describe any construction support activities for the project (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas):
Staging of material and equipment onsite and at adjacent park, material stockpiles may need perimeter control, stockpile coverage, and a SPCC, or hazardous material management plan, whichever is appropriate.
Contact information for construction support activity:
Insert Name Insert Telephone No.
Insert Email Insert Address And/Or Latitude/Longitude
[Repeat as necessary.]
2.4 Sequence and Estimated Dates of Construction Activities
Phase I
Insert General Discription of Phase Estimated Start Date of Construction Activities for this Phase
Insert Estimated Date
Estimated End Date of Construction Activities for this Phase
Insert Estimated Date
Instructions (see CGP Part 7.2.3):
Describe the intended construction sequence and duration of major activities.
For each portion or phase of the construction site, include the following:
Commencement and duration of construction activities, including clearing and grubbing, mass grading, demolition activities, site preparation (i.e., excavating, cutting and filling), final grading, and creation of soil and vegetation stockpiles requiring stabilization;
Temporary or permanent cessation of construction activities in each portion of the site;
Temporary or final stabilization of exposed areas for each portion of the site. The dates for stabilization must reflect the applicable deadlines to which you are subject to in Part 2.2.14; and Removal of temporary stormwater controls and construction equipment or vehicles, and cessation of any construction-related pollutant-generating activities.
The construction sequence must reflect the following requirements:
Part 2.1.3 (installation of stormwater controls); and Parts 2.2.14 (stabilization deadlines).
Estimated Date(s) of Application of Stabilization Measures for Areas of the Site Required to be Stabilized
Insert Estimated Date [Add additional dates as necessary]
Estimated Date(s) when Stormwater Controls will be Removed
Insert Estimated Date [Add additional dates as necessary]
Phase II Insert General Discription of Phase Estimated Start Date of Construction Activities for this Phase
Insert Estimated Date
Estimated End Date of Construction Activities for this Phase
Insert Estimated Date
Estimated Date(s) of Application of Stabilization Measures for Areas of the Site Required to be Stabilized
Insert Estimated Date [Add additional dates as necessary]
Estimated Date(s) when Stormwater Controls will be Removed
Insert Estimated Date [Add additional dates as necessary]
[Repeat as needed.]
2.5 Authorized Non-Stormwater Discharges
Instructions (see CGP Parts 1.2.2 and 7.2.5):
Identify all authorized non-stormwater discharges. The authorized non-stormwater discharges identified in Part 1.2.2 of the 2022 CGP include:
Discharges from emergency fire-fighting activities;
Fire hydrant flushings;
Landscape irrigation;
Waters used to wash vehicles and equipment, provided that there is no discharge of soaps, solvents, or detergents used for such purposes;
Water used to control dust;
Potable water including uncontaminated water line flushings;
External building washdown, provided soaps, solvents and detergents are not used, and external surfaces do not contain hazardous substances as defined in CGP Appendix A (e.g., paint or caulk containing polychlorinated biphenyls (PCBs));
Pavement wash waters provided spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and detergents are not used. You are prohibited from directing pavement wash waters directly into any receiving water, storm drain inlet, or constructed or natural site drainage features, unless the conveyance is connected to a sediment basin, sediment trap, or similarly effective control;
Uncontaminated air conditioning or compressor condensate;
Uncontaminated, non-turbid discharges of ground water or spring water;
Foundation or footing drains where flows are not contaminated with process materials such as solvents or contaminated ground water; and Uncontaminated construction dewatering water discharged in accordance with
Part 2.4.
List of Authorized Non-Stormwater Discharges Present at the Site
Authorized Non-Stormwater Discharge Will or May Occur at Your Site?
Discharges from emergency fire-fighting activities Yes No Fire hydrant flushings Yes No
Landscape irrigation Yes No Water used to wash vehicles and equipment Yes No Water used to control dust Yes No Potable water including uncontaminated water line flushings Yes No External building washdown (soaps/solvents are not used and external surfaces do not contain hazardous substances)
Yes No
Pavement wash waters Yes No
Uncontaminated air conditioning or compressor condensate Yes No Uncontaminated, non-turbid discharges of ground water or spring water Yes No Foundation or footing drains Yes No Uncontaminated construction dewatering water Yes No
(Note: You are required to identify the likely locations of these authorized non-stormwater discharges on your site map. See Section 2.6, below, of this SWPPP Template.)
2.6 Site Maps
Instructions (see CGP Part 7.2.4):
Attach site maps in Tabs 5 and 6 of the SWPPP Binder. For most projects, a series of site maps is necessary and recommended. The first should show the undeveloped site and its current features. An additional map or maps should be created to show the developed site or, for more complicated sites, show the major phases of development.
These maps must include the following features:
Boundaries of the property and of the locations where construction will occur, including:
Locations where earth-disturbing activities will occur, noting any phasing of construction activities and any demolition activities;
Approximate slopes before and after major grading activities. Note any areas of steep slopes, as defined in CGP Appendix A;
Locations where sediment, soil, or other construction materials will be stockpiled;
Locations of any crossings of receiving waters;
Designated points where vehicles will exit onto paved roads;
Locations of structures and other impervious surfaces upon completion of construction; and Locations of on-site and off-site construction support activity areas covered by the permit (see CGP Part 1.2.1.c).
Locations of any receiving waters, including wetlands, within your site and all receiving waters within one mile downstream of the site�s discharge point(s). Indicate which receiving waters are listed as impaired, and which are identified by your State, Tribe, or EPA as Tier 2, Tier 2.5, or Tier 3 waters.
Any areas of Federally-listed critical habitat for endangered or threatened species within the action area of the site as defined in CGP Appendix A (Helpful resources: CGP Appendix D and www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility).
Type and extent of pre-construction cover on the site (e.g., vegetative cover, forest, pasture, pavement, structures).
Drainage pattern(s) of stormwater and authorized non-stormwater before and after major grading activities.
Stormwater and authorized non-stormwater discharge locations, including:
Locations where stormwater and/or authorized non-stormwater will be discharged to storm drain inlets, including a notation of whether the inlet conveys stormwater to a sediment basin, sediment trap, or similarly effective control; and
Locations where stormwater or allowable non-stormwater will be discharged directly to receiving waters, including wetlands (i.e., not via a storm drain inlet).
Locations where turbidity benchmark monitoring will take place to comply with Part 3.3, if applicable to your site.
Locations of all potential pollutant-generating activities identified in Part 7.2.3g (note:
you should have those identified in Section 2.3 (Nature of the Construction Activities) in this SWPPP Template).
Designated areas where construction wastes that are covered by the exception in Part 2.3.3e.ii (i.e., they are not pollutant-generating) will be stored.
Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with the permit.
Locations where polymers, flocculants, or other treatment chemicals will be used and stored.
SECTION 3: DOCUMENTATION OF COMPLIANCE WITH OTHER FEDERAL REQUIREMENTS
3.1 Endangered Species Protection
Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?
Criterion A: No ESA-listed species and/or designated critical habitat present in action area. Using the process outlined in Appendix D of the CGP, you certify that ESA-listed species and designated critical habitat(s) under the jurisdiction of the USFWS or NMFS are not likely to occur in your site�s �action area� as defined in Appendix A of the CGP.
Please Note: NMFS� jurisdiction includes ESA-listed marine and estuarine species that spawn in inland rivers.
Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D (Note: reliance on State resources is not acceptable; see CGP Appendix D).
Documentation: Insert Text Here
Instructions (see CGP Parts 1.1.5, 7.2.9.a, Appendix D, and the �Endangered Species Protection� section of the Appendix H � NOI Form and Instructions as well as resources available at www.epa.gov/npdes/construction-general-permit-cgp-threatened-and-endangered-species-eligibility):
Using the instructions in Appendix D of the permit, determine which criterion listed below (A-F) applies with respect to the protection of endangered species. To make this determination, you must use information from BOTH the National Marine Fisheries Service (NMFS) and U.S. Fish and Wildlife Service (USFWS). Both the NMFS and USFWS maintain lists of Endangered Species Act-listed (ESA-listed) species and designated critical habitat. Operators must consult both when determining their eligibility.
Check only 1 box, include the required information, and provide a sound basis for supporting the criterion selected. Select the most conservative criterion that applies.
Copies of the ESA compliance documentation should be placed in Tab 16 of the
SWPPP.
Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?
Criterion B: Eligibility requirements met by another operator under the 2022 CGP. The construction site�s discharges and discharge-related activities were already addressed in another operator�s valid certification of eligibility for your �action area� under eligibility Criterion A, C, D, E, or F of the 2022 CGP and you have confirmed that no additional ESA-listed species and/or designated critical habitat under the jurisdiction of USFWS and/or NMFS not considered in the that certification may be present or located in the �action area.� To certify your eligibility under this criterion, there must be no lapse of NPDES permit coverage in the other CGP operator�s certification. By certifying eligibility under this criterion, you agree to comply with any conditions upon which the other CGP operator's certification was based. You must include in your NOI the NPDES ID from the other 2022 CGP operator�s notification of authorization under this permit and list any measures that you must comply with. If your certification is based on another 2022 CGP operator�s certification under criterion C, you must provide EPA with the relevant supporting information required of existing dischargers in Criterion C.
Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D.
Documentation: Insert Text Here
Criterion C: Discharges not likely to result in any short- or long-term adverse effects to ESA-listed species and/or designated critical habitat. ESA-listed species and/or designated critical habitat(s) under the jurisdiction of the USFWS and/or NMFS are likely to occur in or near your site�s �action area,� and you certify to EPA that your site�s discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects to ESA-listed threatened or endangered species and/or designated critical habitat. This certification may include consideration of any stormwater controls and/or management practices you will adopt to ensure that your discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects to ESA-listed species and/or designated critical habitat. To certify your eligibility under this criterion, indicate 1) the ESA-listed species and/or designated habitat located in your �action area� using the process outlined in Appendix D of this permit; 2) the distance between the site and the listed species and/or designated critical habitat in the action area (in miles); and 3) a rationale describing specifically how short- or long-term adverse effects to ESA-listed species will be avoided from the discharges and discharge-related activities. (Note: You must include a copy of your site map from your SWPPP showing the upland and in-water extent of your �action area� with your NOI.)
Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D.
Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?
Criterion D: Coordination with USFWS and/or NMFS has successfully concluded.
Coordination between you and the USFWS and/or NMFS has concluded. The coordination must have addressed the effects of your site�s discharges and discharge-related activities on ESA-listed species and/or designated critical habitat under the jurisdiction of USFWS and/or NMFS, and resulted in a written confirmation from USFWS and/or NMFS that the effects of your site�s discharges and discharge-related activities are not likely to result in any short- or long-term adverse effects. By certifying eligibility under this criterion, you agree to comply with any conditions you must meet for your site�s discharges and discharge-related activities to not likely result in any short- or long-term adverse effects. You must include copies of the correspondence with the participating agencies in your SWPPP and this NOI.
Check to confirm you have provided documentation in your SWPPP as required by
Documentation:
Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?
Criterion E: ESA Section 7 consultation has successfully concluded. Consultation between a Federal agency and the USFWS and/or NMFS under section 7 of the ESA has concluded. Consultations can be either formal or informal, and would have occurred only as a result of a separate Federal action (e.g., during application for an individual wastewater discharge permit or the issuance of a wetlands dredge and fill permit), and the consultation must have addressed the effects of your construction activity�s discharges and discharge-related activities on all ESA-listed threatened or endangered species and all designated critical habitat under the jurisdiction of each Service, as appropriate, in your action area. The result of this consultation must be either:
i. A biological opinion currently in effect that determined that the action in question (taking into account the effects of your facility�s discharges and discharge-related activities) is likely to adversely affect, but is not likely to jeopardize the continued existence of listed species or result in the destruction or adverse modification of critical habitat. The biological opinion must have included the effects of your facility�s discharges and discharge-related activities on all the listed species and designated critical habitat in your action area under the jurisdiction of each Service, as appropriate. To be eligible under (i), any reasonable and prudent measures specified in the incidental take statement must be implemented;
ii. Written concurrence (e.g., letter of concurrence) from the applicable Service(s) with a determination that your facility�s discharges and discharge-related activities are not likely to adversely affect ESA-listed species and/or designated critical habitat. The concurrence letter must have included the effects of your facility�s discharges and discharge-related activities on all the ESA-listed species and/or designated critical habitat on your species list(s) acquired from USFWS and/or NMFS as part of this worksheet.
The consultation does not warrant reinitiation under 50 CFR §402.16; or, if reinitiation of consultation is required (e.g., due to a new species listing, critical habitat designation, or new information), the Federal action agency has reinitiated the consultation and the result of the consultation is consistent with the statements above. (Note: you must include any reinitiation documentation from the Services or consulting Federal agency with your
NOI.) -
Check to confirm you have provided documentation in your SWPPP as required by
Documentation: USFWS Biological Opinion FWS/R1/2023-0092871
Eligibility Criterion Following the process outlined in Appendix D, under which criterion are you eligible for coverage under this permit?
Criterion F: Issuance of section 10 permit. Potential take is authorized through the issuance of a permit under section 10 of the ESA by the USFWS and/or NMFS, and this authorization addresses the effects of the site�s discharges and discharge-related activities on ESA-listed species and designated critical habitat. You must include copies of the correspondence between yourself and the participating agencies in your SWPPP and your NOI.
Check to confirm you have provided documentation in your SWPPP as required by CGP Appendix D.
3.2 Historic Property Screening Process
Appendix E, Step 1 Do you plan on installing any stormwater controls that require subsurface earth disturbance, including, but not limited to, any of the following stormwater controls at your site? Check all that apply below, and proceed to Appendix E, Step 2.
Dike
Berm
Catch Basin
Pond
Constructed Site Drainage Feature (e.g., ditch, trench, perimeter drain, swale, etc.)
Culvert
Channel
Other type of ground-disturbing stormwater control: Insert Specific Type of Stormwater Control
Instructions (see CGP Part 1.1.6, 7.2.9.b, Appendix E, and the �Historic Preservation� section of the Appendix H � NOI Form and Instructions):
Follow the screening process in Appendix E of the permit to determine whether your installation of subsurface earth-disturbing stormwater controls will have an effect on historic properties.
Include documentation supporting your determination of eligibility. Place copies of 106 compliance documentation in Tab 16 of the SWPPP.
To contact your applicable State historic preservation office, information is available at https://ncshpo.org/directory/
To contact your applicable Tribal historic preservation office, information is available at https://grantsdev.cr.nps.gov/THPO_Review/index.cfm
(Note: If you will not be installing any subsurface earth-disturbing stormwater controls, no further documentation is required for Section 3.2 of the Template.)
Appendix E, Step 2 If you answered yes in Step 1, have prior professional cultural resource surveys or other evaluations determined that historic properties do not exist, or have prior disturbances at the site have precluded the existence of historic properties? YES NO
If yes, no further documentation is required for Section 3.2 of the Template and you may provide the prior documentation in your SWPPP.
WA DAHP File 2023-05-03038 March 5, 2024. Hoh Tribe THPO concurred 2/13/24 with finding of "no historic properties affected by the project".
If no, proceed to Appendix E, Step 3.
Appendix E, Step 3 If you answered no in Step 2, have you determined that your installation of subsurface earth-disturbing stormwater controls will have no effect on historic properties? YES NO
If yes, provide documentation of the basis for your determination. Insert references to documents, studies, or other sources relied upon If no, proceed to Appendix E, Step 4.
Appendix E, Steps 4 and 5 If you answered no in Step 3, did the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO), or other Tribal representative (whichever applies) respond to you within 15 calendar days to indicate their views as to the likelihood that historic properties are potentially present on your site and may be impacted by the installation of stormwater controls that require subsurface earth disturbance? YES NO
If yes, describe the nature of their response:
Written indication that no historic properties will be affected by the installation of stormwater controls. WADAHP 2023-05-03038 No Historic Properties Affected
Written indication that adverse effects to historic properties from the installation of stormwater controls can be mitigated by agreed upon actions. Insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative
No agreement has been reached regarding measures to mitigate effects to historic properties from the installation of stormwater controls. Provide a description of any significant remaining disagreements regarding mitigation measures and insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative
Other: Insert copies of letters, emails, or other communication between you and the applicable SHPO, THPO, or other Tribal representative
If no, no further documentation is required for Section 3.2 of the Template.
3.3 Safe Drinking Water Act Underground Injection Control Requirements
Do you plan to install any of the following controls? Check all that apply below.
Infiltration trenches (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)
Commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults, chambers, or other devices designed to capture and infiltrate stormwater flow
Drywells, seepage pits, or improved sinkholes (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)
If yes, insert copies of letters, emails, or other communication between you and the State agency or EPA regional office.
Instructions (see CGP Part 7.2.9.c):
If you will use any of the identified controls in this section, document any contact you have had with the applicable State agency or EPA Regional Office responsible for implementing the requirements for underground injection wells in the Safe Drinking Water Act and EPA�s implementing regulations at 40 CFR Parts 144-147.
For State UIC program contacts, refer to the following EPA website:
https://www.epa.gov/uic.
SECTION 4: EROSION AND SEDIMENT CONTROLS AND DEWATERING PRACTICES
4.1 Natural Buffers or Equivalent Sediment Controls
Buffer Compliance Alternatives
Are there any receiving waters within 50 feet of your project�s earth disturbances? YES NO
(Note: If no, no further documentation is required for Section 4.1 in the SWPPP Template.
Continue to Section 4.2.)
Check the compliance alternative that you have chosen:
(i) I will provide and maintain a 50-foot undisturbed natural buffer.
(Note 1: You must show the 50-foot boundary line of the natural buffer on your site map.)
(Note 2: You must show on your site map how all discharges from your construction disturbances through the natural buffer area will first be treated by the site�s erosion and sediment controls. Also, show on the site map any velocity dissipation devices used to prevent erosion within the natural buffer area.)
(ii) I will provide and maintain an undisturbed natural buffer that is less than 50 feet and is supplemented by additional erosion and sediment controls that achieve, in
General Instructions (See CGP Parts 2.2 and 7.2.6):
Describe the erosion and sediment controls that will be implemented at your site to meet the requirements of CGP Part 2.2.
Describe any applicable stormwater control design specifications (including references to any manufacturer specifications and/or erosion and sediment control manuals/ordinances relied upon).
Describe any routine stormwater control maintenance specifications.
Describe the projected schedule for stormwater control installation/implementation.
Instructions (see CGP Parts 2.2.1 and 7.2.6.b.i, and Appendix F):
This section only applies to you if discharge to a receiving water is located within 50 feet of your site�s earth disturbances. If this is the case, consult CGP Part 2.2.1 and Appendix F for information on how to comply with the buffer requirements.
Describe the compliance alternative (CGP Part 2.2.1.a.i, ii, or iii) that you will implement to meet the buffer requirements, and include any required documentation supporting the alternative selected. For alternative 3, also include why it is infeasible for you to provide and maintain an undisturbed natural buffer of any size. For �linear construction sites� where it is infeasible to implement alternative 1, 2, or 3, also include a description of any buffer width retained and/or supplemental erosion and sediment controls installed. The compliance alternative selected must be maintained throughout the duration of permit coverage. However, if you select a different compliance alternative during your period of permit coverage, you must modify your SWPPP to reflect this change.
If you qualify for one of the exceptions in CGP Part 2.2.1.b, include documentation related to your qualification for such exceptions.
combination, the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
(Note 1: You must show the boundary line of the natural buffer on your site map.)
(Note 2: You must show on your site map how all discharges from your construction disturbances through the natural buffer area will first be treated by the site�s erosion and sediment controls. Also, show on the site map any velocity dissipation devices used to prevent erosion within the natural buffer area.)
Insert width of natural buffer to be retained Insert either of the following:
(1) The estimated sediment removal from a 50-foot buffer using applicable tables in Appendix F, Attachment 1. Include information about the buffer vegetation and soil type that predominate at your site
OR
(2) If you conducted a site-specific calculation for the estimated sediment removal of a 50-foot buffer, provide the specific removal efficiency, and information you relied upon to make your site-specific calculation
Insert description of additional erosion and sediment controls to be used in combination with natural buffer area
Insert the following information:
- (1) Specify the model or other tool used to estimate sediment load reductions from the combination of the buffer area and additional erosion and sediment controls installed at your site, and
- (2) Include the results of calculations showing that the combination of your buffer area and the additional erosion and sediment controls installed at your site will meet or exceed the sediment removal efficiency of a 50-foot buffer
(iii) It is infeasible to provide and maintain an undisturbed natural buffer of any size, therefore I will implement erosion and sediment controls that achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
The project is to replace existing (2) 48� diameter culverts. In-water work is required to construct the project, clearing and grading to access to the creek must go through the 50-foot natural buffer to access the creek and thus a 50-fooot undisturbed buffer is not possible.
Insert either one of the following:
(1) The estimated sediment removal from a 50-foot buffer using applicable tables in Appendix F, Attachment 1. Include information about the buffer vegetation and soil type that predominate at your site
OR
(2) If you conducted a site-specific calculation for the estimated sediment removal of a 50-foot buffer, provide the specific removal efficiency, and information you relied upon to make your site-specific calculation Under the 2022 Construction General Permit � Appendix F Buffer Requirements, Under Part 2.2.1 the project is exempt from the requirement of either (1) or (2) above because;
The project disturbances are exempt from the requirements Part 2.2.1 and this Appendix F Buffer Requirements: - Construction approved under a CWA Section 404 permit.
I qualify for one of the exceptions in Part 2.2.1.b. (If you have checked this box, provide information on the applicable buffer exception that applies, below.)
Buffer Exceptions Which of the following exceptions to the buffer requirements applies to your site?
There is no discharge of stormwater to waters of the U.S. through the area between the disturbed portions of the site and any waters of the U.S. located within 50 feet of your site
(Note: If this exception applies, no further documentation is required for Section 4.1 of the Template.)
No natural buffer exists due to…