Attachment_3_-_Projected_Wash_Schedule.pdf

PDF 253 KB Posted

Attached to
JBER Aircraft Wash Federal contract opportunity
Solicitation number
W91ZRU-19-R-0010
Issued by
Department of the Army Alaska Army National Guard

About this file

Attachment 3 - Project Wash Schedule

View the file

Other files for this federal contract opportunity

Other files attached to JBER Aircraft Wash, newest first.
File Type Posted
Attachment_8_-_QA_6-25-19.docx DOCX document
W91ZRU-19-R-0010_Amendment_1.pdf PDF
Attachment_5_-_Historical_Wash_Process.pdf PDF
Attachment_1_-_Past_Performance_Specific_Relevant_Contract_Reference_Sheet.pdf PDF
W91ZRU-19-R-0010.pdf PDF
Attachment_6_-_Wage_Determination.pdf PDF
Attachment_7_-_PWS_6.10.19.pdf PDF
Attachment_2_-_Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

June 2019 -----------------------------------------------------------------------------------------------------------------------> May 2023

Wash & HSC 25-May-19 19-Jun-19 16-Dec-19 13-Jun-20 10-Dec-20 8-Jun-21 5-Dec-21 3-Jun-22 30-Nov-22 29-May-23 Wash & HSC 27-Apr-19 R 2-Apr-19 29-Sep-19 27-Mar-20 23-Sep-20 22-Mar-21 18-Sep-21 17-Mar-22 13-Sep-22 12-Mar-23 Wash & HSC 23-Feb-19 W 19-Feb-19 18-Aug-19 14-Feb-20 12-Aug-20 8-Feb-21 7-Aug-21 3-Feb-22 2-Aug-22 29-Jan-23 Wash & HSC 13 Apr 19 R 19-Mar-19 15-Sep-19 13-Mar-20 9-Sep-20 8-Mar-21 4-Sep-21 3-Mar-22 30-Aug-22 26-Feb-23 Wash & HSC 11-May-19 R 23-Apr-19 20-Oct-19 17-Apr-20 14-Oct-20 12-Apr-21 9-Oct-21 7-Apr-22 4-Oct-22 2-Apr-23 Wash & HSC 23 Jan 19 R 3-Jan-19 2-Jul-19 29-Dec-19 26-Jun-20 23-Dec-20 21-Jun-21 18-Dec-21 16-Jun-22 13-Dec-22

Wash & HSC C/W 3-Jan-19 R 23-Jan-19 22-Jul-19 18-Jan-20 16-Jul-20 12-Jan-21 11-Jul-21 7-Jan-22 6-Jul-22 2-Jan-23

Wash & HSC 16 Mar 19 R 9-Jun-19 6-Dec-19 3-Jun-20 30-Nov-20 29-May-21 25-Nov-21 24-May-22 20-Nov-22 19-May-23

Contract Year

Base Year

Option Year 1

Option Year 2

Option Year 3

Total C-17 Washes

Wash 7-Apr-19 4-Oct-19 1-Apr-20 28-Sep-20 27-Mar-21 23-Sep-21 22-Mar-22 18-Sep-22 17-Mar-23 Wash 22-Mar-19 18-Sep-19 16-Mar-20 12-Sep-20 11-Mar-21 7-Sep-21 6-Mar-22 2-Sep-22 1-Mar-23 Wash 20-Apr-19 17-Oct-19 14-Apr-20 11-Oct-20 9-Apr-21 6-Oct-21 4-Apr-22 1-Oct-22 30-Mar-23 Wash 8-Jun-19 5-Dec-19 2-Jun-20 29-Nov-20 28-May-21 24-Nov-21 23-May-22 19-Nov-22 18-May-23

Contract Year Base Year

Option Year 1 Option Year 2 Option Year 3

Total HC-130 Washes

Wash 19-May-19 15-Nov-19 13-May-20 9-Nov-20 8-May-21 4-Nov-21 3-May-22 30-Oct-22 28-Apr-23 Wash 10-Feb-19 9-Aug-19 5-Feb-20 3-Aug-20 30-Jan-21 29-Jul-21 25-Jan-22 24-Jul-22 20-Jan-23 Wash 29-Mar-19 25-Sep-19 23-Mar-20 19-Sep-20 18-Mar-21 14-Sep-21 13-Mar-22 9-Sep-22 8-Mar-23 Wash 9-Feb-19 8-Aug-19 4-Feb-20 2-Aug-20 29-Jan-21 28-Jul-21 24-Jan-22 23-Jul-22 19-Jan-23 Wash 14-Apr-19 11-Oct-19 8-Apr-20 5-Oct-20 3-Apr-21 30-Sep-21 29-Mar-22 25-Sep-22 24-Mar-23

Contract Year Base Year

Option Year 1 Option Year 2 Option Year 3

Total HH-60 Washes

Wash/Lube 1-Jul-19 1-Jan-20 1-Jul-20 1-Jan-21 1-Jul-21 1-Jan-22 1-Jul-22 1-Jan-23 Wash/Lube 1-Sep-19 1-Mar-20 1-Sep-20 1-Mar-21 1-Sep-21 1-Mar-22 1-Sep-22 1-Mar-23 Wash/Lube 1-Nov-19 1-May-20 1-Nov-20 1-May-21 1-Nov-21 1-May-22 1-Nov-22 1-May-23

Total Projected Washes

01 June 2019 - 31 May 2023

CLIN 0006: E-3

Estimated Projected 4 year Aircraft Wash Schedule

OPTION CLIN 0005 : HH-60G

CLIN 0004: HC-130J

CLINS 0001 - 0003: C-17

01 June 2019 - 31 May 2023

Period of Performance 01 June 2019 - 31 May 2020 01 June 2020 - 31 May 2021 01 June 2021 - 31 May 2022 01 June 2022 - 31 May 2023

Period of Performance Total Projected Washes

01 June 2019 - 31 May 2020

01 June 2020 - 31 May 2021

Total Estimated Projected Airframe Washes between June '19 and May

'23…

01 June 2021 - 31 May 2022

01 June 2022 - 31 May 2023 17

Period of Performance 01 June 2019 - 31 May 2020 01 June 2020 - 31 May 2021 01 June 2021 - 31 May 2022 01 June 2022 - 31 May 2023

01 June 2019 - 31 May 2023

Total Projected Washes

IMPORTANT NOTE: This projected wash schedule is current as of 4-11-2019, and provided purely for information purposes, to give prospective contractors an idea on the frequency of washes. These numbers are subject to change, in accordance with the min/max quantities in the CLINs solicited in W91ZRU-19-R-0010. The number of washes are ultimately subject to the issuance of task orders.

Contract Year

Base Year

Option Year 1

Option Year 2

Option Year 3

Total E-3 Washes

***Min requirement of (2) washes/year, (6) at most***

Period of Performance Total Projected Washes

01 June 2019 - 31 May 2020 6

01 June 2020 - 31 May 2021 6

01 June 2021 - 31 May 2022

01 June 2019 - 31 May 2023 24

01 June 2022 - 31 May 2023

Workload Estimate