This document is a combined synopsis and solicitation for maintenance and repair services for a Depleted Uranium Containment Facility known as the SUPERBOX. The solicitation seeks quarterly inspection services, routine and emergency maintenance and repairs on a firm-fixed price and time-and-materials basis. The period of performance is one base year and two option years from an estimated start date of March 15, 2022 through March 14, 2025. Pricing is requested for fixed-price CLINs for inspections, optional painting services, and time-and-materials rates for labor categories involved in maintenance and repairs. The solicitation sets a response deadline of February 8, 2022 and will result in a lowest-price technically acceptable contract award with the U.S. Department of the Army Contracting Command at Aberdeen Proving Ground.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF SERVICES

BASE YEAR

Item Number

Description Estimated Quantity

Amount

0001 SUPERBOX INSPECTIONS FFP 1 Job $_______________

The contractor shall conduct quarterly inspections of the Superbox test site to include its constituent systems and components to identify routine maintenance needs, deficiencies, and recommended repair actions. All work will be in accordance with the Performance Work Statement and terms and conditions set forth in the contract.

0002 SUPERBOX MAINTENANCE & REPAIRS

T&M

1 Job

The contractor shall provide routine and emergency maintenance and repairs (M&R). This includes executing, as directed, the M&R actions identified during quarterly inspections (CLIN 0001) as well as providing emergency (unplanned) troubleshooting and repairs. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with the Performance Work Statement and terms and conditions set forth in the contract.

Labor:

Engineer :Per hour rate _______/ Est hours 70 Technician :Per hour rate _______/ Est hours 100 Fabricator :Per hour rate _______/ Est hours 100

Material Markup Cost ___________

0003 Superbox Facility Painting – Optional.

FFP.

1 Job $_______________

The contractor shall provide inspection, surface preparation, and painting of the Superbox. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with the Performance Work Statement and terms and conditions set forth in the contract.

OPTION YEAR ONE

Item Number

Description Estimated Quantity

Amount

1001 SUPERBOX INSPECTIONS FFP 1 Job $_______________ The contractor shall conduct quarterly inspections of the Superbox test site to include its constituent systems and components to identify routine maintenance needs, deficiencies, and recommended repair actions. All work will be in accordance with the Performance Work

1002 SUPERBOX MAINTENANCE & REPAIRS T&M 1 Job The contractor shall provide routine and emergency maintenance and repairs (M&R). This includes executing, as directed, the M&R actions identified during quarterly inspections (CLIN 0001) as well as providing emergency (unplanned) troubleshooting and repairs. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with the Performance Work Statement and terms and conditions set forth in the contract.

Labor:

Engineer :Per hour rate _______/ Est hours 70 Technician :Per hour rate _______/ Est hours 100

1003 Superbox Facility Painting – Optional. FFP. 1 Job $_______________ The contractor shall provide inspection, surface preparation, and painting of the Superbox. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with

OPTION YEAR TWO

Item Number

Description Estimated Quantity

Amount

2001 SUPERBOX INSPECTIONS FFP 1 Job $_______________ The contractor shall conduct quarterly inspections of the Superbox test site to include its constituent systems and components to identify routine maintenance needs, deficiencies, and recommended repair actions. All work will be in accordance with the Performance Work

2002 SUPERBOX MAINTENANCE & REPAIRS T&M 1 Job The contractor shall provide routine and emergency maintenance and repairs (M&R). This includes executing, as directed, the M&R actions identified during quarterly inspections (CLIN 0001) as well as providing emergency (unplanned) troubleshooting and repairs. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with the Performance Work Statement and terms and conditions set forth in the contract.

Labor:

Engineer :Per hour rate _______/ Est hours 70 Technician :Per hour rate _______/ Est hours 100

2003 Superbox Facility Painting – Optional. FFP. 1 Job $_______________ The contractor shall provide inspection, surface preparation, and painting of the Superbox. All labor, parts, and materials will be provided by the contractor. All work will be in accordance with