Questions_and_Answers.docx
DOCX document 13 KB Posted
- Attached to
- Office and Bathroom Trailers Federal contract opportunity
- Solicitation number
- W91WRZ-17-Q-0020
- Issued by
- Department of the Army Cyber Command
About this file
Q&A
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers.docx | DOCX document | |
| W91WRZ-17-Q-0020-0001_Solicitation.pdf | ||
| Questions_and_Answers.docx | DOCX document | |
| 44x12_trailer.jpg | JPG image | |
| MARSECDET_new_trailer.pdf | ||
| W91WRZ-17-Q-0020_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1) The spec calls out a drop ceiling to accommodate the HVAC duct work. This can done without having a drop ceiling which is costly. Can you please clarify if a drop ceiling is required?
We do not believe that the drop ceiling is required as long as the facility can be cooled. Most trailers vent from under the trailer to distribute HVAC. Thus, the dropped ceiling is not a requirement.
2) Please provide pictures of the trailers.
3) The solicitation does not have any drawings for the buildings. Can you please provide drawings? Drawing attached.