A07-W91RUS-18-R-DA89-0003.pdf

PDF 381 KB Posted

Attached to
Installation Fiber Optic Cables Federal contract opportunity
Solicitation number
W91RUS-18-R-DA89
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

Modification

View the file

Other files for this federal contract opportunity

Other files attached to Installation Fiber Optic Cables, newest first.
File Type Posted
A07-Conformed_Copy-W91RUS-18-R-DA89.pdf PDF
A07-W91RUS-18-R-DA89-0002.pdf PDF
A07-Conformed_Copy-W91RUS-18-R-DA89.pdf PDF
A07-W91RUS-18-R-DA89-0001.pdf PDF
A07-Conformed_Copy-W91RUS-18-R-DA89.pdf PDF
A07-Solicitation-W91RUS-18-R-DA89.pdf PDF
A01-CSLA-SOW-1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACC-APG

RHONDA GILL

BLDG 61801 RM 3410

PN: 520-533-5269 FAX: 520-538-6400

FORT HUACHUCA AZ 85613

0011182934

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment 03 is to:

1. Provide Answ ers to Questions Recieved. See Document Labeled Questions & Answ ers 2

2. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W91RUS18RDA89

X 9B. DATED (SEE ITEM 11)

30-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jun-2018

CODE

ACC-APG

2133 CUSHING ST.

BLDG 61801 RM 3212

FORT HUACHUCA AZ 85613

W91RUS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W91RUS

FACILITY CODECODE

EMAIL:TEL:

W91RUS18RDA89

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

QUESTIONS & ANSWERS 2

QUESTIONS – CSLA FIBER OPTICS

Q. The customer is requesting two different color cables (gray for data and Blue for voice) Yes or No?

a. Yes

Q. Will the jacks be color coded as well (gray and blue)?

Q. Do we need to quote cabinet or Relay Rack for Room 337?

a. Relay rack for hallway to room 337 as needed, If this your question.

Q. What about grounding and bonding?

a. We will ground to the green bar at the top of the rack, or find a place in the floor for grounding under the rack.

Q: During the walk it was mention that a 2 pair fiber cable be installed. Is this to mean 4 strands per drop? This is a total of 120 SC connectors (60 in the Server Room), correct? Where does the 48 strands come into play? Refer back to Q&A question 1.

a. That correct if you are using the 120 SC connectors, disregard the 48 Strands. Need the 30 drops.

Q: If new fiber is being installed back to the server room; Can we install OM3 (current standard) to the desk and provide the patch cables to match? Refer back to Q&A question 3.

a. No OM3 IS 50/125 Fiber, we want to keep it all to the existing standard with the 62/5/125 as customer requested.

Q: What will the Manufacturer of the Modular Furniture be?

a. We will not use the Modular Furniture, the Customer requested that all drop will be just above the Modular Furniture on the Walls.

b. Into the walls with sheetrock and use Raceway/Panduit on the cement walls.(facing windows outer walls)

Q: Assuming fiber and copper can route in the same patch, will separate face plates be required for the copper and fiber?

a. Different face plate.

Q: Per the site walk, CAT5 is Voice and CAT6 will be Data. Please verify. Q&A question 2 refers to Riser Rated. Is the cable Plenum or Riser rated?

a. Plenum rated cable

Q: Grounding – Observed during the site walk that no grounding is present. Should this be included in the Statement of Work?

a. Yes, we will ground on the green bar above the rack, or under the rack in the floor.

Q: During the site walk a fiber consolidation point was shown. Is this to be the termination point for the fiber optic?

a. Yes, the fiber will be termination into the rack, and hall way box and into room 337.

Q. Solicitation page 4, SOW: 30 strand FOC is not a standard strand count, please clarify requirements.

a. Disregards SOW 30 strand FOC, because of the 30 drops needed for the fiber run.

Q. Solicitation page 7, 3.1: Section 3.1 calls for MM FOC to be Riser rated, armored, with metallic strength member; while 4.2.1 calls for Plenum rated FOC with dielectric strength members. Please clarify requirements.

a. Please use plenum rated cable accordance to I3A Standard IAW NFPA 70.

Q. Solicitation page 7, 3.1: What MM FOC type is required? OM1, OM2, etc.

a. As per meeting please use OM1, 62.5/125 Multimode.

Q. Please confirm that this requirement is for OM1 (62.5/125um) fiber, as per the end user and NEC's discussion at the site visit.

Q. Are fiber, voice and NIPR patch & equipment cables required?

a. Yes, Cable, Patch Panel, etc.

Q. Will escorts be provided for the duration of the work effort?

a. Yes, the Customer will take care of that.

Q. Will this work be performed during standard business hours or after hours/nights?

a. Standard business hours, between 7:00 AM to 4:00 PM or 5:00 PM

(End of Summary of Changes)