This statement of work outlines requirements for a construction project at Arlington National Cemetery. The contractor will demolish an existing exposed aggregate concrete drive and gravel area, and install a new eight-foot wide exposed aggregate concrete sidewalk to match existing surfaces. Additional requirements include replacing an existing sidewalk, installing park benches and trash receptacles provided by the government, and protecting and stabilizing exposed soils. The contractor must develop concrete mix designs and sample slabs to match the existing sidewalk, and obtain all necessary permits, equipment, labor, and materials. The performance period is 120 calendar days. The contractor must submit plans, reports, and obtain approvals according to the specified schedule. The Army Materiel Command Mission and Installation Contracting Command at Fort Sam Houston will award a firm fixed-price contract for this work at Arlington National Cemetery.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
(SOW)
Lee Drive
Arlington National Cemetery
01 May, 2021
1. General Information
1.1 Introduction
This project is to demolish current exposed aggregate concrete drive (approximately 467 LF of 12 feet wide roadway) and install new exposed aggregate sidewalk (approximately 674 LF of 8 feet wide sidewalk) that matches the existing exposed aggregate sidewalks. By observation the concrete mix utilized natural river gravel and sand components that give the concrete a rosy-tan hue and shade. It is required that the new concrete pavement must match the existing concrete in appearance. The contractor shall develop a minimum of four concrete mix designs and pour / finish a minimum of four mock-up sample slabs adjacent to existing Lee Drive that may be observed by ANC staff to judge the adequacy and sufficiency of the new concrete appearance for suitability for use on this project. Other work requirements include replacement of a section of existing sidewalk and installation of government provided park type sitting bench and trash receptacles mounted to new a concrete pad.
1.2. Background
Replacement of the existing concrete and graveled area along Lee Drive with an exposed aggregate sidewalk will facilitate better pedestrian traffic and reduce maintenance, water ponding problems and safety concerns in this area.
1.3. Objectives
Arlington National Cemetery is our nation's most sacred shrine and the final resting place for our most revered military and civilian leaders. The Cemetery receives nearly four million visitors each year. Six thousand or more funerals are conducted yearly in addition to over two thousand other ceremonies, such as commemorations, wreath ceremonies, and head-of-state visits. These ceremonies and funerals often receive the intense focus of the press and other media. Because of
Arlington's special significance and the attention, it receives, strict adherence to these specifications is essential. Failure to meet specifications will have a negative impact on our nation’s image and will not be tolerated. The successful contractor forms a true partnership with the federal
Government to ensure those who served our nation are properly honored.
1.4. Scope of Work
The contractor shall provide all labor, supervision, supplies, equipment and transportation to construct approximately six hundred and seventy-four (674 LF) linear feet of eight (8’) feet wide roadway from the start of the existing Lee Drive exposed aggregate pavement to the National
Park Service Arlington House pavement. The contractor shall perform the following: removal of existing exposed aggregate concrete drive; removal of river gravel surfaced areas; removal of two feet of underlying subgrade materials; identifying, protecting and adjusting utility lines (within the work area) if necessary; setting elevations on the new concrete sidewalk to provide positive surface sheet flow drainage from upgrade to downslope such that no pockets or puddling remain;
site clearing; site grading; soil compaction; placement and compaction of aggregate base stone;
new concrete sidewalk (to match existing exposed aggregate concrete sidewalks); temporary and final stabilization of exposed soils.
The significant and historic nature of the Arlington Mansion and its approach has endured for many decades. It is of utmost importance that this sidewalk and associated required improvements blend in naturally to the existing site landscape. A government provided sitting park type bench and trash cans shall be anchored to new (matching sidewalk pavement mix) concrete pad.
The project area shall be graded to ensure storm water sheet flows to the adjacent turfed areas of the cemetery. The transition zone areas between the edges of the new sidewalk and existing undisturbed grass surfaced burial areas shall be gently regraded to eliminated dispersed low spots and to maintain current (downgrade) storm water sheet flow regimen. The reconstructed transition zones shall be filled with stone for a width of 2 feet from each side of the sidewalk and any remaining areas are to be sodded.
The contractor shall protect all existing site features within work area including: curved brick retaining wall, two interpretive placard stations, street signage and two existing full growth boxwoods near Sheridan Drive. Existing curved brick retaining wall at terminal end of new roadway pavement shall be protected from construction equipment. The curved brick wall is located outside the footprint of the new exposed aggregate sidewalk. Final finish may be a combination of a gravel (two feet wide) and sod placement. Removal of two existing National
Park Service (NPS) signage placards is required. The contractor shall carefully remove and safely store and reinstall these placards.
Concrete Matching Requirements- The contractor shall retain an established licensed material testing service that is normally engaged in identifying components of various types of concrete to obtain samples of existing Lee Drive concrete pavement to conduct analysis of existing concrete constituents and formulate a minimum of four new concrete mixes for this project that will replicate and match the existing Lee Drive concrete pavement. The COR will identify the location of where the existing Lee Drive concrete pavement may be sampled.
The contactor shall prepare a minimum of four mock-up test slabs utilizing the graduated concrete mix designs in order to select the mix design that most closely replicates and matches the existing concrete in hue and shade. Additional mock-ups may be required if test slabs do not meet visual test for acceptance by ANC.
Contractor shall maintain sheet flow thru the project work site areas and not concentrate the natural sheet flow nor discharge of any concentrated storm water flow unto the existing managed turf in the areas below Lee Drive.
The contractor shall demolish the existing (approximately 467 LF of 12-feet-wide and 6-inch-deep roadway) pavement, the existing grey sidewalk alongside roadway (approximately 26 LF of
4.5-feet-wide and 6-inch-thick sidewalk) and the existing bollards and chains. Replace with a new custom concrete sidewalk selected from mock-up test slabs to match the existing sidewalks
(approximately 674 LF of 8-feet-width and 6-inch-deep). Provide proper tie-ins with a new matching sidewalk path to all existing sidewalks that currently intersect Lee Drive.
The contractor shall take special precautions so as not to damage the existing paved (and newly paved) areas during the construction phase by the movement of construction and materials delivery equipment by the heavy wheel loadings (including the removal of poor subgrade soils from the project site).
The Period of Performance (PoP) shall start from the Notice to Proceed (NTP).
The period of performance shall last one hundred and twenty (120) calendar days, unless completed earlier. Performance shall commence onsite work within 72 hours of the issuance of the NTP or as coordinated with the COR.
1.6 General
1.6.1. PLACE OF PERFORMANCE
The work under the resultant contract will be performed within and around Lee Drive of
Arlington National Cemetery (ANC), Arlington, Virginia 22211.
1.6.2. Recognized Holidays
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Independence Day Christmas Day
1.6.3. Hours of Operation
The Contractor is responsible for conducting business, between the hours of 7:00 AM through 7:00
PM, Monday through Friday. Work during the night throughout the week or on weekends is possible but shall first be coordinated with the COR. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential to the success of this requirement.
1.6.4. Type of Contract
The Government intends to award a Firm Fixed Price (FFP) Contract.
1.6.5 Quality Control
The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this SOW. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which the Contractor assures them-self that their work complies with the requirement of the contract. At a minimum, the contractor shall develop quality control procedures that address the areas identified in Technical Exhibit 1, “Performance
Requirements Summary” (PRS). The contractor shall make any modifications required to the plan within seven (7) calendar days of notification; and obtain Contracting Officer approval in writing of any proposed change to their QC system. The Contractor’s QC Plan is to be submitted with the proposal.
1.6.6. Quality Assurance
The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the
Government must do to ensure that the Contractor has performed in accordance with the performance standards. The QASP defines how the performance standards will be applied, the frequency of the surveillance, and the minimum acceptable defect rate(s).
1.6.7. Quality Control Plan (QCP)
Quality Control is the responsibility of the Contractor. The Contractor is responsible for the delivery of quality services and/or supplies to the Government (see FAR 52.246-1 Contractor Inspection
Requirements). The Contractor will develop, implement and maintain an effective Quality Control
System which includes a written Quality Control Plan (QCP).
1. The Quality Control Plan (QCP) shall implement the standardized procedures and/or methodology for monitoring and documenting contract performance to ensure all contract requirements are met.
2. The Contractor’s QCP must contain a systematic approach to monitor operations in order to ensure that best practices are undertaken and adhered to ensure these services are provided to the Government.
1.6.8 The QCP, at a minimum, shall include:
1. Addressing of continuous process improvements,
2. Procedures for scheduling,
3. Conducting and documentation of any inspections,
4. Compliance with applicable codes,
5. Discrepancy identification and correction,
6. Corrective action procedures to include procedures for:
a. Addressing Government discovered non-conformances,
b. Procedures for root cause analysis to identify the root cause and root cause corrective action to prevent re-occurrence of discrepancies,
7. Procedures for trend analysis, and
8. Procedures for collecting and addressing customer feedback and/or complaints.
The Contractor shall, upon request, provide to the Government their quality control documentation.
The Contractor shall deliver the QCP to the Contracting Officer (KO) and Contracting Officer’s
Representative (COR) within five (5) days after contract award and within two (2) working days when changes are made thereafter. After acceptance of the Quality Control Plan the Contractor shall receive the Contracting Officer’s acceptance in writing of any proposed change to their QC system.
1.6.9. The KO may require the Site Manager to meet with the KO, the COR, and other Government personnel as deemed necessary. Written minutes of such meetings will be recorded by the
Government and signed by the Site Manager and the KO or COR and distributed within five (5) workdays after the meeting. The Contractor may request a meeting with the KO or COR when the
Contractor believes such a meeting is necessary. Written minutes of such meetings shall be recorded by the Contractor and signed by the Site Manager and the KO or COR and distributed within five (5) workdays after the meeting. In either case, if the Contractor does not concur with any portion of the minutes recorded by the Government or the Contractor, such non-concurrence shall be provided in writing to the KO within two (2) calendar days following receipt of the minutes.
1.7.0 Contracting Officer Representative (COR)
The COR will be Dewayne Roby, P.E., Arlington National Cemetery, 703-614-0601(office), 703-
304-5317(mobile); email: dewayne.e.roby.civ@mail.mil. The COR monitors all the technical aspects of the contract and assists with contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract:
Performs the necessary inspections in connection with contract performance. The COR maintains written and oral communications with the Contractor concerning technical aspects of the contract.
Issue written interpretations of technical requirements, including Government drawings, designs, and specifications.
Monitors the Contractor's performance and notifies both the KO and the Contractor of any deficiencies.
Co-ordinate availability of Government Furnished Property, and provide site entry of
Contractor personnel. A Letter of Designation issued to the COR, a copy of which is sent to the Contractor, which states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates.
The COR is not authorized to change any of the Terms and Conditions of the contract.
mailto:dewayne.e.roby.civ@mail.mil
1.7.1 Technical Point of Contact
Dewayne Roby, P.E., Arlington National Cemetery, 703-614-0601(office), 703-304-5317
(mobile); email: dewayne.e.roby.civ@mail.mil.
1.7.2 GOVERNMENT OBSERVATION
The Contractor shall provide access to government owned real property operated by the Contractor for observation or inspection by any government agency or individual authorized access by the KO.
Government personnel will not interfere with the Contractor’s performance.
1.7.3 Personnel
The Contractor shall provide a work force possessing the skills, knowledge, and training to perform the requirements of this contract. Personnel performing work under this Statement of Work (SOW) shall remain employees of the Contractor and will not be considered employees of the Government.
All Contractor personnel will be able to communicate fluently in English both verbally and in writing.
1.7.4. Organizational Conflict of Interest (OCI)
The Contractor and subcontractor personnel performing work under this contract may receive, gain, have access to, or participate in the development of proprietary or Source Selection Information
(e.g., cost or pricing information, budget information or analyses, specifications and/or Statement of Work (SOW), etc.) or perform evaluation services which may create a current or subsequent
Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever they become aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s Mitigation Plan will be determined to be acceptable solely at the discretion of the KO and in the event the COR unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.7.5 Identification of Contractor Employees
Uniforms are selected by the Contractor, and shall provide a uniform appearance from one (1) employee to the next including all visible outer clothing covering the head, torso, legs, and feet.
Shorts are not permitted. Appropriateness of selected uniforms is otherwise subject to review by the COR
1.7.6 Special Qualifications N/A
mailto:dewayne.e.roby.civ@mail.mil
1.7.7. N/A
1.7.8. Key Personnel
The Government considers the Site Manager / Project Manager o be Key Personnel. Key Personnel identified in the proposal shall be assigned positions as identified on the proposal. Projected replacement of Key personnel must be submitted in writing to the COR and KO for approval no more than three (3) days prior to a replacement. All key personnel shall have means of verbal communication and written communication ( by e-mail ) with the COR, as the Cemetery anticipates communication, at a minimum, twice daily. Resume or Curriculum vitae (CV) of key personnel are required as part of the response to this Government request for proposals. No substitution of or additional key personnel are allowed without prior submission of their resumes by the Contractor and approval of the new key personnel by the COR.
1.7.9 Site Manager/Project Manager
The Contractor shall provide a full-time Site Manager and an identified alternate Site Manager who shall be responsible for competent performance of the specified work. Either the Site Manager or alternate Site Manager shall be onsite during the performance of this contract. The Contractor shall designate in writing to the COR the Site Manager and an alternate who shall act for the Contractor when the Site Manager is absent. The Site Manager and/or alternate shall have full authority to act on behalf of the Contractor on all contract matters relating to daily operation of this contract. The
Contract Site Manager and alternate shall have a cellular phone to maintain communication with the COR at all times during the work hours. The Contractor shall provide the contact number to the
KO and the COR.
1.8. Contractor
The Contractor is responsible for ensuring all employees possess all required licenses for operating equipment and vehicles used in the execution of this contract. Use of any chemicals shall meet EPA guidelines and State of Virginia law for licensed applicator requirements – if applicable – and shall not be used without prior review and consent of the COR.
1.8.1 N/A
1.8.2 Data Rights
All notes, reports, sketches, photographs, drawings, specifications, estimates, calculations and other documents produced as a result of this contract shall be and remain the sole property of the
Government, and may be used on any other work at no additional compensation to the contractor.
The Contractor may retain copies of all such materials.
1.8.3 AT Level I Training
1.8.3.1 All Contractor employees, including all subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within seven (7) calendar days after contract award or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR, or to the
KO if a COR is not assigned, within seven (7) calendar days after completion of training by all the employees and Subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
1.8.4. Access and General Protection/Security Policy and Procedures
1 .8 .4 .1 The Contractor and all associated sub‐contractor employees shall provide all the information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services or
Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.8.5 N/A
1.8.6 iWATCH Training
This section concerns Contractor employees and all associated sub‐contractor with an area of performance within an Army controlled installation, facility or area. The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within sixty (60) calendar days of contract award and within thirty (30) calendar days of new employees commencing performance with the results reported to the COR NLT 90 calendar days after contract award.
For information assurance (IA)/information technology (IT) training. All contractor employees and associated sub‐contractor employees must complete the DoD Cyber Awareness Challenge
(https://ia.signal.army.mil/dodiaa/default.asp) before issuance of network access and annually thereafter.
1.8.7 Contracts that Require OPSEC Training
The Contractor shall comply with DoD Directive 5205.01, AR 530-1, and any applicable service regulation. The Contractor must comply with contractually imposed operations security requirements. If contractors have access to government information they are required to follow the same requirements for protection of sensitive, unclassified government information per Joint Ethics http://jko.jten.mil/
Regulation and Public Law. The contractor shall implement OPSEC measures as ordered by the
Director, USAASC. In addition, the contractor shall have an identified OPSEC coordinator.
Contractor personnel shall receive OPSEC awareness training within 30 days of the beginning of the contract performance. The contents of the training shall comply with AR 530-1.
1.8.8 Liability
The Contractor shall be held liable for damage or destruction of privately owned property (e.g.
privately owned vehicles), as defined in this SOW, caused by the Contractor, Contractor personnel, or representatives of the Contractor in the performance of services under this contract. The
Contractor shall take corrective action in a reasonable amount of time to repair damages or replace destroyed property.
1.8.9 Damage Reports
The Contractor shall submit a Damage Report to the KO and the COR within two (2) workdays of damage or destruction to Government property or privately owned property caused by the
Contractor, Contractor personnel, or representatives of the Contractor. The Damage Report shall detail the facts and the extent of damages or destruction, and the corrective action taken by the
Contractor to repair damages and / or replace the destroyed property.
1.9 Personnel Requirements
All personnel assigned to the project shall be required to adhere to the guidelines prescribed under the Freedom of Information Act (FOIA) and the Privacy Act. All personnel shall be fully qualified to perform the work required under this contract; any specific requirements will be listed.
1.9.1 Environmental Impact
1.9.1.1 Disposal
Any materials used such as containers, solvents, oil, grease, etc., are the property of the
Contractor and will be removed from Cemetery property and disposed of in accordance with all local, state and federal laws. The Contractor shall provide copies of the disposal tickets upon request to the COR.
1.9.1.2 The Contractor will not allow any solvents or chemicals used while performing this contract onto any roadway, drainage structure, or grassed area. If accidental spills occur, the
Contractor will notify the ANC Environmental Coordinator and will proceed to immediately clean up the area, and properly dispose of the spillage or materials in accordance with all local, state, and federal standards.
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government.
Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE. An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does
NOT have authority to change the terms and conditions of the contract.
2.1.4 DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.5 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.6 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.7 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.8 PRIVATELY OWNED PROPERTY. For the purposes of this SOW, means property ownership by a non-governmental organization (e.g. privately owned vehicles).
2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The
Government does not have privity of contract with the subcontractor.
2.1.12 UTILITY/UTILITIES. Sanitary sewer lines, storm drains, gas, electric, water, irrigation lines, and communication lines.
2.1.13 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.14 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS
AQL Acceptable Quality Level
ACOR Alternate Contracting Officer's Representative
AFARS Army Federal Acquisition Regulation Supplement
AR Army Regulation
CFR Code of Federal Regulations
CMR Contractor Management Reporting
COR Contracting Officer Representative
COTS Commercial-Off-the-Shelf
DA Department of the Army
DD250 Department of Defense Form 250 (Receiving Report)
DD254 Department of Defense Contract Security Requirement List
DFARS Defense Federal Acquisition Regulation Supplement
DOD Department of Defense
FAR Federal Acquisition Regulation
SDS Safety Data sheet
KO Contracting Officer
NACE National Association of Corrosion Engineers (NACE)
OCI Organizational Conflict of Interest
PIPO Phase In/Phase Out
POC Point of Contact
PRS Performance Requirements Summary
PWS Performance Work Statement
QA Quality Assurance
QAP Quality Assurance Program
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY (GFE), EQUIPMENT, AND SERVICES
3.1. Contractor Services
The Contractor shall provide all the labor, supervision, personnel, equipment, supplies, transportation, tools, materials, associated services, other items, and non-personal services necessary to demolish existing exposed aggregate roadway of Lee Drive and graveled area and to install an exposed aggregate sidewalk that matches the existing exposed aggregate concrete as defined in part 5 of this Statement of Work (SOW). The Contractor shall perform to the standards in this contract.
3.2 Facilities– N/A
3.3 Utilities – N/A
3.4 Equipment –N/A
3.5 Materials –Government to provide to the contractor for installation a park type sitting bench and trash receptacles (to be field located).
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1. General
The Contractor shall furnish all the supplies, equipment, and services required to perform work under this contract that are not listed under Section 3 for this requirement.
4.2 Secret Facility Clearance: N/A
4.3. Materials
The Contractor shall furnish all materials, supplies, and equipment necessary to meet the requirements under this PWS that are not listed under Section 3 for this requirement.
4.4. Equipment
The Contractor shall furnish all equipment necessary to meet the requirements under this PWS.
4.5 Cemetery Access
The Contractor shall be responsible for ensuring that all contractor personnel authorized to perform work under this contract obtain Cemetery access. Within five (5) workdays after contract award, the Contractor shall submit to the KO and the COR the names and completed JBM-HH Form 190-
16a (Request for a Joint Base Myer-Henderson Hall Installation Access Control Pass-Contractor) of ALL personnel working under this contract. Changes of the contractor personnel list shall be submitted within 24 hours of the change-taking place. All Contractor employees shall have on them, at all times, positive and valid photographic identification, and the Joint Base Myer –
Henderson Hall issued badge and / or paperwork certifying they have completed the vetting process.
4.6 Limited Background Check
The Limited Background Check is for Contractors that do not require CAC, but do require access to a DoD facility or installation. The Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center
Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army
Directive 2014-05/AR 190-13), applicable installation, facility and /or area commander installation/facility access and/or local security policies and procedures (provided by Government representative).
4.7 The Contractor shall enforce a ban on all alcohol and drugs – both their sale and usage (or the effects of their usage) by any Contractor employee. The Contractor shall adhere to the terms of
FAR 52.223-6 - Drug-Free Workplace in performance of this contract.
4.8 The Contractor shall maintain a neat and professional appearance throughout its workforce, vehicles, equipment, work sites, and staging areas.
4.9 The Contractor shall ensure all contract employees behave with appropriate decorum, courtesy, and respect while within the Cemetery or at its perimeter or entrances. Shouting, cursing, angry outbursts, sleeping, intoxication, and violence or criminal acts of any kind will not be tolerated -and is cause for immediate removal from the Cemetery and/or prosecution.
PART 5
5.0. Specific Tasks
5.1. Specifications
The contractor shall provide all labor, supervision, supplies, equipment and transportation to demolish current exposed aggregate concrete drive (approximately 468 LF of 12 feet wide roadway) and install new exposed aggregate sidewalk (approximately 674 LF of 8 feet wide sidewalk) that matches the existing exposed aggregate sidewalks. The Contractor shall perform to the standards in this contract.
5.2 Specific Tasks
Primary features for this project is the demolition of the current exposed aggregate concrete drive
(approximately 467 LF of 12-feet-wide and 6-inch-deep roadway) and installation of a new exposed aggregate sidewalk (approximately 674 LF of 8-feet-wide and 6-inch-deep sidewalk) that matches the existing exposed aggregate sidewalks. Secondary features are the demolition of a section of existing concrete sidewalk and replacement with sidewalk that matches the existing exposed aggregate sidewalk and the installation of a government furnished park type sitting bench and trash receptacles on a new matching exposed aggregate concrete pad.
Other work also includes the careful removal of two NPS signage placards located at terminal end of new road pavement to protect them from damage during construction activity, safely store and reinstall.
Due to the sensitive nature of the watershed the contractor shall take every precaution to control and contain soil erosion from the project location at all times (during construction and turf establishment period) to prevent any soil sediments escaping from the project limits into downstream areas.
All disturbed areas shall be sodded, irrigated, nurtured and maintained until accepted by the
Government.
Contractor shall identify and protect existing graves, trees, shrubs, and other site features that may be damaged by construction traffic along haul routes and within project work limits. ANC forester-arborist to be consulted prior to any activities that may damage existing cemetery trees and root systems.
Demolition activities for this project are the removal of the existing graveled section, the existing
(approximately 467 LF +/- by 12 feet +/-) section of exposed aggregate concrete roadway, existing non-matching sidewalk and any pavement or soils to be removed. Demolition activities include: Existing gravel and exposed aggregate road sections and non-matching sidewalk shall be removed along with excavated soils, man placed fill debris, and 2 feet of subgrade materials from
ANC to a commercial construction waste disposal/recycle facility by the contractor.
The Contractor shall notify the COR, ANC and Miss Utility before excavating or digging.
Digging permission (an approved digging permit) shall be obtained from ANC prior to excavation. All excavated soils and man placed fill debris will not suitable for fill placement elsewhere in this road project and shall be removed off-site from ANC to a commercial licensed disposal facility by the Contractor. No disposal areas are available on ANC property.
The Contractor shall provide a complete work plan showing the project site and full extent of impacted areas. The site is situated on a cemetery hillside which has both interspersed individual trees and areas that have clumps of trees. The areas adjacent to the Lee Drive pavement upgrade project area are grassed burial areas on both sides of the roadway. Areas of required work shall be enclosed with safety fencing and signage to keep visitors out of the work areas.
The proposed pavement upgrade project area is located along a cemetery hillside consists of a fairly level (gently ascending) gravel stone covered surface. The tendency of the natural drainage is to sheet flow down the hillside and adjacent burial area, over and through the existing gravel drive surface, and downhill through a grassed burial area into the large expanse of the cemetery bounded by Lee Drive and Sheridan Drive.
Vegetative (temporary for erosion control) ground cover and turf establishment on disturbed and bare earth areas within the project work limits shall be in accordance with ANC Standards and guidelines for turf establishment.
Work will be within close proximity of graves, monuments, possible utilities, and tree root systems. Extreme caution and proper procedures are to be performed during all demolition and construction phases of the project. The contractor will be required to protect existing gravesites, the brick wall near the NPS property, monuments, memorials, utility lines, stairways, the existing concrete roadway, trees, and other existing site features that are within close proximity to the road reconstruction area that may fall within the work limits. Special consideration for protecting trees located close to the roadway will be required. Construction in the area shall be performed after the examination and approval by the ANC Forester who shall advise the contractor of procedural requirements necessary when working in close proximity to mature tree(s) root structures.
Damage that may occur to existing grass areas within and outside the construction envelope shall be repaired by the contractor at no additional cost to the Government by preparing, placing, and maintaining new sod. The DB Contractor shall maintain and irrigate new sod during the construction period and/or until the project is accepted by the Government.
Prior to digging at ANC, the contractor will be required to receive approval from ANC. If any unknown items or objects are encountered all excavation shall cease and finding shall be reported to the COR immediately. No excavation activities shall commence until expressly permitted by the COR.
The exposed aggregate concrete mix is to match (both in texture, aggregate size and color) the existing exposed aggregate sidewalks that intersect Lee Drive. The contractor shall develop a minimum of four (4) concrete mix designs and pour/finish a minimum of four (4) mock-up sample slabs which shall measure 4-feet wide, 6-feet long, and 4-inches thick. Additional mock-ups may be required if test slabs do not meet visual test for acceptance by ANC. These mock-up slabs shall be poured/finished adjacent to the existing Lee Drive so that they may be observed by
ANC Engineering personnel to judge the adequacy and sufficiency of the new exposed aggregate concrete appearance for suitability for use on this project. The locations for the temporary placement of these slabs shall be as directed by the COR. The contractor will be required to use both protective and safety measures around the perimeter of the mock-up samples so that pedestrians will avoid the area during curing. A construction fence shall be placed around the mock-up samples to prevent pedestrians from entering the area, and the contractor shall provide personnel to watch and protect the integrity of the mock-up samples for at least two (2) hours after pouring to ensure that pedestrians will stay away from the area. After ANC Engineering personnel have selected the mock-up sample that best matches the existing Lee Drive pavement, the contractor shall remove all mock-up samples off-site except the sample that has been selected by personnel. The mock-up sample that has been selected shall remain in place until end of construction. After end of construction, the contractor shall remove the selected mock-up sample, dispose of the sample off-site, and restore the area where the mock-up samples were placed to existing condition or better. The restored area shall be approved by ANC Engineering personnel prior to departure from the site. The contractor shall retain an established, licensed materials testing service that is experienced in identifying the components of various types of exposed aggregate concrete mix designs.
The contractor shall conduct all appropriate materials tests deemed necessary by the materials testing laboratory on the existing exposed aggregate concrete sample, such as but not limited to, a constituents and components analysis, and shall formulate test designs for new exposed aggregate concrete mixes for this project that will replicate and match the existing Lee Drive concrete pavement. In order to create the proper exposed aggregate concrete mix, a sample of the existing concrete on Lee Drive may need to be collected by the contractor as deemed necessary. The COR shall identify the location of where the existing Lee Drive concrete pavement may be sampled.
The contractor shall submit a sampling and testing plan prior to collecting the existing exposed aggregate concrete sample on Lee Drive.
Prior to construction the existing stanchion post and chain fence which is located along the side of Lee Drive shall be removed by the contractor and properly disposed of at an approved landfill.
The contractor will also be required to remove two existing NPS signage placards. The contractor shall carefully remove and place the placards into a safe storage area until ANC may arrange for their transfer to the NPS.
The contractor shall use safety precautionary measures to protect pedestrians such as but not limited to installing fencing, signs, and cones, to indicate caution that construction is being performed within the project area. The contractor shall coordinate with the COR on what measures should be taken.
The contractor shall use the existing Lee Drive as an entering and exiting route during construction as directed by ANC.
The contractor shall also take into consideration the sharp turn area of the existing Lee Drive roadway. This turn area is located at the southeastern corner of the Lee House Garden. Due to the sharp turn angle in the existing roadway, large construction equipment, such as but not limited to dump trucks, may not be capable of maneuvering around the turn to reach the construction site.
The contractor shall anticipate the use of construction equipment that will be capable of maneuvering around the sharp turn to reach all areas of the construction site, and shall take preventative measures to not cause damage to the existing grass and burial areas surrounding the concrete roadway. Pavement construction planning should be based upon these parameters.
Construction of the proposed Lee Drive sidewalk will be required to start on the north end of Lee
Drive at the NPS property boundary near Arlington House. It must be emphasized that construction traffic shall not travel over the new sidewalk once it has been constructed.
Prior to initiating any structural fill placement and/or compaction operations, representative samples of the soils which will be used as structural fill or subgrade, both suitable on-site soils and off-site soils (borrow), shall be obtained and tested to determine their classification and compaction characteristics. The samples shall be carefully selected to represent the full range of soil types to be used. The moisture content, maximum dry density, optimum moisture content, grain-size and plasticity characteristics shall be determined. These tests are required to determine if the fill and subgrade soils are acceptable and for compaction quality control of the subgrades and structural fill. Tests for the above soil properties shall be in accordance with the following:
Moisture Content ASTM D 2216
Maximum Dry Density and Optimum Moisture ASTM D 1557
Grain-Size (Wash No. 200, w/o Hydrometer) ASTM D 442 and ASTM D1140
Plasticity ASTM D 4318
a. A representative number of in-place field density tests shall be performed in the subgrade of compacted on-site soils and in the structural fill and backfill to confirm that the required degree of compaction has been obtained. In-place density tests shall be performed in accordance with the sand cone method prescribed in ASTMD 1556. At least one (1) density test shall be performed for each lift of fill per 1,000 square feet, or portion thereof, of compacted existing on-site soils, subgrades, and in each lift of compacted structural fill. The density test can be performed using the nuclear test in accordance with ASTMs D 1556, D 2167, and D 6938 can be used, however one (1) sand cone test per every ten (10) tests shall be performed in accordance with ASTM D
1556.
Density tests shall be performed at 50-foot intervals along roadway subgrade soils. In addition, for utilities, a density test shall be performed for each 25 linear feet of backfill placed per foot of depth. Where other areas are compacted separately by manually operated compactors, a minimum of one (1) density test shall be performed for every 400 square feet, or portion thereof, of fill placed per foot of depth.
b. Any area that does not meet the required compaction criteria shall be reworked, and retested. If the moisture content of the soil is within the recommended range, additional compaction may be all that is necessary to increase the density. If the moisture content is not within the recommended range, then, the moisture content shall be adjusted to within the range, and the area re-compacted.
c. All laboratory and field density testing shall be performed by a commercial testing laboratory which has been found adequate and qualified by a Corps of Engineers Division Laboratory
Inspection Team.
d. Perform tests on re-compacted areas to determine conformance with specification requirements. Appoint a registered professional geotechnical engineer to certify inspections and test results. These certifications shall state that the tests and observations were performed by or under the direct supervision of the engineer and that the results are representative of the materials or conditions being certified by the tests.
Sidewalk construction requirements shall be as follows:
a. 6-inch thick expose aggregate concrete slabs, reinforced with welded wire fabric. The wire fabric shall be 6x6–W1.4xW1.4 welded wire reinforcement weighing 21 pounds per hundred 100 square feet. It shall be placed in a vertical location in the center of the 6-inch slab. The exposed aggregate concrete slabs shall use the ANC selected and approved design mix. The exposed aggregate concrete slabs shall have a minimum flexural strength of 650 psi, and a minimum compressive strength of 4,000 psi.
b. Joint spacing shall be 8-feet, and the width of each slab shall be 8-feet wide. The joints shall measure a minimum of 1.5 in depth for contraction or construction joints and 1/2-inch in width for expansion joints. The new exposed aggregate concrete mix design slabs shall have alternating expansion joints and either a contraction or a construction joint. An expansion joint shall first be placed where the new exposed aggregate concrete mix is poured at the edge of the existing concrete pavement on Lee Drive, then every 16-feet following this joint location. The joint materials shall meet the criteria as stated in UFC 3-250-01FA Pavement Design for Roads, Streets, Walks, and Open Storage Areas, and ASTM D6690-15 Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements. The joint materials used shall match the existing joints on Lee Drive as much as possible. The contractor shall provide a submittal stating the proposed sealant materials to be used in the joints of the exposed aggregate concrete slabs. The contractor shall receive approval of the sealant materials from the COR, prior to incorporating the materials.
c. 9-inches of base course consisting of VDOT 21A dense graded coarse aggregate.
d. A single layer of triaxial geogrid shall be placed in the middle of the VDOT 21A dense graded coarse aggregate layer.
e. 9-inches of base course consisting of VDOT 21A dense graded coarse aggregate.
f. Total pavement section thickness shall be 24-inches if the depth of the any utilities encountered are deeper than 24-inches. Due to the existing utilities that may be encountered, a pavement section of 24-inches may not be possible near and above the conduit if it is shallower than 24-inches. In this case the pavement section may be adjusted to accommodate the depth of the utility conduit with approval of the COR. To accommodate the shallow utilities, the pavement section may be revised so the total pavement section is at least 17-inches thick.
g. Before placing concrete, the subgrade shall be thoroughly moistened. Concrete shall then be deposited between the forms in its full course in one continuous operation. It shall then be thoroughly consolidated by means of vibrating screeds or internal vibrators, after which it shall be struck off and given the matching exposed aggregate finish. All edges and expansion joints shall be edged with 1/4 inch radius tool.
A 12-foot wide and 24-inch undercut shall be performed below the surface of the existing surface of the existing exposed aggregate and/or gravel roadway to remove all existing “pea” gravel, soils, and man placed debris so that the sidewalk section may be installed. The contractor may encounter areas containing poor quality soils, and may have difficulty meeting the compaction and proof-rolling requirements. An additional undercut of up to 12-inches may be required in some areas of the roadway that encounter poor quality soils.
It is estimated that the total linear footage of possible undercut is approximately 150 linear feet.
The volume of possible additional undercut (additional 12-inches) is approximated to be 70 cubic yards. Areas that receive the additional undercut shall be backfilled with compacted, controlled structural fill consisting of dense graded aggregate (VDOT No 21A).
The contractor shall perform a 12-foot wide and 2-foot (24-inch) deep undercut below the existing surface of the gravel roadway to remove all existing “pea” gravel, soils, and man placed debris so that the pavement section may be installed. The “pea” gravel on the surface of the roadway was encountered to vary in thickness of one to two inches. The contractor shall use caution not to damage roots from existing nearby trees which may extend beneath the limits of the roadway. Construction in the area shall be performed after the examination and approval by the ANC Forester who shall advise the Contractor of procedural requirements necessary when working in close proximity to mature tree(s) root structures.
Existing Lee Drive is devoid of all conventional storm water collection system (storm drain inlets and conduits). It is the intent of this project to maintain the same storm water (sheet flow) disposal regimen after this improvement project. Post construction storm water sheet flow will dissipate into the cemetery's expansive managed turf areas. The project will not require drainage structures and drainage conduits.
On the two feet on both sides of the sidewalk provide approximately 1-inch wash gravel stones to match coloration of sidewalk exposed aggregate to match the 6-inch depth of the sidewalks.
GENERAL:
All work involving use of tools or equipment which would interfere with any interment service conducted in the immediate vicinity of the work sites shall cease until the service has been completed.