This is Amendment 0002 to Solicitation W91QF426RA007, issued by the U.S. Army Corps of Engineers (MICC - Fort Leavenworth) on March 3, 2026, with an effective date of March 3, 2026. The amendment extends the response due date from March 11, 2026 to March 17, 2026 and updates solicitation documents and instructions. The Government intends to award two Blanket Purchase Agreements (BPAs) for asbestos abatement services at Fort Leavenworth, Kansas.

Offerors must submit proposals organized into four volumes: Volume I (RFP Documents - 1 hard copy), Volume II (Technical Capability - 3 hard copies, 25-page limit), Volume III (Past Performance - 1 hard copy), and Volume IV (Price Proposal - 1 hard copy). Technical proposals must address an Asbestos Abatement Program demonstrating compliance with UFGS 02 82 00 specifications, including qualified personnel certifications (AHERA Supervisor/Worker), quality control procedures, and third-party air monitoring processes. Offerors must also provide a narrative for a Sample Task Order execution approach and submit up to three recent (within 3 years) and relevant past performance references. The price proposal requires a firm-fixed-price for all labor, materials, and equipment for the Sample Task Order. A mandatory site visit is scheduled for Thursday, March 5, 2026 at 2:00 PM CST at Building 338, 535 Kearny Avenue, Fort Leavenworth, KS 66027-1391. Questions must be submitted to CPT Jazmin Burns (jazmin.burns.mil@army.mil) no later than Monday, March 9, 2026 at 1:00 PM CST. Hard copies must be submitted to MICC - Fort Leavenworth, Attn. CPT Jazmin Burns, 535 Kearny Avenue, Building 338, Fort Leavenworth, KS 66027-1391.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form Continuation

The following changes have been made:

INFORMATION FROM TO

Response Due Date 11 Mar 2026 17 Mar 2026

List of Contract Documents, Exhibits, or Attachments

The attachments table has changed from:

Identifi er

Document Name

Document Description Reference Identifier

Date Line Item

Page N umbers

Docum ent Type

Provid ed Under Separa te Cover

0001 Attachment

1_UFGS 02

82 00-Asbesto s_Specification s

Specification 30 Jan

56 Attach ment

No

0002 Attachment 2_ Wage Determination

Wage Determination 30 Jan

20 Attach ment

No

0003 Attachment

3_B48 ACM

tile Abatement

SOW

Statement of Work 03 Mar

Attach ment

No

To:

Identifi er

Document Name

Document Description Reference Identifier

Date Line Item

Page N umbers

Docum ent Type

Provid ed Under Separa te Cover

0001 Attachment

1_UFGS 02

82 00-Asbesto s_Specification s

Specification 30 Jan

56 Attach ment

No

0002 Attachment 2_Wage

Wage Determination 09 Mar

7 Attach ment

No

W91QF426RA0070002

Determination Kansas

0003 Attachment

3_B48 ACM

tile Abatement

SOW

Statement of Work 03 Mar

3 Attach ment

No

The following contract documents were added:

Attachment 2_Wage Determination Kansas

The following contract documents were deleted:

Attachment 2_ Wage Determination

The following contract documents Page Counts were changed:

DOCUMENT PAGE COUNTS

DOCUMENT NAME FROM TO

Attachment 2_Wage Determination Kansas none 7

Addendum to 52.212-1, Instructions to Offerors - Commercial Products and Commercial Services

Miscellaneous text in this section has been modified to:

L.2 ADDENDUM TO 52.212-1

L.2.1 General Instructions

The Government intends to award two Blanket Purchase Agreements (BPAs) from this solicitation. Proposals shall be prepared in accordance with the instructions provided herein.

Offerors are expected to examine this entire solicitation document. Failure to do so shall be at the Offeror's own risk.

L.2.2 Proposal Submission and Organization

The proposal shall be organized into four (4) separate volumes as detailed in the table below.

Proposals should be submitted in a three-ring loose-leaf binder that shall permit each volume to lie flat when open. A cover sheet shall be bound in each book, clearly marked as to volume number, title, copy number, and solicitation identification.

Vo lu m e

Title Hard Copi es

V O L I

RFP Documents (Copy of Signed Combined Synopsis- Solicitation and subsequent SF 30 Amendments issued)

V O L

II

Technical Capability 3

V O L

III

Past Performance 1

V O L

IV

Price Proposal 1

L.2.3 Proposal Formatting and Page Limitations

a. Formatting: All text shall be single-spaced and printed in black on 8 1/2" x 11" white paper.

Printing shall be easily readable (Times New Roman, 12-point font is recommended). This black-and-white requirement does not apply to graphics, photos, etc. Cross-references should be utilized to preclude unnecessary duplication of data between sections. Use at least 1-inch margins on the top and bottom and 3/4-inch side margins. All pages of each volume shall be identified with the solicitation number.

b. Page Definition: A page is defined as one side of an 8 1/2" x 11" sheet. When both sides of a sheet display printed material, it shall be counted as two pages. Fold-outs on 11"x17" sheets will be counted as two pages.

c. Page Limitations: The proposal shall not exceed the page limits identified below. If the page limits are exceeded, the pages in excess of the limit will be removed and returned, unread, to the offeror.

* Volume II - Technical Capability: 25 pages

* There are no page limitations for Volumes I, III, and IV, but offerors are cautioned to be concise and include only relevant information.

L.3 PROPOSAL CONTENT

L.3.1 Volume I - RFP Documents

Submit one (1) original signed copy of the Page 1 of the Combined Synopsis-Solicitation and any subsequent SF 30 amendments issued.

L.3.2 Volume II - Factor 1: Technical Capability Proposal

This volume shall not contain any pricing information. It shall be organized into the subfactors listed below.

Subfactor 1: Asbestos Abatement Program

The Offeror shall provide a comprehensive narrative describing its Asbestos Abatement Program. This narrative must demonstrate a thorough understanding of, and capability to comply with, the requirements outlined in Unified Facilities Guide Specifications (UFGS) 02 82 00, "Asbestos Abatement." The proposal shall, at a minimum:

1. Program Compliance: Detail how the Offeror's program meets or exceeds the specifications of UFGS 02 82 00.

2. Qualified Personnel: Identify the key personnel responsible for executing abatement procedures. For each individual, provide a summary of their specific qualifications, certifications (e.g., AHERA Supervisor, Worker), and experience in executing abatement for both Friable and Non-Friable Asbestos Containing Material (ACM).

3. Quality Control (QC): Describe the key Quality Control practices and procedures the Offeror will execute during abatement activities to ensure safety, compliance, and effectiveness.

4. Third-Party Testing: Detail the company's standard process for engaging and managing independent, third-party air monitoring and testing services to ensure project compliance and successful clearance.

Subfactor 2: Sample Task Order Execution Narrative

The Government will provide a Sample Task Order description and schedule a site visit during the solicitation period. The Offeror shall provide a narrative describing the key steps and methodologies it would employ to execute the Asbestos Abatement required by the Sample Task Order. The 3rd floor server room without servers is to be treated the same for 1st and 2nd

This narrative is not expected to be all-encompassing but should demonstrate the floor.

Offeror's technical approach, project management, and safety considerations for a representative project.

L.3.3 Volume III - Factor 2: Past Performance Proposal

The Offeror shall provide a maximum of three (3) past performance references for projects that are recent and relevant to the scope of this BPA.

Recent: A project that is ongoing or has been completed within the last three (3) years from the date of issuance of this solicitation.

Relevant: A project that is similar in scope, size, and complexity to the Asbestos Abatement services described in this solicitation. The work must have been self-performed by the Offeror.

For each project submitted, provide the following information:

1. Contracting Activity/Customer Name

2. Point of Contact Name, Title, Phone Number, and Email Address

3. Contract Number

4. Total Contract Value and Final Price (if complete)

5. Period of Performance

6. Brief description of the work, detailing its relevance to this requirement (e.g., type of ACM abated, facility type, etc.).

The Government reserves the right to obtain past performance information from any available source and may contact customers other than those identified by the Offeror.

L.3.4 Volume IV - Factor 3: Price Proposal

The Offeror shall submit a complete price proposal for the following item:

CLIN 0001 - Sample Task Order (Asbestos Abatement): Provide a firm-fixed-price for all labor, materials, and equipment required to complete the Sample Task Order described in the solicitation attachments. The price should be based on the Offeror's technical approach detailed in Volume II, Subfactor 2.

L.4. Address Submission- Hard Copies

MICC - Fort Leavenworth

Attn. CPT Jazmin Burns

535 Kearny Avenue, Bldg 338

Fort Leavenworth, KS 66027-1391

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018

52.204-16 Commercial and Government Entity Code Reporting JUL 2016

52.204-22 Alternative Line Item Proposal JAN 2017

252.215-7007 Notice of Intent to Resolicit JUN 2012

CLAUSES INCORPORATED BY FULL TEXT

52.237-1 Site Visit APR 1984

A Site Visit will be conducted on Thursday 05 March 2026 at 2:00 PM Central Standard Time at: (CST)

MICC - Fort Leavenworth

535 Kearny Avenue, Building 338

Fort Leavenworth, KS 66027-1391

Submit any questions following scheduled site visit to CPT Jazmin Burns at email (jazmin.burns.

mil@army.mil) NLT Monday 09 March 2026 at 1:00 PM Central Standard Time (CST).

Please be sure to allow for additional time to process through the Post Visitor's Center.

Point of Contact (RSVP and Directions):

CPT Jazmin Burns

Contract Specialist

Comm: 520-706-2498

(End of provision)

IDCode: J
Page: 1
Pages: 8
AmendNo: 0002
EffDate: 03 MAR 2026
ReqNo:
ProjNo:
IssCode: W91QF4
AdmCode:
IssuedBy: W6QM MICC-FT LEAVENWORTH

535 KEARNY AVENUE, BLDG 338

FORT LEAVENWORTH, KS 66027-0000

UNITED STATES

JAZMIN BURNS, EMAIL: JAZMIN.BURNS.MIL@ARMY.MIL TELEPHONE: (520) 944-3389

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W91QF426RA007
SolDate: 18 FEB 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is:

a. Update L.3.1 Volume I - RFP Documents

b. Update L.3.2 Volume II - Technical Capability Proposal

b. Add L.4. Address Submission for Hard Copies

c. Update Wage Determination Attachment to Kansas

ContNameTitle:
CoNameTitle: ROBERT M. PARVIN
ContDate:
CODate: 09 MAR 2026

File details come from the government source that posted it. Updated .