This is a Scope of Work for asbestos abatement services at Building 48, located at 731 McClellan Ave, Fort Leavenworth, Kansas 66027. The project requires removal of approximately 1,940 square feet of ACM (asbestos-containing material) tile with black mastic from six rooms and a north hallway across three floors. The contractor must submit two separate bids: one for the entire project collectively and individual bids for each room as separate projects. Room 118, 132, and the North Hallway contain two layers of non-ACM tile or linoleum overlaying the ACM tile, while Rooms 120, 314, and 313 have a single layer of non-ACM material over the ACM tile and mastic. The ACM material consists of dark brown spotted tile containing 3% Chrysotile and black mastic containing 5% Chrysotile.

The contractor must remove all materials to the concrete subfloor and completely eliminate all mastic residue down to the concrete foundation, while being cautious of floor cracks to prevent mastic solvent from leaking into the basement. Any areas inaccessible due to permanent fixtures such as countertops, cabinets, or servers must leave underlying tile in place. Full regulated area containment is required, with daily air monitoring conducted outside the regulated area throughout the project duration while the remainder of the building remains occupied. Upon project completion, the contractor must obtain air clearance for the regulated area and coordinate with the Fort Leavenworth Asbestos Manager for inspection before containment removal. All employees handling asbestos must possess state licenses and certifications. The contractor must provide copies of all air test monitoring results and waste manifest/disposal weights to Fort Leavenworth DPW Environmental personnel. The project includes complete cleaning of all abatement residue and materials, with furniture and stored objects to be removed prior to contractor arrival.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work for Building 48

• Removal of approximately 1,940 sq ft ACM tile with black mastic from Building 48. Two bids for this project are required, collectively as one single project and separately for each room as individual projects. Refer to the follow slide for rooms and square footage. RM 118, 132, and North Hallway have 2 layers of non-ACM tile or linoleum overlaying the ACM tile. RMs 120, 314, & 313 have a single layer of non-ACM tile overlaying the ACM tile & mastic.

• Any areas blocked from accessing ACM tile is to leave the tile beneath in place, for example:

countertops/cabinets in the kitchen, servers in the communications room, etc.

• Full regulated area containment is required.

• Daily Air monitoring outside regulated area throughout project or projects. The rest of the building will be occupied throughout the abatement.

• Air Clearance for regulated area upon completion of the work.

• Fort Leavenworth Asbestos Manager or representative will inspect work areas after Air Clearance and prior to tear down of containment to address any further abatement concerns.

• A copy of all air test monitoring results must be provided to Fort Leavenworth DPW Environmental personnel.

• A copy of all waste manifest/disposal weights must be provided to Fort Leavenworth DPW

Environmental personnel.

731 McClellan Ave, Fort Leavenworth, KS 66027

N

4’ 3”

1. Refer to the highlighted areas. Remove all the materials to the concrete subfloor, to include the dark brown tile (spotted) with black mastic.

The spotted, dark brown tile was 3% & Mastic was 5% Chrysotile.

2. Completely remove all mastic from beneath the base layer, down to the concrete foundation. Watch for any cracking in the floor to prevent mastic solvent from leaking into the basement area.

3. All tile layers or linoleum covering the brown tile with spots are non-ACM.

4. Ensure all state and federal laws concern asbestos removal are followed. All employes handling asbestos are must have state licenses/certifications.

5. Area shall be completely cleaned of all abatement residue and/or materials.

Note: furniture and other stored objects (shelves, JC supplies, etc.) will be removed from the work area prior to contractor arrival.

RM Floor SQ FT 118 1 147 120 1 230 132 1 266

North Hallway 1 567 214 2 365

313 3 365 RM 120

6’RM 118

22’

Kitchen

1st Floor

RM

2st Floor

RM 214

RM 314

3rd Floor

Building 48

Example of ACM brown tile with spots Hallway looking North RM 214 (RM 313 looks similar)

Slide 1: Scope of Work for Building 48
Slide 2