AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Adjust the submission deadline for proposals to 7 July 2021; and
2. Incorporate Questions and Answ ers dated 22 June 2021 into Section J as an attachment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 16
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jun-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W91CRB21R0033
X 9B. DATED (SEE ITEM 11)
25-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jun-2021
CODE
ACC - APG - W91CRB
BLDG 4310
6515 INTEGRITY COURT
ABERDEEN PROVING GROUND MD 21005-3013
W91CRB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91CRB21R0033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been modified:
CONTRACT DETAILS
CONTRACT TYPE:
a. This requirement is a 100% small business set aside.
b. The basic contract is a firm, fixed price (FFP) indefinite delivery, indefinite quantity (IDIQ)-type contract with an ordering period of five (5) years or sixty (60) months, in accordance with Federal Acquisition Regulations (FAR) 16.505.
c. The Government intends to award up to two (2) firm fixed price (FFP), Indefinite Delivery, Indefinite Quantity (IDIQ) contracts. The Government will issue all delivery orders IAW the fair opportunity procedures within Federal Acquisition Regulation (FAR) 16.505.
CONTRACT MINIMUM: Per the shoot pack Purchase Description (AR/PD 11-01C), each awardee will submit sixty-eight (68) Pathfinder S shoot packs and forty-five (45) MSV-B-100 shoot packs for FAT. After FAT approval, each vendor will produce one (1) Lot of twelve hundred (1,200) Pathfinder S shoot packs.
The Contractor shall deliver the contract’s minimum number of end item articles within the following timelines:
a. Deliver the Pre-First Article Test (FAT) Deliverable, also known as the Design Package, (CLIN 0001) NLT twenty-one (21) calendar days after award of Delivery Order IAW the
SOW.
b. Deliver FAT samples (CLIN 0002) NLT forty-five (45) calendar days after award of Delivery Order IAW with the SOW.
c. Deliver 1st Lot (CLIN 0003) NLT forty five (45) calendar days after First Article Test
Approval IAW the SOW.
The Government reserves the right to award only the contract minimum for each awarded contract resulting from this solicitation.
CONTRACT MAXIMUM: The Government may place additional delivery orders for a maximum of up to seventy-one thousand six hundred forty-one (71,641) Pathfinder S shoot packs and eighty thousand one hundred thirty-two (80,132) MSV-B-100 shoot packs.
Each production lot shall contain no more than three thousand two hundred (3,200) finished end items.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
LIST OF ATTACHMENTS
Attachment # Description Document Title 0001 Purchase Description AR/PD 11-01C, dated 22 January 2021 0002 Exhibit 1 Form 1 Engineering Change Request Form 0003 Exhibit 2 Production Readiness Review Audit Form 0004 Exhibit 3 Form 11 ISO 9001 – 2015 Crosswalk Matrix 0005 Exhibit 4 Corrective Action Report Form 0006 Exhibit 5 Form 15 Process Control Plan Template 0007 Shipping Instructions Peckham General Vendor Shipping Instructions 0008 Access Request Request for Access to Limited Distribution Materials 0009 Questions & Answers Questions and Answers dated 10 June 2021 0010 Questionnaire Past Performance Questionnaire 0011 Questions & Answers Questions and Answers dated 22 June 2021
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
PROPOSAL SUBMISSION
1. PROPOSAL SUBMISSION REQUIREMENTS
a. Each volume shall be submitted electronically via email. Offerors shall deliver the written portion of the proposals electronically to the Contract Specialist, Hilary Shaw at hilary.shaw.civ@mail.mil and Contracting Officer, Kelly Griffin at kelly.l.griffin11.civ@mail.mil. Offerors shall ensure that all delivered files are the required type as specified herein AND are compatible and openable by either any Microsoft Office software that is version 2016 and later OR by any Adobe Acrobat Versions greater than or equal to XI. If files are too large to email, vendors are to use the DoD SAFE site (https://safe.apps.mil/) for sending these large files. Any portion of the proposal that is changed (as a result of negotiations or proposal revisions) should be annotated and dated. Each volume shall be clearly labeled with its appropriate title. The Offeror’s proposal must be divided into six (6) volumes.
Subparagraph f. lists the title for each volume and specifies the page limit and number of digital copies required for each volume. Questions are due NLT 12:00 pm EST on 17 June 2021. Proposals are due NLT 2:00 pm EST 7 July 2021.
b. Each paragraph should be single spaced, and shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Tables and illustrations may use a reduced font size no less than 8-point and may be produced in landscape mode.
c. Offerors SHALL NOT include any pricing information in any section of their proposal except for Volume II: Price, Volume VI: Offer, and Shoot Pack Price Matrix.
d. Proposals shall remain valid for a period of one hundred eighty (180) days from the closing date of the solicitation.
e. The Government advises Offerors to submit any questions for clarification or explanation to the ACC-APG Point of Contact (POC) provided for the solicitation on the Contract Opportunities (https://beta.sam.gov) website.
f. Table 1 provides the volumes of material that shall be submitted
Table 1: Proposal Volumes
Proposal Volume
Title Digital Copies Maximum Pages
I Technical
*Table of contents and test data do not count towards page count
II Price 1 No page limit
III Past Performance 1
See Section (iii) Past Performance Below
IV Small Business Participation 1 No page limit
V Quality Assurance 1 No page limit
VI
Solicitation, Offer and Award Documents, and Certifications and/or Representations
1 No page limit
g. Offerors shall ship hardware samples, Production Demonstration Models
(PDM), to:
PM SPE
10170 Beach Road, Bldg. 325T Fort Belvoir, VA 22060 Attn:
Ms. Patricia Gogats
RFP Number: W91CRB-21-R-0033 Submission Date and Time:
(required) Offerors Name:
(required)
h. Offerors shall comply with all instructions. The Government will consider how well Offerors complied with these instructions when evaluating capabilities to perform the prospective contract. Each Offeror shall submit a single, complete proposal that contains the Offeror’s best terms. If the Offeror fails to adhere to these instructions, the Government may reject the offer without evaluation or consideration for award. The Government cautions Offerors that "parroting" of the technical requirements or the Statement of Work (SOW) with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform and may be considered unacceptable. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal.
NOTE: The Government will not evaluate pages that exceed the required page limitations. The Government will remove and will not include any additional pages over the maximum allowed during the evaluation.
2. PROPOSAL FILES
a. Format. The submission shall be clearly indexed and logically assembled.
Each volume shall be clearly identified and begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number (W91CRB-21-R0033) in any combination of the header or footer. Each volume shall contain a Table of Contents similar to the structure generated when using the Table of Contents feature in Microsoft (MS) Word.
Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge – Header, Footer 0.5”
Page Size, Width - 8.5” Page Size, Height – 11” The following additional restrictions apply:
b. File Packaging. All of the proposal files shall either be compressed (zipped) into one file titled “Proposal Zip” or delivered as separate files in their native format, e.g., .doc, .xls, .ppt, and so forth. Compressed (zipped) files shall be decompressible using the default decompression tools built into Windows 10. The Government will not evaluate compressed (zipped) files that cannot be opened by Windows 10 without the use of special software. All proposal files shall be in read-only format, and the preference is for all delivered files (except those containing cost or price) to be in a published Adobe Reader format openable by Adobe Acrobat Versions greater than or equal to XI. All price breakdown information to aide in the cost or price evaluation shall be submitted in a spreadsheet format that is openable by any Microsoft Office Excel version 2016 or newer. ** Please note – Self-extracting .exe files are not acceptable.
c. Content Requirement. All information shall be confined to the appropriate file.
The Offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each file of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion. The Summary Section shall contain a brief abstract of the file. Proprietary information shall be clearly marked. The following shall be included in the Narrative discussion:
(i) VOLUME I – TECHNICAL (Factor 1). Offerors shall name the file as follows:
C03_AbbreviatedCompanyName_Technical_SP_21R0033
Note: The Offeror SHALL NOT include any pricing information in this volume.
Offerors shall submit:
1. Product Demonstration Models (PDMs): The Offeror shall submit the following PDM sample hardware:
• Five (5) complete Pathfinder S Shoot Packs representative of the Pathfinder S TDP; and
• Five (5) complete MSVB100 Shoot Packs representative of the
MSVB100 TDP
The Government will use the PDMs to assess the technical capabilities of the Offeror’s proposed Shoot
Packs through inspection to ensure a standardized, repeatable production process and quality workmanship. The Offeror shall ensure that the PDMs fully demonstrate all technical capabilities and potential to meet Shoot Pack requirements. PDMs will not be returned. The Offeror will provide information to substantiate the following:
• KEY POINT #1: Technical Design Package (TDP) adherence;
• KEY POINT #2: Purchase Description (PD) adherence; and
• KEY POINT #3: Shoot Pack pocket and panel cover design compliance
2. Technical Narrative: Offerors must submit a Technical Narrative that clearly addresses the following:
• Compliance with the Buy American and Berry Amendment provisions for their submitted product;
• Processes the manufacturer plans use to ensure a standardized, repeatable construction, and quality workmanship;
• All manufacturing considerations including assembly line layout; equipment list; production, test, inspection, assembly, packaging, and shipping process;
supply chain management and long lead time items; and
• Proposed production schedule for maximum production quantities.
(ii) VOLUME II – PRICE (Factor 2). The Offeror shall name the files as follows:
C03_Abbreviated Company Name_Price Narr_SP_21R0033 (Price volume);
and C03_Abbreviated Company Name_PS_Price Matrix_21R0033 (Pricing evaluation matrix). This narrative volume shall be organized to include the following data:
(1) Electronic Copy. Files shall not be password protected. Electronic links are only permissible within the Cost Volume. If files contain links, the links must be intact and maintained through all revisions. The Offeror shall not include pivot tables in Excel spreadsheets. The Offeror shall provide a completed Section B Supplies or Services and Prices and shall complete a signed SF33 with the proposal, and acknowledgment of any amendment that may have been issued against the solicitation.
(2) Compliance. Failure to comply with the RFP requirements for Cost information may result in an adverse assessment of an Offeror’s proposal and reduce or eliminate its chance of being selected for award. Offerors shall ensure that the information presented in this volume is consistent and correlates with the information contained in the other proposal volumes. In addition, the Offeror shall ensure that the information submitted in this volume is consistent with and fully supports the amounts set forth in the SF33 and continuation sheets.
(3) General Instructions. Based on market research, the Government anticipates adequate competition in response to this solicitation; therefore, IAW FAR 15.402 and 15.403-1, certified cost or pricing data are not required because adequate competition is expected for this procurement. Information other than certified cost or pricing data may be provided in contractor format providing that sufficient information is made available. Information submitted shall be prepared following the instruction in FAR 15.403-5. If after receipt of proposals the Contracting Officer determines that there is insufficient information available to determine price reasonableness and none of the exceptions at FAR 15.403-1 apply, the Offeror may be required to submit cost or pricing data. There are no page limitations for this volume. Proposal information included in this volume, which is not directly related to Price, will be disregarded.
(iii) VOLUME III – PAST PERFORMANCE (Factor 3). This volume shall contain past performance information regarding similar contracts. This volume shall not exceed twentyfive (25) pages plus five (5) pages for each major subcontractor, excluding Past Performance Questionnaire Forms. For the purposes of this SSP and Requirement, major subcontractors are defined as members of an Offeror’s overall team who are expected to perform 25 percent or more of the proposed effort. Offerors shall submit information for all Government and all commercial contracts for the prime Offeror and each major subcontractor in performance or awarded during the past three (3) years, from the issue date of this RFP, which are relevant to the efforts required by this solicitation. Relevant efforts are defined as services or efforts that are the same as or similar (i.e. manufacturing of uniforms or individual protective equipment, with comparable production quantities and contract cost) to the effort required by the RFP. If the Prime Offeror and/or major subcontract(s) do not possess past performance experience, that is both recent and relevant to the present effort, this shall be clearly stated in the proposal. Data concerning the Offeror shall be provided first, followed by each proposed major subcontractor, in alphabetical order. The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s past performance information to the Offeror.
In addition, letters of commitment shall be included for all major subcontractors for their past performance to be considered. This volume shall be organized into the following sections:
The Offeror shall name this file as follows: C03_Abbreviated Company Name_Past Perf_SP_21R0033
• The Offeror shall submit a narrative containing their own past performance information for all recent, relevant contracts performed as either a prime contractor or major subcontractor.
o Recent: The Offeror shall submit references for three (3) recent contracts performed within the last three (3) years (to include the current year).
o Relevant: Contract references shall be for relevant contracts, meaning those contracts for which the same or similar scope (types of work, i.e. government protective garment manufacturing) and magnitude (i.e. cost and production quantities) of effort and complexities, to those required of the current solicitation were performed.
o The information gathering process may include telephone interviews, questionnaires, sent to all POCs listed in the Offeror’s proposal, and review of Contractor Past Performance Retrieval System (CPARS).
• The Government advises Offerors that:
o The Government may utilize past performance information from sources other than those identified by the Offeror. Further, if an Offeror’s firm is divided into severable segments, the Government will only evaluate the past performance of those segments of the firm that actually will perform the work.
o The Government reserves the right to not obtain information on all of the listed contract references and may not contact all of the identified POCs.
Therefore, it is incumbent upon the Offeror to explain the relevance of any data provided in the proposal.
o While information may be submitted for relevant efforts performed under subcontracts, the Government may be unable to obtain any qualitative information due to the government's lack of privity with subcontractors.
The Offeror shall also include the following in the narrative description for each contract reference:
(1) Section 1 – Contract Descriptions. This section, which covers Federal
Government contracts, shall include the following information in the following format. For all other contracts, including state and local government contracts and commercial contracts, submit similar information, as applicable.
(a) Contractor and Subcontractor place of performance, CAGE Code and DUNS Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, and current address, e-mail address, and telephone and fax numbers).
(b) Government contracting activity, and current address, Procuring Contracting Officer’s name, e-mail address, telephone and fax numbers.
(c) Government’s technical representative or
Contracting Officer’s Representative and current email address, telephone and fax numbers.
(d) Government contract administration activity and the Administrative Contracting Officer’s name, and current e-mail address, telephone and fax number.
(e) Government contract administration activity’s Pre-
Award Monitor’s name, and current e-mail address, telephone and fax numbers.
(f) Contract Number and, in the case of Indefinite
Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order Numbers.
(g) Contract Type (specific type such as Fixed-Price (FP), Cost Reimbursement (CR), Time & Material (T&M), etc.). In the case of Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.).
(h) Awarded price or cost.
(i) Final or projected final price or cost.
(j) Original delivery schedule, including dates of start and completion of work.
(k) Final or projected final, delivery schedule, including dates of start and completion of work.
(2) Section 2 – Performance. Offerors shall provide a specific narrative explanation of each contract listed in Section 1, Contract Description, describing the objectives achieved and detailing how the effort is relevant to the requirement of this RFP.
(a) For any contracts that did not or do not meet original schedule or technical performance requirements, provide a brief explanation of the reason(s) for the shortcomings and any corrective action(s) taken to avoid recurrence. The Offerors shall list each time the delivery schedule was revised and provide an explanation of why the revision was necessary. All Requests for Deviation and Requests for Waiver shall be addressed with respect to causes and corrective actions. The Offerors shall also provide a copy of any Cure Notices or Show Cause Letters received on each contract listed and a description of any corrective action implemented by the Offeror or proposed subcontractor. The Offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
(b) For all contracts, the Offeror shall provide data on all manufacturing warranty returns. Data shall delineate total number of warranty returns, number of Could Not Duplicate (CND), number of failures attributable to GFE component failures, and number and nature of failures attributable to the Offeror’s delivered product.
(3) Section 4 – New Corporate Entities. New corporate entities may submit data on prior contracts involving its offices and employees. However, in addition to the other requirements in this section, the Offeror shall discuss in detail the role performed by such persons in the prior contracts cited. Information shall be included in the files described in the sections above. Letters of Commitment shall be included in the proposal for these employees in order to be considered.
(4) Past Performance Questionnaire. For all contracts identified in Section 1, Contract Descriptions, a Past Performance Questionnaire shall be completed and submitted. The Offeror shall complete Part I of the Past Performance Questionnaire and e-mail the questionnaire to the Government contracting activity (where applicable) and to the technical representative responsible for the past or current contract. The POCs shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the Contracting Office no later than the proposal due date, to the Contract Specialist, Hilary Shaw at hilary.shaw.civ@mail.mil and Contracting Officer, Kelly Griffin at kelly.l.griffin11.civ@mail.mil. The Offeror shall e-mail to the Contracting Officer a list of all the POCs who were sent a questionnaire. The Government will receive this list no later than the proposal due date. The Offeror shall submit a POC List in a digital table format so that it can be opened by all Microsoft Word or Excel versions that are 2016 or later for use by the Government. This table shall include the following fields:
Solicitation Number; Company Name; Contract Number; Government Agency (where applicable); POC Last Name, First Name; POC Title; POC Telephone Number; POC E-mail Address; and the Date E-Mail was sent to POC.
(5) Submissions. Offerors submitting past performance information as
“subcontractors” are discouraged from providing prime contractor points of contact that have knowingly submitted a proposal for this requirement. Offerors shall provide and submit the prime contract number and all POCs (including Governmental agency POCs, where applicable) in lieu of subcontract numbers.
(6) Small Business Participation Past Performance. All Offerors shall submit information substantiating the Offerors’ past performance in complying with FAR 52.219-8, Utilization of Small Business Concerns, maximizing opportunities for U.S. small business subcontractors. Offerors shall also provide a statement indicating whether any negative information has been reported in the past six (6) years concerning the Offerors’ past compliance with FAR 52.219-8. If any such negative information has been reported, the Offeror may submit explanations or comments responding to such negative information. Offerors with no prior contracts containing FAR 52.219-8 shall certify the same.
(iv) VOLUME IV – SMALL BUSINESS PARTICIPATION (Factor 4). Offerors shall name this file as follows: C03_Abbreviated Company Name_SBA_SP_21R0033. This factor evaluates the Offeror’s approach to maximizing opportunities for small businesses in the proposed effort, both in terms of the percentage of overall contract value as well as actual work performed.
The Offeror shall demonstrate small business participation by addressing the following areas in its Small Business Participation Commitment Document (SBPCD), which will be incorporated into any resulting contract(s):
(a) Proposed Small Business Participation Plan in performance of the potential contract
(b) Commitment to Small Business (Under this section, the Offeror shall address payment procedures by including a written statement of its established procedures to ensure timely payments to small business subcontractors in accordance with FAR 52.219-8, Utilization of Small Business Concerns (for those contracts under which it was required within the past three (3) years from the closing date of this solicitation). If not required in any recent contracts, the Offeror shall so state.
Small Business Participation Plan:
1.) All Offerors shall provide the following Small Business Participation Commitment Document (SBPCD) requirements and substantiating documentation to demonstrate how you will meet these requirements. This required information will be used to evaluate the extent of your proposed participation/commitment to use U.S. small businesses in the performance of this acquisition (as small business prime Offerors or small business subcontractors) relative to Section M, Factor III, Small Business Participation. These SBPCD requirements will be incorporated into any resulting contract(s) as specified below.
1. The small business concerns (SBC) as defined in FAR Part 19 that are to be used in your proposed approach to satisfying the requirements of this solicitation for the entire performance period, including company name, business category(ies), description of products or services and NAICS code to be provided by each SBC and the nature of the commitment with the SBC (i.e., letter of commitment, joint ventures, mentor protégé agreements, others) (Table 2). Binding commitments shall become enforceable, contractual requirements. Use the table/format below in proposing this required information.
Table 2. SB Participation Commitment
Company Name
SB Category(ies)
(SB, WOSB, SDB,
HubZone, VOSB
SDVOSB)
Product(s)/Service(s) to be Provided, including type & variety of work
NAICS
Code
Nature of Commitment
The Government's small business participation objectives for this acquisition are in Table 3.
Table 3. SB Participation Commitment Objectives
Category Percent
Small Business 15.0%
Small Disadvantaged Business 3.0%
Women-Owned Small Business 3.6%
HUB Zone Small Business 1.3%
Veteran-Owned Small Business 5.0%
Service-Disabled Veteran-Owned Small Business 3.0%
Small business Offerors are advised that their own participation as a Prime counts towards the percentages set in this evaluation factor.
Small businesses are not required to subcontract to other small businesses in order to achieve the small business participation goals.
1. Offerors shall propose quantitative participation of SBCs (as small business prime Offerors and/or small business subcontractors) in terms of the value of the total acquisition (total contract value).
Offerors shall provide detailed explanations/ documentation to support quantitative small business participation. Binding commitments shall become enforceable, contractual requirements. Use the table/format below in proposing this required information. (Note: Section M, Factor III elements 4 and 5)
Proposed Total Contract Value < fill in base contract and all option years>
Minimum Quantitative Requirement (MQR) - Small Business Participation (Including Small Business prime Offeror’s participation)
Business Category Dollar Value % of Total Contract Value
Total Proposed Contract Value Prime Offeror
Total Small Business $ %
Small Disadvantaged Business $ %
Woman-Owned Small Business $ %
HUBZone Small Business $ %
Veteran-Owned Small Business $ %
Service-Disabled Veteran-Owned Small Business
All supporting documentation is excluded from the page count. Supporting documents will not be incorporated into any resulting contract.
For each category in which the Offeror’s SBPCD contains goals below those described above, the Offeror shall provide a detailed explanation as to why they are unable to meet the applicable goal.
(v) VOLUME V – QUALITY ASSURANCE (Factor 5): File shall be named as follows: C03_
Abbreviated Company Name_QA_SP_21R0033
Offerors shall organize Volume 5 – Quality Assurance into the following two (2) Sub-factors:
• Sub-factor 1: International Organization of Standardization (ISO) Quality Management System (QMS) Compliance
KEY POINT #1: Quality Manual
KEY POINT #2: ISO 9001:2015 compliance shown through the crosswalk
KEY POINT #3: Completeness of submission documents
ISO QMS Compliance:
Quality Manual (QM): The Offeror shall develop and maintain their own QM which outlines their plan for achieving customer satisfaction and which assures that the product meets contractual requirements. The Offeror shall submit their own QM with their proposal submission.
Their QM shall be compliant with the requirements of ISO 9001:2015 or higher Industry Standard for QMS and shall include:
• The scope of the QMS;
• All ISO 9001:2015 required documented procedures established for the QMS that enable compliance to the quality standard (to include at a minimum: 7.1.5 Monitoring and measuring resources;
7.4 Communication; 7.5 Documented Information; 8.1
Operational planning and control; 8.2 Requirements for Products and Services; 8.4 Control of externally provided processes, products and services; 8.5.1 Control of production and service provision; 8.5.2 Identification and
Traceability; 8.5.6 Control of Changes; 8.7 Control of Non-Conforming Outputs; 9.1.3 Analysis and evaluation; 9.2 Internal Audit; 10.2 Nonconformity and Corrective Action; and
10.3 Continual Improvement), all documented procedures shall be submitted in their entirety; and
• The description of the interaction between the processes of the quality management system.
Crosswalk Matrix: In conjunction with the QM, the Offeror shall provide a crosswalk matrix (Exhibit 3 – PM SPE Form 11) to further demonstrate how their documented procedures map to the ISO 9001:2015 elements and, where there are no written procedures, a brief explanation of how they meet the ISO 9001:2015 standard requirements shall be provided
• Sub-factor 2: Subcontractor and Supplier Management Plan
(SMP)
• KEY POINT #1: Plan completeness to requirements
• KEY POINT #2: Completeness of submission documents
Sub-factor 2 - Subcontractor and Supplier Management Plan (SMP):
The Offeror shall develop and maintain their own SMP and submit their SMP with their proposal submission. Their SMP shall specifically state material, sub-component, component, and product acceptance requirements (if not already specified in the contract or performance specification) for Subcontractors and Suppliers and emphasis shall be placed on product verification at the Subcontractor and Supplier level in order to identify and correct defects at the earliest point of inspection and test. All procedures describing the activities needed to implement the SMP shall be submitted in their entirety.
The SMP shall include:
• Quality control and technical requirements;
• Subcontractor and Supplier Selection Criteria;
• Rating system;
• Subcontractor and Supplier Qualification Standards;
• Subcontractor and Supplier ISO 9001:2015 compliance verification process and results
• Identify key features, characteristics, and performance requirements that must be verified at the component acceptance test level;
• Identify subassembly manufacturing or processes to be performed by any subcontractor and all suppliers (functions only, i.e., ballistics, material purchase, cut, sewn, inspection and performance verification testing of ballistics, etc.);
• Management and Surveillance Plan for the duration of the contract;
• Customer contract requirements flow-down;
• Flow chart showing the supply chain (all material suppliers, component suppliers, Subcontractors, assemblies, etc. must be specifically identified on the flow chart); and
• Letter of intent for all subcontractors and suppliers for every component and material used the make the Shoot Pack.
(vi) VOLUME VI – SOLICITATIONS, OFFER AND AWARD DOCUMENTS
AND
CERTIFICATIONS/REPRESENTATIONS
Certifications and Representations – Each Offeror shall complete (fill-in and sign) the solicitation sections indicated below using the file (without further modification to the file) provided with the RFP. An authorized official of the firm shall sign the Standard Form (SF) 33 and all certifications requiring original signature. An Acrobat PDF file shall be created to capture the signatures for submission.
Section A –SF 33, Solicitation, Offer and Award, and any applicable Amendments
Section K – Representations, Certification and Other Statements of Offerors
Solicitations, Offer and Award Documents and Certifications/Representations shall not be addressed separately from that submitted in VOLUME VI – SOLICITATIONS, OFFER AND
AWARD DOCUMENTS AND CERTIFICATIONS /REPRESENTATIONS.
(End of Summary of Changes)