CJAG Demo Questions and Answers as submitted via RFI.docx

DOCX document 14 KB Posted

Attached to
Camp James A. Garfield (CJAG) Demolition Project Invitation for Bid (IFB)
Solicitation number
W91364-22-R-0002
Issued by

About this file

This document outlines requirements for the Camp James A. Garfield (CJAG) Demolition Project solicitation. The Ohio Army National Guard requires abatement and demolition services for eight buildings on the CJAG site, with pricing to be provided for each individual building and combination of buildings. This is a set-aside for Service-Disabled Veteran-Owned Small Businesses. A site visit will be held on August 19th, with all questions due by August 23rd and bids to be submitted in person by September 8th. The selected contractor will be required to complete the project in accordance with Camp James A. Garfield Department of Public Works standards and specifications.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CJAG Demo Questions and Answers as submitted via RFI

Are on site fire hydrants available for use to either connect directly to or connect to fill water trucks? We will need water on site or fugitive dust control. Requesting use of hydrants for this purpose.

Per Section 3.1.8 “The contractor shall bring water in for use on the Project (from a Municipal source)”. The Contractor cannot use any hydrants on the base.

3.1.4: Salvage items-locations for delivery and items for retention to be determined and disseminated prior to the bid?

OHARNG does not anticipate any items for retention on these buildings.

3.1.5: Asbestos: Can we be provided a detailed copy of all the surveys RE where ACM samples were conducted and quantity of results?

See demo analysis-and surveys provided in addendum 3.1.6: Is water to be assumed contaminated, to provide accurate cost of disposal?

See survey analysis for SD-03.

3.1.8, 3.1.9, and 3.1.11 - all give conflicting responses regarding the removal and crushing of clean concrete. Is an on-site location for crushing available? Can clean block/concrete be repurposed as fill at a size of 3"?

Contractor to assume all concrete is to be removed from site. No block/concrete can be repurposed as fill and must be removed from the site.

1.2.1 and 3.1.11- conflicting accounts of removal of pavement, concrete pads, and appurtenances. 1.2.1 states 10' radius, 3.1.11 states in entirety?

Removal of pavement, concrete pads and appurtenances are to be a part of and congruent with the building area itself and not a permanent feature like an existing Roadway. 10' is a minimum expected for a contractor work area around the building.

3.1.10- can utilities be cut and capped at main and at structure, then left in place? If no, can drawings/plans displaying utilities be provided?

Utilities to be removed with the 10' minimum of the structures. However, any power if installed shall be removed to the closest disconnection point (i.e. Transformer-disconnect) available.

Can the government provide a cost estimate for this project?

No cost estimate will be available until opening of the Bids.

1. Building 28-18 - square footage of windows with ACM caulking and number of doors with ACM caulking; number and length of fluorescent bulbs, number of PCB and/or non-PCB ballast; and number of mercury thermostats?

See surveys and analysis provided in addendum.

2. Building A0001 - quantity of ACM thermal system insulation (lf or sf), quantity of ACM linoleum flooring, quantity of ACM transite panels, and estimated volume of floor sweep; number and length of fluorescent bulbs, number of PCB and/or non-PCB ballast?

See surveys and analysis provided in addendum.

3. Building A0004 - quantity of ACM transite (signs) and quantity of exterior ACM mudding and quantity of painted wood door frames to be disposed of as hazardous waste?

See surveys and analysis provided in addendum.

4. Building A009 - quantity of ACM window glazing, quantity of exterior ACM caulking, quantity of ACM transite (signs, over doors, boiler room and restrooms); quantity of ACM boiler gaskets, quantity of ACM flexible ducts, quantity of ACM boiler breeching and quantity of ACM mudding in boiler; quantity of wood exterior doors and wood exterior window framing to be disposed of as hazardous waste; number and length of fluorescent bulbs, number of ballast PCB and non-PCB ballast; and number of mercury thermostats?

See surveys and analysis provided in addendum.

5. Building SD003 - quantity of ACM window glazing and ACM exterior caulking and quantity of water to be included in the bid for disposal?

See surveys and analysis provided in addendum.

6. Building U-14 - quantity of ACM window glazing, quantity of ACM wall caulking; quantity of ACM flexible ductwork; quantity of ACM transite; number and length of fluorescent bulbs, number of ballast PCB and non-PCB ballast; and number of mercury thermostats and volume of floor sweep?

See surveys and analysis provided in addendum.