W91364-19-B-8002_Addendum_01.pdf
PDF 158 KB Posted
- Attached to
- ADAL Simulator Bldg. Federal contract opportunity
- Solicitation number
- W9136419B8002
About this file
response to RFI
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SIM_Abstract_of_Offers.pdf | ||
| Sim_Bid_Opening_sign-in.pdf | ||
| 2.Attachment_2_-_Revised_Detail_2_-_Sheet_EY501.pdf | ||
| 2.Attachment_1_-_ADVANTOR_ACS_Panel_Detail_-_Sheet_EY501.pdf | ||
| W9136419B80020001_ADAL_Sim_Amendment_01.pdf | ||
| W91364-19-B-8002_Addendum_02_RFIs.pdf | ||
| Attmt_-_TTL_Geotech_Report_ADAL_Sim__7-26-18.pdf | ||
| Sim_Site_visit_2_signin.pdf | ||
| Pre-Bid_Conference_SIM-19B8002v2.pptx | PPTX presentation | |
| PreBid_SIM_signin.pdf | ||
| Drawings_B3_Add_Alt_B158_Simulator_1Feb19.pdf | ||
| W9136419B8002-ADAL_SIM.pdf | ||
| Specification_B3_Add_Alt_B158_Simulator_1Feb19.pdf | ||
| RFI_template-SIM.doc | DOC document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 01
W91364-19-B-8002 FOR ADAL Simulator
AT 180TH FIGHTER WING
Current DOL-Wage Determination is WD-OH190088-Mod 01 dated 2-15-19
See below response to Request For Information (RFI’s) thru 1 March
1-Mar-19
WYTD162018
Item Date Received Bidder Name Reference: Print / Page Number
Discipline RFI Assigned to Evaluation A/E Response Date Returned to CTANG
1 (NOT USED) (NOT USED)
2 22-Feb-19 Blue Spader Project Solicitation Documents
Project Management
Solicitation for this project indicates funds are not presently available but anticipates funding will become available before September 30, 2019. To prepare our bids properly the contractors need to know if we are to assume 9/30/19 a start date and if we are expected to work through the winter months to achieve the 180 substantial completion milestone or if we will be given the NTP in the spring allowing us to construct this project without winter conditions.
Toledo ANG Base CE Response
We have advance Contracting Authority for this project.
This project is Programmed for Q4FY19 funding, and we are anticipating that funds will be provided shortly after bid closing, But Not later than requested Bid acceptance period.
22-Feb-19
3 22-Feb-19 Dawn Incorporated
Specs - 055213-1, 2.6, A.
Architectural Instructs us to hot dip galvanize the exterior railings. Sheet AE502 Detail 3 calls for the railing to be painted. What is the governments preference? FSB -
Estrada Response Hot dip galvanize per Specification.
1-Mar-19
4 26-Feb-19 K&T Installation
1. DOL website shows Dav is Bacon wage rates as of 2-15-19. Are these the rates to be included in our proposal? Toledo ANG Base CE Response
Most current DOL Wage Rates (Davis Bacon) will be incorporated No Later Than 5-days before Closing. 26-Feb-19
5 26-Feb-19 K&T Specification
01 9113 Project
Management
2. Specification 01 9113 1.3 appears to indicate that we should include an allowance for commissioning, but no amount is given. Is an allowance for commissioning to be included in our proposal? If so, what amount should be included?
BASE CE Response
The contractor shall provide as part of their bid proposal all necessary labor, materials and equipment to demonstrate to the Government's Commissioning Agent that all HVAC equipment and systems installed meet the performance criteria in the contract documents. The commissioning agent shall also verify proper operation of the reinstalled PV array, water heaters and any lighting controls. Provide any contractor required documents and attend meetings as needed to complete the commissioning process.
5-Mar-19
6 26-Feb-19 K&T Specification
31 2000 Project
Management
3. Specification 31 2000 1.3 references specification 01 2200 Unit Prices and 01 2100 Allowances but these specifications are not included in the bid documents. Are there unit price and/or allowance requirements for earth moving?
FSB -
Niggemeyer /
Fanelli Response
There are no Unit Prices or Allowances associated with Earth Moving.
Please disregard.
1-Mar-19
7 26-Feb-19 K&T Specification
09 6900 Interior Design
4. Specification 09 6900 2.5A calls for VCT covering on the raised access floor panels. According to the manufacturer, high pressure laminate would be a much more durable alternative and easier to maintain.
Is HPL an acceptable alternative to VCT? (Data sheet attached)
FSB -
Huddleston Response
Specification 09 0690 calls for High Pressure Laminate (HPL) on the raised access flooring. HPL is acceptable.
1-Mar-19
8 26-Feb-19 K&T Sheet AE302 Architectural
5. Note 11 on AE302 references detail 6/AE131 but there is no detail 6 on AE131.
FSB -
Estrada Response
Note 11 should refer to detail 5/AE502. This detail is also referred to on Note 7 on sheet AE131. 1-Mar-19
9 26-Feb-19 K&T Architectural
6. What is the existing roof construction type in the UTD Room and Rehearsal Room?
FSB -
Estrada Response
According to the record drawings: 60 mil single ply EPDM roofing membrane on 4 inch rigid insulation on metal deck. It will ultimately be the contractors responsibility to field verify roof construction.
1-Mar-19
10 26-Feb-19 K&T Architectural 7. Is the brick and/or the CMU to be toothed in at the window infills? FSB - Estrada
Response Correct, toothed in at infills. 1-Mar-19
Ohio Air National Guard
Toledo ANG Base, Toledo Express Airport, OH
BIDDER INQUIRIES
ADAL B158 for Flight Simulator
Item Date Received Bidder Name Reference: Print / Page Number
Discipline RFI Assigned to Evaluation A/E Response Date Returned to CTANG
Ohio Air National Guard
Toledo ANG Base, Toledo Express Airport, OH
BIDDER INQUIRIES
ADAL B158 for Flight Simulator
11 27-Feb-19 Massillon Specification
07 2726 Architectural
Per Specification Section 07 2726, several references are made in regards to the Air Barrier Membrane “When tested in accordance to ASTM Standards.” No specific specifications exist on Air Barrier Testing. Will a Building Envelope Air Barrier Test be required by a Certified Air Barrier Testing Agency, and if so, will the results be a required LEED/Closeout submittal?
FSB -
Estrada /
Smith Response
No Building Envelope Air Barrier Testing is required in this project.
Please disregard.
1-Mar-19
12 28-Feb-19 JCI M-803 Mechanical
1. Drawing M-803 – Floor Mounted CRAC Control
a. BAS shall monitor space temperature sensor TS-1 and space humidity
HS-1.
Please confirm that TS-1 and HS-1 will be furnished by the CRAC manufacture for field installation/wiring by the control contractor.
b. Please provide a location for TS-1 and HS-1
FSB -
Doolittle Response
TS-01 and HS-01 shall be manufacturer provided, built-in to the indoor unit.
1-Mar-19
13 28-Feb-19 JCI M-803, MH101 Mechanical
2. Drawing M-803, MH101 and Section 23 0923.18
a. Who furnishes the leak detection sensors and the leak detector control panel as noted on drawing MH101, Sheet Keynote 12.
b. Please provide a specification for the leak detector control panel/LDS controller as shown on drawing M-803
FSB -
Doolittle Response
Leak detection control panel spec listed in Spec Division 230923.18.
1-Mar-19
14 28-Feb-19 JCI MH101 Mechanical
3. Drawing MH101, Security Office 104
a. What is the BAC Control Panel that is located in Security Office 104?
b. Who furnishes and installs the BAC Control Panel?
c. If the control contractor is to furnish the panel, please provide a specification for a BAC Control Panel.
FSB -
Doolittle Response
BAC Control panel spec listed in Spec Division 23 0900 -2.3B.
1-Mar-19
15 28-Feb-19 Pinnacle
AE131
Spec Section 075323
Architectural
Pinnacle Construction’s roofing subcontractor would like to submit an alternative EPDM roofing manufacturer to the manufacturers referenced in the specifications. This alternative manufacturer is Durolast. The attached PDF contains the specifications and information on the proposed materials. Our subcontractor has worked on this alternative material proposal and believes it will meet the required specification for the project.
Per the specification number 07 5323, section 2.2 A1, the two manufacturers referenced are:
a.Firestone Building Products b.Johns Manv ille; a Berkshire Hathaway company
Will the proposed Durolast brand be an acceptable alternative material and product for this project?
FSB -
Estrada Response
This substitution is not acceptable. A 60 mil PVC roofing membrane (Durolast) is not equivalent to a 90 mil EPDM as specified.
1-Mar-19
16 1-Mar-19 K&T-2 AE202 Architectural
1. What is keynote 20 on AE202? FSB -
Estrada Response Keynote 20 is "CMU control joint, Beyond."
1-Mar-19
17 1-Mar-19 K&T-2 AE601 Architectural
2. Should frame type for door 110A be D4? FSB -
Estrada Response Yes. Frame Type for Door 110A is D4.
Item Date Received Bidder Name Reference: Print / Page Number
Discipline RFI Assigned to Evaluation A/E Response Date Returned to CTANG
Ohio Air National Guard
Toledo ANG Base, Toledo Express Airport, OH
BIDDER INQUIRIES
ADAL B158 for Flight Simulator
18 1-Mar-19 K&T-2 Mechanical
3. Is Stulz an acceptable alternate for the computer room A/C system?
(Product data attached)
FSB -
Doolittle Response
No. Size restraints of this project will limit equipment choices.
1-Mar-19
19 1-Mar-19 K&T-2 Project
Management
4. Please confirm geotechnical testing is by owner as stated in 31 2000 3.19.
BASE CE Response
See attached Geotechnical Report. The contractor is responsible for all geotechnical testing that is required. Delete the word "owner" from all references in the specification and change to "Contractor". The contractor shall provide all required soils testing and inspections. Submit all tests and inspection reports to the government and the governments engineer for review. The government reserves the right to perform additional testing under a separate contract as needed.
5-Mar-19
20 1-Mar-19 K&T-2 Project
Management
5. There is no specification for access controls. Please confirm whether access controls and CCTV, to be performed by Advantor, is in contractor’s scope or by the government.
BASE CE Response
All Intrusion Detection System (IDS) and Access Control System (ACS) equipment and components shall be supplied to the contractor by ADVANTOR. The contractor shall provide and install hardware and software for ACS and IDS that meets the requirements of Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities, VERSION 1.4, IC Tech Spec – for ICD/ICS 705. Additionally, the contractor shall provide equipment that is compatible and operates with the existing base IDS and ACS. The contractor shall provide all conduit, cabling, coordination and testing with ADVANTOR as part of the contracted work to provide the government a complete and usable ACS/IDS.
The camera and monitor are also part of the contractor's work. The camera and monitor do not need to be supplied by Advantor. The CCTV materials & equipment and the installation must meet the requirements of the Tech Spec - for ICD/ICS 705.