B08.03 W913T2Q0031- Amendment 0002.docx
DOCX document 38 KB Posted
- Attached to
- Controls System Test Laboratory (CSTL) Federal contract opportunity
- Solicitation number
- W9132T25Q0031
About this file
This document is an Amendment 0002 to a Performance Work Statement (PWS) for the U.S. Army Engineer Research and Development Center's (ERDC) Control System Test Laboratory (CSTL) contract. The solicitation seeks technical support for installing, configuring, and integrating new technologies into the CSTL, specifically focusing on BACnet and BACnet SC technologies. The contractor will participate in three one-week installation sessions to integrate up to 30 devices and eight subsequent troubleshooting/integration sessions, with detailed documentation required after each session.
Key contract details include a period of performance of 410 calendar days starting from the award date, with anticipated session timeframes from January to December 2026. The contract requires on-site travel to ERDC-CERL for eleven sessions, involves non-personal services, and has no cybersecurity requirements. Deliverables include meeting minutes, installation summaries, and integration session reports. The solicitation is issued by the Department of the Army Corps of Engineers, with offers to be submitted to CERL-CT-Quotes@usace.army.mil, and the response date has been extended to 05-Nov-2025 at 11:59 AM.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08.03 Amendment 0002 Q&A.docx | DOCX document | |
| B08.03 Amendment 2 Q&A Attachment - Draft components list.xlsx | XLSX spreadsheet | |
| B08.03 W913T2Q0031- Amendment 0001.pdf | ||
| Questions and Answers 1-7 MS.docx | DOCX document | |
| Questions and Answers 1-4 MS.docx | DOCX document | |
| B08.02 W9132T25Q0031.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9132T25Q0031
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 23-Oct-2025 11:59 AM to 05-Nov-2025 11:59 AM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
Support to the Controls System Test Laboratory (CSTL)
1. INTRODUCTION: ERDC has several ongoing and upcoming research projects which have a need to evaluate Facility Related Control Systems (FRCS) and their interaction with the growing number of installation microgrids in an operational laboratory environment.
Department of Defense (DoD) installations have a growing number of control systems. There is potential for the coordination or integration of these systems to greatly improve situational awareness and operational management. Many technologies claim to provide part or all of this capability. Testing these devices in a functional network architecture will highlight any compatibility issues and/or cybersecurity concerns with other existing devices and equipment. Testing this capability in an integrated environment is important because it would highlight issues prior to deployment.
ERDC-CERL recently stood up the Control System Test Lab (CSTL) to address the FRCS testing gap, but additional system components are needed to provide the full range of testing services required to meet new and emerging Army control system requirements and goals. In line with this, CERL is using the CSTL to perform testing to support a demonstration project evaluating Managed BACnet. The contract is for the installation and integration of components into the CSTL. Activities beyond those required to install and integrate components into the CSTL as indicated are not within the scope of this contract. Activities outside the scope of this contract include cybersecurity engineering/configuration, cybersecurity testing, and functional product testing. There are no cybersecurity requirements associated with this contract.
2. OBJECTIVE: Support the execution of a project by supporting the installation, configuration, and integration of new technologies into the CSTL for future use by ERDC-CERL. Regarding DFARS Clauses 252.204-7012 & 252.204-7020, there is not anticipated to be any Controlled Unclassified Information (CUI) involved in the performance of this contract.
3. MAJOR REQUIREMENTS: In order to accomplish the above objective, the Contractor must complete the following tasks:
a. Task 1. New Equipment Installation Support.
Provide support for the installation, configuration, and integration of new technologies into the Control System Test Lab by completing the following:
i. Participate in three (3) major install/integration sessions lasting one (1) week each, by serving as expert controls technicians in the CSLT for the installation and configuration of BACnet and BACnet SC technologies and integration of these technologies to the CSTL font-ends. The number of devices to be installed and integrated is estimated to be 24 and will not exceed 30.
ii. At the conclusion of each integration session, provide a brief written summary (maximum 5 pages) of the devices integrated, the front-end to which they are integrated, the network address(es) of the devices, and any issues encountered integrating those components.
b. Task 2. Configuration and Integration Troubleshooting Support.
Following the integration and configuration described in Task 1, ERDC CERL will begin using and reconfiguring as needed the new components and integrating additional components. Provide support for the reconfiguration and integration by completing the following:
i. Participate in eight (8) minor integration/troubleshooting sessions lasting up to four (4) hours each. Each session may be the integration of a single components or troubleshooting multiple components that are on a common front-end. The purpose of each session will be determined by the needs of the project at the time the sessions occur.
ii. At the conclusion of each session, provide a maximum one (1) page written summary detailing the objective of the session and the outcome.
4. GOVERNMENT-FURNISHED SUPPORT/INFORMATION/PROPERTY:
Access to the physical CSTL building must be coordinated with ERDC-CERL. All technologies to be installed and integrated, relevant documentation, installation hardware and equipment, and necessary software tools will be provided by ERDC-CERL.
5. CONTRACTING OFFICER’S REPRESENTATIVE (COR): The ERDC CERL COR for this contract will be appointed in accordance with DFARS 252.201-7000, and a copy of the designation letter will be provided to the Contractor. Although other Government personnel may clarify technical points or supply relevant information to the Contractor regarding this contract, only a Contracting Officer has the authority to revise any requirements in these specifications, including those resulting from verbal clarification. Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed with the change and shall immediately notify the Contracting Officer.
6. NON-PERSONAL SERVICES: The Government and the Contractor understand and agree that the services to be delivered under this contract by the Contractor to the Government are non-personal services and the parties recognize and agree that no employer-employee or master-servant relationship exists or will exist under the contract between the Government and the Contractor’s employees.
7. MEETINGS AND REVIEWS: The contractor shall attend the following:
a. General:
1. Unless otherwise indicated, all meetings will be held on-site.
2. Any virtual meetings must be conducted via a web meeting platform which enables screen sharing. Contractor may choose whether to provide the web meeting platform or to use the CERL provided platform (Teams).
3. Unless specific dates and times are provided, meetings must be scheduled in coordination with CERL to ensure they occur at a time which allows participation by the relevant Government personnel.
b. Kick Off Meeting (Virtual, 1 hour): The contractor must participate in a one-hour technical virtual orientation meeting within two (2) weeks of award. This will be a meeting to discuss general technical requirements of contract; including technical requirements, deliverables schedule, and contractor clarifications. Within one (1) week of the kick-off meeting, the contractor must submit written minutes from the meeting to the COR in a Microsoft Word (.docx) or Adobe pdf format.
c. Task-Specific Meetings (On-Site): Meetings will be scheduled by CERL in coordination with the contractor and other meeting attendees.
1. (Task 1) Three one-hour session coordination meetings, one per installation and integration session required in Task 1. These meetings will cover the devices and systems being worked on and the work to be performed and will take place during the first hour of each Task 1 session as defined in 3. a.
a. Task 1 – Session 1 Coordination Meeting
b. Task 1 – Session 2 Coordination Meeting
c. Task 1 – Session 3 Coordination Meeting
2. (Task 2) Up to eight thirty-minute session coordination meetings, one per integration/testing/troubleshooting session required in Task 2. These meetings will cover the devices and systems being worked on, the issue to be addressed, and the work to be performed and will take place during the first thirty minutes of each Task 2 session as defined in 3. b.
a. Task 2 – Session 1 Coordination Meeting
b. Task 2 – Session 2 Coordination Meeting
c. Task 2 – Session 3 Coordination Meeting
d. Task 2 – Session 4 Coordination Meeting
e. Task 2 – Session 5 Coordination Meeting
f. Task 2 – Session 6 Coordination Meeting
g. Task 2 – Session 7 Coordination Meeting
h. Task 2 – Session 8 Coordination Meeting
8. TRAVEL REQUIREMENTS: Travel from contractor offices to ERDC-CERL for eleven (11) on-site sessions (including the coordination meeting at the beginning of each session).
9. SUMMARYS/DELIVERABLES: Submit the following reports/deliverables to the ERDC-CERL COR, or to the required reporting system specified, within the time specified:
a. Kick-Off Meeting Minutes (Summary): Within one (1) week of the kick-off meeting, submit written minutes from the meeting to the COR in a Microsoft Word (.docx) or Adobe pdf format.
b. Technical Deliverables: Deliverables must be provided as indicated, in the formats shown in parenthesis after the deliverable name.
Deliverables for Base Tasks (Tasks 1 & 2)
iii. (Task 1) Installation and Integration Session Summaries: provide a written summary (maximum 5 pages) for each installation and integration session of the devices integrated, the front-end to which they are integrated, the network address(es) of the devices, and any issues encountered integrating those components. No specific summary format is required.
a. Task 1 – Session Summary 1 (.pdf or .docx)
b. Task 1 – Session Summary 2 (.pdf or .docx)
c. Task 1 – Session Summary 3 (.pdf or .docx)
ii. (Task 2) Integration/Testing/Troubleshooting Summaries: provide a written summary (maximum 1 page) for each integration/troubleshooting session summarizing the objectives of their respective session and the outcome of that session.
a. Task 2 – Session Summary 1 (.pdf or .docx)
b. Task 2 – Session Summary 2 (.pdf or .docx)
c. Task 2 – Session Summary 3 (.pdf or .docx)
d. Task 2 – Session Summary 4 (.pdf or .docx)
e. Task 2 – Session Summary 5 (.pdf or .docx)
f. Task 2 – Session Summary 6 (.pdf or .docx)
g. Task 2 – Session Summary 7 (.pdf or .docx)
h. Task 2 – Session Summary 8 (.pdf or .docx)
10. SCHEDULE: Approximated timeframes for the required sessions are shown in the table below. Session dates can be adjusted according to the associated project schedule and government and contractor availability. Summary due dates will shift accordingly.
TASK 1 – Installation and Integration Sessions
| Task 1 – Session 1 |
| January 2026 |
| Task 1 – Session 1 Coordination Meeting |
| conducted at the start of Session 1 |
| Task 1 – Session Summary 1 |
| due 4 weeks after Session 1 |
| Task 1 – Session 2 |
| February 2026 |
| Task 1 – Session 2 Coordination Meeting |
| conducted at the start of Session 2 |
| Task 1 – Session Summary 2 |
| due 4 weeks after Session 2 |
| Task 1 – Session 3 |
| March 2026 |
| Task 1 – Session 3 Coordination Meeting |
| conducted at the start of Session 3 |
| Task 1 – Session Summary 3 |
| due 4 weeks after Session 3 |
TASK 2 - Integration/Troubleshooting Sessions
| Task 2 – Session 1-8 |
| approx. monthly from April-December 2026 |
| Task 2 – Session 1-8 Coordination Meeting |
| conducted at the start of respective Session |
| Task 2 – Session Summary 1-8 |
| due 2 weeks after respective Session |
11. ANTI-TERRORISM/OPERATIONAL SECURITY
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
12. PERIOD OF SERVICE: The period of performance for this contract will begin on the date of award and end 410 calendar days after award.
Performance Requirement Summary
| Deliverable or Other item surveilled |
| Reference Number |
| Standards |
| Maximum |
Allowable Degree of Deviation Method of Surveillance
Remedy for Non- Conformance
| Kick-Off Meeting Minutes (Summary) |
| PWS para 9.a |
| · Submitted by the required deadline |
| 0% |
| Review by COR |
| Re-performance |
| Technical Deliverables |
| PWS para 9.b |
| · Submitted by the required deadline |
· Summary contains the information required by the PWS (devices integrated, systems integrated to, and any issues encountered integrating those components)
| 0% |
| Review by COR |
| Re-performance |
(End of Summary of Changes) image1.wmf