This document is an Amendment to Solicitation W912WJ24B0012 for the Natick Soldier System Center - Building 15 South Wing Barracks Replacement project.
The amendment addresses several RFIs related to the project, including: clarifying the acceptable concrete density specification, confirming the Contractor Superintendent can also serve as the Quality Control Manager, providing details on utility rates and access, and addressing questions about the photovoltaic system requirements and accommodations. The amendment confirms that the allocated roof area can support the 15 kW photovoltaic system, and that the roof structure and lightning protection system can accommodate the additional load. The amendment also extends the offer receipt date but does not change any other solicitation terms. The solicitation is being issued by the U.S. Army Corps of Engineers, New England District, for a construction project at the Natick Soldier Systems Center in Natick, MA.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This Amendment is to release RFIs. All other aspects remanin the same.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jul-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24B0012
X 9B. DATED (SEE ITEM 11)
12-Jun-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jul-2024
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ24B0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
RFI 0005
1. Per composite metal deck table on sheet S-515 lite weight concrete at 110 PCF is being called out. Typical light weight in this market due to the availabilty and type of light weight aggregrate is 115-117 +/- PCF.
Please advise.
Per Specification 03 30 00, Section 2.5.1 allows for a max density of 115pcf. 115pcf density is acceptable.
2. As a follow-up to Questions and Responses 2, 3, and 4 in Amendment 0003, please confirm that the specifications allow the contractor’s Superintendent to also serve as the Quality Control Manager.
See Specification section 01 45 00.00 10 Quality Control , 3.4.2 CQC System Manager
3. Section 01 50 00 page 10 requires “Contractor is responsible for all coordination and payment of temporary utilities required for construction.” What are the rates for use of water, electric, natural gas, and steam (if available) at the Natick SSC?
There is no way for USASSC Natick or the contractor to install a new sub-meter for the water. For that reason, the contractor will use the water free (See response to question 5). The contractor is required to contact the USASSC Natick environment dept. to explain how they are going to mitigate the water consumption/waste/disposal.
The rate for the electrical is an approximated value as a reference only, the rates can change at any time:
FY 22 $0.213817 Kw/Hr.
FY 23 $0.212714 Kw/Hr.
The rate for the natural gas is an approximated value as a reference only, the rates can change at any time:
FY 22 $1.341335 Therms.
FY 23 $1.366518 Therms.
Current rates for 2024 Electric and Natural Gas are not available.
No Steam is available.
4. Please confirm that the response provided to Question 3 in Amendment 0002 indicates that the existing portion of Building 15 to remain can be tapped for temporary electrical service for the contractor’s trailer, resident engineer’s trailer, and project site for the duration of the project.
Confirmed, the contractor is allowed to tap to the existing electrical service in Bldg. 15. See response to question 3 about sub-meter.
5. Section 01 50 00 page 14 requires water and sanitary for the resident engineer’s trailer, from/to utility mains near the site. Is this a firm requirement or is a temporary toilet and source of water acceptable?"
There is no charge for the water. The contractor will be allowed to tap into NSSC water service and the contractor shall provide the equipment/materials to tap into the facility. The contractor shall contact USASSC environment for approval and previous equipment installation. NO wet trailers are allowed. The contractor shall provide and coordinate with US Army SSC Natick environment dept. about water waste and disposal. Portable/temporary toilet is acceptable. The contractor shall coordinate with USASSC DPW
W912WJ24B0012
and the installation for the portable toilets, dry trailer, equipment storage, or any other environmental related issue to prevent catastrophic environmental issues.
6. Please revisit Question and Response 8 in Amendment 0002. The issue is the size of the allocated roof area on drawing EP-103. It will not accommodate enough panels to provide 15 KW. Revising the question: Can other areas of the roof, including to the north of column line J and/or above the stair towers be utilized to provide the full 15 KW?
From the previous response provided in Amendment 0002 Response 8, the allocated roof area can accomodate enough PV panels to achieve the 15Kw. However, should the bidders still question whether the 15Kw can be acheived in the area provided, other areas of the roof may be utilized upon approval from NSSC and provided that clearances are maintained from other rooftop systems (i.e. mechanical equipment).
7. Please confirm that the roof structure and lightning protection system can both accommodate the optional photovoltaic array.
Confirmed, the roof structure has been designed to accomodate the added load of the photovoltaic system.
Bidders should refer to sheet EG 103, keyed note number four for the lightning protection option for the PV system.